160 likes | 173 Views
BETTER SOLUTIONS. 6-1. Installation Press equipments & schedule. BMI SLOVAKIA. BETTER SOLUTIONS. 6-2. Installation working scope. 1. General (1) Schedule Management (2) Safety Management (3) Management of Works
E N D
BETTER SOLUTIONS 6-1. Installation Press equipments & schedule BMI SLOVAKIA
BETTER SOLUTIONS 6-2. Installation working scope 1. General (1) Schedule Management (2) Safety Management (3) Management of Works (4) Inevitable condition, Disaster (5) Investigation and Technical advise for abnormal condition during installation, assembling and start up. (6) Working time (A) Seven(7) days / week Two shift should be done if not to keep the installation schedule (B) One(1) shifts / days or Two(2) shift / days (C) Eleven(11) hours / shift 2. Unloading and Packaging (1) Checking quantities and condition (2) Protection cover from rain, flood and snow fall at outdoor (3) Transportation from storage area to erection site (4) Unpacking at installation site (5) Disposal of crate, case, skid and steel, and rubbish to the outside of the plant (6) Removing rust preventives and cleaning BMI SLOVAKIA
BETTER SOLUTIONS 6-2. Installation working scope 3. Preparation of foundation (1) Checking of dimension of level and center in accordance with drawings and manuals 4. Installation of press equipments and fixture (1) Base plate (2) Foundation Bolt for Bed (3) Press Proper (Including Crown, Upright, Bed, Die Cushion, Slide, Moving bolster, Platform, Covers, Coil line eqipment, B.T.O ETC) (A) Installation and assembling (including level and center adjust) (B) Assembling of electrical motor and centering (4) Fixture (Auxiliary) * Air tanks * Oil Hydraulic unit with tank * Moving boister and rails, Cable Guides * Safety guards (5) 2,400 Ton Crown Assembly * Assembly work (Refer Packing list) (6) Welding & Cutting work for installation of equipments (7) Welding work for pipe connection between balancer cylinders and air tanks, cushion cylinders and air tanks BMI SLOVAKIA
BETTER SOLUTIONS 6-2. Installation working scope 5. Mechanical pipings (1) Assembling pipes between press and fixtures (2) Installation and connection of air pipes between air tanks and CTB cylinders (3) Flushing work after piping installation (4) The cutting, bending, welding and etc. for piping work of presss, coil line and etc. 6. Installation of electrical equipment (1) Drive panel for main motor (2) Control panels (3) Terminal boxes (4) Cable racks & ducts (Cutting, assembly, installation at site) (5) Conduit pipes (6) Wiring (A) Wiring and termination * From panels to termina boxes (TB) * From TB to sensors / actuators * Between each panels (7) The welding, bending, cutting work for electrical pipe installation BMI SLOVAKIA
BETTER SOLUTIONS 6-2. Installation working scope 8. Installation of scrap chute Carrier railway 9. Installation of the cover for coil line 10. Preparation for Machine Adjustment (1) Charging of grease to each points (2) Filling up the oils to tanks (3) Cleaning and oil sprinkling to Crown inside and Slide (4) Pickling, cleaning and Flushing of the pipes fabricated at site after inspection of Rotem S/V (5) Air blow cleaning of intemediate air pipes (6) Disposal of dirty and/or used oil (7) Wiring check (Continuity) (8) Power on (9) I/O check for electrical 11. Machine adjustment (1) Assistant Workers during the running test & after running test refer the working schedule (2) Responsibility for bad installation work BMI SLOVAKIA
BETTER SOLUTIONS 6-3. Organization chart BMI SLOVAKIA
BETTER SOLUTIONS Four(4) Point Hydraulic lifter : 400 Tons 1 unit Mobile Hydraulic crane : 100 Tons 1 unit 6-4. Installation equipment BMI SLOVAKIA
BETTER SOLUTIONS Mobile Hydraulic crane : 50 Tons 1 unit Fork lifter : 10 ~ 20 Tons 4 units • Remarks : KIA Over-Head Crane (30~50 Tons) 1-5. 설비 장비 BMI SLOVAKIA
BETTER SOLUTIONS 6-5. Installation basetool list BMI SLOVAKIA
BETTER SOLUTIONS 6-5. Installation basetool list BMI SLOVAKIA
BETTER SOLUTIONS 6-5. Installation basetool list BMI SLOVAKIA
BETTER SOLUTIONS 6-5. Installation basetool list BMI SLOVAKIA
BETTER SOLUTIONS 6-5. Installation basetool list BMI SLOVAKIA
BETTER SOLUTIONS 6-5. Installation basetool list BMI SLOVAKIA
BETTER SOLUTIONS 6-5. Installation basetool list BMI SLOVAKIA
BETTER SOLUTIONS Spare part : Rotem location : BMI Slovakia s.r.o in Rosina, Slovakia (8km from KIA site) Mlynska 813, 013 22 Rosina capa. : 1,500m2, Yard 5,000m2 scope : Press equipment Spare Parts 6-6. Spare Parts & maintenance BMI SLOVAKIA