An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Development of HL-LHC D1 Magnetsand Preparation for Series Production Tatsushi NAKAMOTO (KEK) KEK On behalf of CERN-KEK Collaboration for D1 Development for HL-LHC 13th CERN-KEK Committee, CERN, Dec. 11, 2018

  2. Japanese Contribution to HL-LHC: D1 magnets • Beam separation dipole (D1) by KEK • Design study of D1 for HL-LHC within the framework of the CERN-KEK collaboration since 2011. • 150 mm single aperture, 35 Tm (5.6 T x 6.3 m), Nb-Ti technology. • Development 2-m long model magnets (3 units) at KEK • Deliverables for HL-LHC • 1 full-scale prototype cold mass (MBXFP) • 6 series cold masses (MBXF1-6) T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  3. Short summary of 2-m D1 models: MBXFS • MBXFS1: Previous cross section. Insufficient quench performance. • Cold test at April 2016 • MBXFS1b: Increased coil prestress to improve quench performance. • Cold test at Feb. 2017. • MBXFS2: New cross section, improvement on prestress, QPH… • Cold test at Oct. 2018. • MBXFS3: Reproducibility check. • Cold test foreseen at July 2019 T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  4. Design overview from MBXFS2 4 8 13 4 blocks 44 turns 19 Technical challenges ・Large aperture: Management of coil size and pre-stress. ・Radiation resistance:Radiation resistant material for coil parts. Cooling capability. ・Iron saturation:Good field quality from injection to nominal current T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  5. Performance of #1 and #1b: Training Quench • Training performance was significantly improved in the MBXFS1b. • Same or better coil prestress level (target: 115MPa) in MBXFS2. Development by 2017 T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  6. Design Parameters: 1st vs 2nd Models 4 8 13 4 blocks 44 turns 19 • Four HX holes instead of two in yoke: REQUEST from CERN. • Enhancement of mechanical support of coil blocks • Newly designed QPH for reducing MIITs (max T) T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  7. Curing Temp 190oC Coil pressure 30oC/h Total HT time: 15h10m 150oC 15oC/h 120oC 30oC/h Full-close Press w lower pressure Unload/reload Time 3h20m 4h 2h 4h 1h20m 30m • Curing condition for epoxy-blended cyanate ester: 120oC x 4h + 150oC x 4h • Self-fusing of polyimide insulation: 190oC x 0.5h • Coil pressure: lower at RT, while full-closing at 120oC T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  8. Magnet assembly QPH, ground insulation wrapping Top/bottom coil assembly Collaring End-ring welding Shell welding Yoking T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  9. Azimuthal coil pre-stress in straight section • Azimuthal coil pre-stress after yoking: 111 MPa(Target value = 115 MPa) T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  10. Training history MBXFS2 MBXFS1b Ultimate • 7 quenches to the nominal current (12.050 kA) • 11 quenched to the ultimate current (13.020 kA) • Quench current of MBXFS2 achieved acceptance criteria. Nominal MBXFS1 T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  11. Field integral(I=12.047kA) (): OPERA • Unallowed multipole components small enough. • Issue: large b3 of 18 unit at Straight Section. T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  12. MOU’s • MOU’s were signed on July 6, 2018 at MEXT, Tokyo, in presence of Dr. Isogai, Director General of Research Promotion Bureau, MEXT. T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  13. D1 Cold mass Design Pressure: 2.0MPa abs. Operating Temperature: 1.9 K Shell: SUS304L t10 Alignment markers (32) 2 HX pipes Cap for alignment hole End-cover Cold bore (Beam pipe) Support for post • Two halves shell (t10, SUS304L) • Structural design of the main body: KEK • Design of interface (extremities, end-cover, support): CERN (H. Prin) • Alignment feature on the shell: 8 x 4 holes for targets (like MQXA) T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  14. Compliance with CERN Safety Rules • Pressure vessel of the D1 cold mass (LMBXF) delivered from Japan MUST comply with safety requirements defined in 2014/68/EU Pressure Equipment Directive. • HL-LHC Project, CERN-HSE (as notified-body) and KEK have been establishing the agreement and the technical guideline. Final versions will be released soon. T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  15. Open-Tender for Prototype and Series Production • Finalization of Technical Specification: • Body text pp.66, • Appendices pp.113, • Drawings pp. 480. • Explanatory meeting of provisional technical specification: Dec. 14, 2018. • Hearing of opinions by Jan. 4, 2019. • Open-Tender: Jan. 16 - Mar. 11, 2019. • Opening of bids: Apr. 2, 2019 T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  16. Schedule Start of series production Contract signed Deadline of delivery KEK in-house ? Industrial manufacturer • Model magnetdevelopmentuntil 2019. • A contract of a full-scale 7-m long prototype magnet (MBXFP) willbegiven at April 2019. • Production of seriesmagnets (MBXF1-6) willstartafter the vertical test of the prototype. • Foreseenmilestones: delivery date of cold masses (presentbaseline) • MBXFP (for string test): Sep. 2020. • MBXF1-4 (for the HL-LHC machine): Dec. 2022. • MBXF1-6 (all): Dec. 2023. T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  17. Summary • Development of beam separation dipole (D1) for HL-LHC has been carried out by KEKwith a scope of Japanese in-kind contribution to the project. • Development of the 2nd model magnet (MBXFS2) has been carried out. • New cross section with 4 HX holes and several features implemented: enhanced coil pre-stress, improved coil end shape & wet-winding, new QPH, etc. • The 1st cycle of the cold test was done. Good training performance. Fairly good field quality except large b3 of 18 unit. • The 2nd cycle is currently underway. (Dec. 10 - 22) • The 3rd model development for reproducibility check will be started in Jan. 2019. • Significant efforts have been made by KEK with a support of CERN for preparation of a full-scale prototype and series production of D1 cold masses. • Finalizing the technical specification for open-tender. • Harmonization of the interface with respect to CERN’ s design and plan. • Compliance with CERN Safety Rule, in particular PED(2014/68/EU)ESRs. • Quality management in accordance with HL-LHC Quality Plan. T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  18. Link to Technical Reports of D1 (MBXF) • 8th HL-LHC Collaboration Meeting • https://indico.cern.ch/event/742082/overview • HL-LHC WP3 Meeting • https://indico.cern.ch/event/693219/ • https://indico.cern.ch/event/736308/ • https://indico.cern.ch/event/773207/ T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  19. T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production

  20. Overview of Production of D1 Prototype and Series • In-house development of 2-m model magnets so far. • Drawings of magnet are available. Preparation for 7-m magnets have started. • Fine tuning of wedges and end-spacers only after MFM of the 2nd model. • Fine-blanking dies for collar and yoke are developed and are ready for production. • 50% of stainless steel (NSSC130S) for the whole project already procured. • Production of 7-m magnets (cold masses) by a manufacturer. Contract will be given at April 2019. • Involvement of industry already from model magnet development: smooth technical transfer, accurate (lower) cost estimate. • Most of tools will be prepared by the manufacturer. • Very tight time frame for the prototype cold mass: April 2019 to Dec. 2020. • Procurement of coil winding machine in 2018 • Raw materials procured by KEK: timely provision to the manufacturer. • Low cobalt iron and stainless steel, radiation resistant GFRP. • Supplies from CERN: insulated SC cables, laminates of QPH (to be paid), HX tubes, insulated beam tubes (to be paid), end-covers (under discussion). T. Nakamoto, Development of HL-LHC D1 Magnets and Preparation for Series Production