300 likes | 420 Views
CERTIFICATE 4 IN BUILDING BCGBC4004A. Identify and produce estimated costs for projects. Course Overview. 18 week course First 10 weeks in classroom Following 8 in computer room 1.30pm - 5.15pm (with 15 min break) Assessments throughout. Assessments.
E N D
CERTIFICATE 4 IN BUILDING BCGBC4004A Identify and produce estimated costs for projects
Course Overview • 18 week course • First 10 weeks in classroom • Following 8 in computer room • 1.30pm - 5.15pm (with 15 min break) • Assessments throughout
Assessments • Assessment tasks/to submit every week • Test end of First term • Major assignment • Final test (cordels)
What you will need • Big folder with dividers • Calculator • Scale rule • Pencils or Pacer • Erasor • Highlighters • Punch • Stapler • USB memory stick
Be Prepared! • Arrive on time • Buddy up
Construction Estimates (page 24) • Estimating means the process of working out the Expected Nett Cost of constructing a building, and preparing a Tender or price for the finished project. • Calculating expected nett cost of the proposed building or work 2. Setting the Tender or selling price of the building or work
Calculation of Nett Cost (page 24) • Considerations: • The nature and Iocation of the work • Building methods and time scales • Bill of quantities • Labor and productivity • Supervision • Office backup and overheads • Materials and suppliers • Mechanical plant • Statutory requirements -Eg W.H.S -Insurance- Licences and Permits Scaffolding • Non - mechanical plant • Sub – contractors • On - site facilities
Calculation of Nett Cost • Most often based on the traditional detailed quantity take-off and unit price estimating method. • Quantities of materials are calculated from a full set of plans: • site plan • floor plans • Specialist drawings/reports prepared by: • consulting structural engineers • consulting electrical engineers • consulting hydraulic engineers • consulting mechanical engineers • specialist suppliers (eg. reinforcing steel fabricators, precast panel fabricators) • Shop fitters • Arborist • sections • details • specifications • finishes Schedules
Preparing an Estimate • Builder will need to: • Study the drawings, specifications and bill of quantities • Carry out a site visit • Develop a method statement • Prepare a preliminary construction program- (duration of the building works for accurate costing time related Preliminaries) • Seek quotations for materials supply, sub-contract work and possibly plant hire- (especially relatively long-term items such as scaffolding)
Tender/ Selling Price (page 25) • Factors Determining the Tender/ Selling price • The project risk • Current state of the market • Company policy (profit and mark ups) • Importance of winning or losing the particular project So the Tender price = Expected Nett cost + Profit/Markup (if successful the contract will be based on this figure)
The Bill of Quantities (page 26) • Definition- A bill of quantities is a list of numbered or coded items describing quantities and materials required to carry out the contract work that is divided into sections corresponding with their usual building trade and in accordance with the ASMMBW. • A bill of Quantities- • Is prepared by a trained Quantity Surveyor according to the ASMMBW. • provides a common basis for tendering • prevents differences of opinion/interpretation of the drawings and specification. • a thorough check of the drawings and specification.
How Does the process work? Owner/Client Quantity Surveyor Architect Professional Consultants Subcontractors/ Suppliers Builder/Estimator
Bill of quantities format (page 31) • A formal BOQ is prepared according to ASMMBW. • Arranged in trade order typically as you would construct • Measure only the finished product - (no allowance for waste or laps) • All dimensions before calculating to 2 decimal places • Do not deduct for openings < 1m2 or voids < 0.1m3 in volume • State dimensions in order of length, width and height or depth • Units of measurement should be m, m2, m3, tonne (steel) • All Billing quantities should be billed whole numbers. (except steel which is billed to 2 decimal places)
Points to be observed in the measurement of quantities • All ITEMS listed in alphabetical order and the first item on every page is ‘A’ • All descriptions shall adequately cover the work being measured as per the ASMMBW, but common methods of construction or stock sections need not be described in detail. • The functions of the five columns in the PARTICULARS column shall be strictly observed and carefully set out in accordance with the general practice of a quantity surveyor. • All dimensions are in metres and shall be taken to two decimal places • In the dimension column horizontal Iines are used to signify the differences between linear, area, volume, number and weight measures. • The measurement paper shall be spaced well apart to ensure clarity • Headings and sub-headings are recommended to clearly identify section and sub- sections of a trade and shall be underlined • The billing UNIT shall be in accordance with the ASMMBW • The billing UNIT shall be placed adjacent to the last line of the description, followed by the extended measured QUANTITY, in their appropriate columns.
EXERCISE 1 100x25 hardwood (Page52)