SPEAKING THE SAME LANGUAGE: Ensuring a smooth lab turnover, from construction to operations. Learning Objectives. Thru this presentation we hope you will gain insights into … Levels of enhanced turnover Best time to identify FM turnover requirements Resources required for enhanced turnover
E N D
SPEAKING THE SAME LANGUAGE: Ensuring a smooth lab turnover, from construction to operations
Learning Objectives Thru this presentation we hope you will gain insights into … • Levels of enhanced turnover • Best time to identify FM turnover requirements • Resources required for enhanced turnover • How to specify in construction contracts
Ohio State University's Plant & Animal Agrosecurity Research (PAAR) • Highly secure BSL-3 bio-containment facility • 27,537 gross SF & 23,000 assignable SF • Two BSL-3 enhanced laboratories & four BSL-3 Ag animal isolation rooms that can handle large animals
Challenges to Enhanced Turnover • Potential challenges • No BIM data • No COBie data required from contractors • Lack of electronic documentation • Inaccurate drawings • Unique assets • Verifying hard-to-access assets • Who has the time and skills to do this • When does it need to be done
Traditional vs Modern Facility Turnover To BIM/FM Integration From Paper
Learning Objective #1 Levels of enhanced turnover: • Paper drawings and documents • Electronic drawings and documents • Key FM Data extracted and loaded • Key FM Data provided as part of construction • BIM to FM integration • Fully integrated Capital Project to Operations processes Lab project
Key FM Data extracted and loaded Scope of Work: • FM data extracted (drawings, documents, field surveys) • Field verification (barcoding optional) • Data formatted and normalized to FM system • Data loaded • PM Tasks/Procedures developed • PM’s Scheduled • Documents loaded and linked
Key FM Data extracted and loaded Data Objects: • Space/location records • Asset/equipment records • Vendors/manufacturers • OEM/Client Preventive Mntc tasks & procedures • PM schedules • Warranty information • Spare parts information • Hazardous materials • Digital images/pictures • Associated electronic documentation
Learning Objective #2 Best time to identify FM turnover requirements: When should you identify your FM needs for enhanced construction to operations transition? • During Construction • Before Contracting • During Design How about now… before your next project even begins.
Learning Objective #3 Resources required for enhanced turnover: • Knowledgeable in FM software applications • Knowledgeable of client’s FM software data requirements • Knowledgeable of Preventive Maintenance • Skilled in data collection/data loading techniques • Cost effective The essence of the COBie turnover process is to distribute the collection of electronic FM data and documents to all those involved in the construction process … Construction Manager, Designer, Contractor, Commissioning Agent, Owner … to share the information they already have and minimize the turnover cost impact.
Learning Objective #4 How to specify in a construction contract: • At a minimum, require contractors to provide COBie data * Be prepared to verify and validate their deliverables * Optionally, include COBie data as part of the BIM Execution Plan • Or, specify the data objects/fields/format required by your FM software application • Document when data must be provided • Make it a requirement for successful closeout and payment
Summary Benefits of an enhanced turnover process: • Complete operational data • Accurate operational data • Timely operational data • Data and documents accessible through FM system • Better coordination between Construction & Operations • Saves time • Saves money