1 / 18

Infrastructure Assessment as Viewed by Technology Holders

This infrastructure assessment outlines the necessary evaluations and considerations for technology holders participating in bid invitations for nuclear power plant projects. It covers various aspects including risk mitigation, regulatory compliance, funding, legislative requirements, grid and site facilities, human resources, environmental protection, and industrial involvement.

frese
Download Presentation

Infrastructure Assessment as Viewed by Technology Holders

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Infrastructure Assessment as Viewed by Technology Holders IAEA Technical Meeting December 10-12, 2008 R. Godden UNRESTRICTED

  2. Infrastructure Assessment Outline • From technology holders perspective what assessments are completed prior to decision to participate in bid invitation • How can technology holders help and support a NEPIO and its process to ensure a successful bid process • How can overall risks be lowered UNRESTRICTED

  3. Infrastructure Assessment Project Risks • Infrastructure • Completion • Technology • Regulatory • Supply Chain • Construction • Operation • Market UNRESTRICTED

  4. Phases for Decision Functions of an NEPIO in Phases 1 and 2 Industrial Fuel Cycle Procurement Waste Emergency Planning Security & Physical Environmental Stakeholder Resources Grid and Site Facilities Regulatory Legislative Radiation Protection Management Safeguards National Position Funding Safety UNRESTRICTED

  5. Infrastructure Assessment National Position • There should be confidence in the market for the vendors and the investors/lenders • Government commitment to safe, secure and peaceful implementation • Public consultative process underway • NEPIO established with clear charter and adequate funding and resources • Bilateral agreements in place with vendor countries UNRESTRICTED

  6. Infrastructure Assessment Safety • Evidence that international safety standards are well accepted • Training process for regulators, operators and specialists are well defined • Local laws and programs are support the health and safety of workers during the construction phase UNRESTRICTED

  7. Infrastructure Assessment Management • The Bid process is managed by experienced personnel • Clear description of how the bid is to be evaluated • Country specific requirements • Technology assessment • Financial, legal, and commercial aspects • There should be adequate time allowed for vendors to submit comprehensive bids UNRESTRICTED

  8. Infrastructure Assessment Funding and Financing • Funding model of the project is very important to vendors, lenders and investors • Upfront assessment of the ability of the owner to finance the NPP • Financing of foreign content • Local financing requirements • Export credits • Need for Sovereign Guarantees UNRESTRICTED

  9. Infrastructure Assessment Legislative • All relevant legislative requirements have been adopted • Nuclear Law is in place • Legislation pertaining to nuclear power program in place: • Intellectual Property protection • Use of local land for site • Foreign investment • Taxation • If needed, financial guarantees UNRESTRICTED

  10. Infrastructure Assessment Regulatory • Establishment of regulatory framework • Use of qualified personnel through consultants, other nuclear regulatory bodies and international organizations • Vendors and lenders/investors need to clearly see that the licensing process is well defined and achievable • Delays in regulatory/licensing process may add to overall cost of project UNRESTRICTED

  11. Start of Process “Regulatory Readiness” In-Service Fully staffed Regulatory Organization Staffing Can use consultants Regulatory Staffing UNRESTRICTED

  12. Infrastructure Assessment Grid • The size of the grid and the and the expected additional capacity should be understood • Any required enhancements agreed by owner/government • Grid specifications need to clearly included in the Bid Site and Supporting Facilities • All siting requirements have been assessed and any political, legal or public acceptance issues can be resolved • Clear delineation of responsibility for access, security, local infrastructure are outlined in Bid document UNRESTRICTED

  13. Infrastructure Assessment Human Resources • Plans that address adequate staffing and training for all areas including regulatory, bid preparation and assessment, support during construction phase and operations and maintenance • Legislation and programs that support the health and safety of workers during construction, commissioning and operations Environmental Protection • Environmental Impact Assessment completed. • Vendors must understand environmental sensitivities during construction phase UNRESTRICTED

  14. Infrastructure Assessment Industrial Involvement • The upfront assessment of the local capacity to support implementation especially in the construction area • Use of local resources will lower overall cost of implementation • More economical to purchase a technology that can be aligned with local resources rather than a “black box” approach • Procurement/local supply of equipment and materials • Selected vendor can assist with development of Quality Assurance and Control process and evaluation of local resources UNRESTRICTED

  15. Infrastructure Assessment Procurement • The team should be experienced and qualified to evaluate the bids and should have good knowledge of: • Technology Assessment • Financing model is important to vendors. Who takes risk? • Schedules and delivery times • Transportation, insurance, taxes and customs • Commercial terms and conditions • Upfront discussions with lenders, vendors and other international bid evaluation teams can help this process UNRESTRICTED

  16. Infrastructure Assessment Summary • Vendors will assess that key issues have been addressed such as: • Political and government support is present • Funding of the project is defined • Clear regulatory environment is present • Environmental and Safety programs are in place • Commercial terms and conditions are clear • Technology assessment criteria is established • Local infrastructure including construction sources have been assessed • Vendors can work with an NEPIO and other support areas in the early phase to ensure these issues are addressed UNRESTRICTED

  17. Construction Permit NEPIO Activity Pre-Project Pre-Construction Construction In-Service Defines and mitigates risk Project Phases UNRESTRICTED

  18. UNRESTRICTED

More Related