An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Balmoral Dam RemovalAdministrative Takings • Town Meeting 2012 • Eminent Domain: Ownership of Balmoral Dam Structure • Temporary Construction Easement • Release of Damages (No Cost to Town)

  2. Project Partners • Town of Andover • Center for Ecosystem Restoration/EII • Commonwealth of Massachusetts • Division of Ecological Restoration • Division of Fish & Wildlife • Division of Marine Fisheries • Atria Senior Living (owner of Marland Pl. Dam) • Shawsheen River Watershed Assn. • American Rivers • U.S. Fish & Wildlife Service • National Oceanic & Atmospheric Administration • Massachusetts Environmental Trust • Coastal America Foundation

  3. Balmoral Dam & Downstream Breached Dam

  4. Balmoral Dam Existing Conditions

  5. Status of Balmoral Dam • Built by American Woolen circa 1920 • Acquired by Textron 1955 • Purchased by Deering Milliken (now Milliken & Co. of SC) 1963 • Condo owns floodwall and half of riverbed; Town owns opposite side

  6. Proposed Town Role in Dam Removal • Two Administrative Takings • Permanent Taking of Balmoral Dam • Temporary Taking of Construction Easement • Town Serves as Applicant for Dam Removal with project team support • Stage construction from Bowling Green • Reconstruct Bowling Green

  7. Balmoral Dam Removed

  8. Takings Plan

  9. Balmoral Dam Dam Out Conditions

  10. THANK YOU!Info & comments:www.ecorestoration.orgTom ArditoCenter for Ecosystem Restoration401-575-6109ecorestoration@gmail.comBob DouglasTown of Andover978-623-8311bdouglas@andoverma.gov