Critical Path Method (CPM)

Critical Path Method (CPM). David S.W. Lai Sept 9, 2013. Example. from Shtub , Bard, Globerson , Project Management, 2 nd Edition, Pearson, 2005. Activity-on-Node Network. 30. 3. 5. 0. 8. A. D. G. END. K. 15. 7. 2. 0. B. E. H. Start. 10. J. 25. 1. 4. C. F. I.

finn
Download Presentation

Critical Path Method (CPM)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Critical Path Method (CPM) David S.W. Lai Sept 9, 2013

  2. Example from Shtub, Bard, Globerson, Project Management, 2nd Edition, Pearson, 2005.

  3. Activity-on-Node Network 30 3 5 0 8 A D G END K 15 7 2 0 B E H Start 10 J 25 1 4 C F I Notations ES: Earliest Start LS: Latest Start TS: Total Slack EF: Earliest Finish LF: Latest Finish FS: Free Slack

  4. Earliest Start and Earliest Finish 30 3 5 0 8 A D G END K 15 7 2 0 B E H Start 10 J 25 1 4 C F I Notations ES: Earliest Start LS: Latest Start TS: Total Slack EF: Earliest Finish LF: Latest Finish FS: Free Slack

  5. Latest Start and Latest Finish 30 3 5 0 8 A D G END K 15 7 2 0 B E H Start 10 J 25 1 4 C F I Notations ES: Earliest Start LS: Latest Start TS: Total Slack EF: Earliest Finish LF: Latest Finish FS: Free Slack

  6. TS = 8 FS = 8 TS = 1 FS = 0 TS = 1 FS = 0 TS = 0 FS = 0 TS = 0 FS = 0 30 3 5 0 8 A D G TS = 0 FS = 0 END K 15 7 2 TS = 16 FS = 0 TS = 0 FS = 0 TS = 1 FS = 1 0 B E H Start 10 J 25 1 4 C F I TS = 0 FS = 0 TS = 16 FS = 16 TS = 0 FS = 0 TS = 0 FS = 0 Notations ES: Earliest Start LS: Latest Start TS: Total Slack EF: Earliest Finish LF: Latest Finish FS: Free Slack

  7. TS = 8 FS = 8 TS = 1 FS = 0 TS = 1 FS = 0 TS = 0 FS = 0 TS = 0 FS = 0 30 3 5 0 8 A D G TS = 0 FS = 0 END K 15 7 2 TS = 16 FS = 0 TS = 0 FS = 0 TS = 1 FS = 1 0 Critical Path B E H Start 10 J 25 1 4 C F I TS = 0 FS = 0 TS = 16 FS = 16 TS = 0 FS = 0 TS = 0 FS = 0 Notations ES: Earliest Start LS: Latest Start TS: Total Slack EF: Earliest Finish LF: Latest Finish FS: Free Slack

  8. Exercise Question: Determine the critical path and the slacks. Interpret their meanings. To check your solution: The critical path is (C, I). The project duration is 14 days. from Shtub, Bard, Globerson, Project Management, 1st Edition, Prentice-Hall, 1994.