An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BETTER SOLUTIONS KMS : PRESS Transport/Installation BMI SLOVAKIA BMI SLOVAKIA 2006.08.30

  2. BETTER SOLUTIONS Contents • Project Overview • Project Execution Schedule • Ocean Transportation • River Transportation • Inland Transportation • 6. Site installation and commisioning BMI SLOVAKIA

  3. BETTER SOLUTIONS 1.Project Overview Manufacturer & Supplier : Rotem Company / WIA Corporation (Korea) Site : KIA Motors Slovakia (Zilina, Teplicka site) KMS Equipment List Transport Schedule : Masan  Rotterdam/Constanza  Rinz  Zilina (sea : 25~35d duration) (river : 15d) (land : 10d) Installation/Commissioning : Press #1st + Aux.–‘05.12~’06.01 / ‘06.01~04 프레스 #2nd – ‘06.03~05 / ‘06.05~07 BMI SLOVAKIA

  4. BETTER SOLUTIONS 2. Project Execution Schedule BMI SLOVAKIA

  5. BETTER SOLUTIONS masan (to load) loading (bulker) trucking Ocean transport (bulker) shipment (changwon) discharging (rotterdam) 4 25 Transport duration (departure~custom clearance) barging Rotem BMI(SSU) 35 Normal : 61d short : 55d Barge transport (danube) 13 discharging,on truck,custom clearance (rinz) custom clearance (zilina) KMS Deliver to factory Inland transport (rinz-zilina) 3 3 3 Installation & commisioning 3. Detail schedule for ocean transportation BMI SLOVAKIA

  6. BETTER SOLUTIONS 3-1. Shipment scope • Requirement at the time of loading BMI SLOVAKIA

  7. BETTER SOLUTIONS 3-2. Loading operation • loading operation BMI SLOVAKIA

  8. BETTER SOLUTIONS Rotterdam Constanza Typical Liner (35days) Suez Masan Charter vessel (25days) 3-3. Route and duration of ocean transportation BMI SLOVAKIA

  9. BETTER SOLUTIONS 3-4.1 Vessel spec. & transit time (Typical Liner) • Vessel Type : Typical Liner • (Multi-purpose heavy lift) • Gross tonnage : 24,000Ton • Net tonnage : 11,000Ton • Length(Over All) : 200M • Breath(Mid) : 28M • Depth(Mid) : 15M • Mouldet Draft/Dwt : 11M/30Ton • Built : Year 2004 • Classification : G. Lloyd + 100 A5 E • Cargo Hold : No.1~5 Hold with Tween Deck • Speed : 18~20 Knots BMI SLOVAKIA

  10. BETTER SOLUTIONS 3-4.2 Vessel spec. & transit time (Charter Vessel) • Vessel Type : Multi-purpose heavy lift • Gross tonnage : 9,000Ton • Net tonnage : 5,000Ton • Length(Over All) : 120M • Breath(Mid) : 20M • Depth(Mid) : 12M • Mouldet Draft/Dwt : 9M/20Ton • Built : Year 2000 • Classification : G. Lloyd + 100 A5 E3 • Cargo Hold : No.1~2 Hold with Tween Deck • Speed : 15 Knots BMI SLOVAKIA