1 / 7

ERCOT Project Update ERCOT Outage Evaluation Phase 2 (SCR745)

ERCOT Project Update ERCOT Outage Evaluation Phase 2 (SCR745). TDTWG May 7, 2008. PR60006_01 Phase 2 ERCOT Update - Overview. Background: SCR 745: To achieve improved Market performance and reliability through a reduction of ERCOT Retail Systems unplanned outages.

Download Presentation

ERCOT Project Update ERCOT Outage Evaluation Phase 2 (SCR745)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERCOT Project UpdateERCOT Outage Evaluation Phase 2 (SCR745) TDTWG May 7, 2008

  2. PR60006_01 Phase 2 ERCOT Update - Overview Background: SCR 745: To achieve improved Market performance and reliability through a reduction of ERCOT Retail Systems unplanned outages. This effort was planned to be implemented in two subprojects; PR60006_01: ERCOT Outage Evaluation Phase I and Phase II • Phase I, NAESB and Proxy Clustered (Delivered 02/2007-Goal Achieved) • Phase II, Paperfree Clustered environment with File Server Redundancy and High Availability PR60006_02: Phase III, Database Clustered environment (Cancelled per recommendations at 04/02/2008 TDTWG) Phase II Status: 02/10/2007 – Implemented Veritas clustered solution resulted in rollback due to unsuccessful failover. 03/08/2008 – Implemented Polyserve clustered solution resulted in rollback due to performance and stability issues (This would have delivered Redundancy and Failover) 05/07/2008 – Seeking recommendations from TDTWG for Next Steps 2

  3. PR60006_01 Phase 2 ERCOT Update – Next Steps Recommendations from HP for Performance improvement will require Architectural changes, server rebuilds, and testing ERCOT Recommends pursuing one of the following Options: 1) Place project “On Hold” due to the following (preferred): • Stabilization of San Switch Replacement Project (Polyserve known issue with loss of connectivity to SAN) • Test Environment Lock down until December 2008 due to Ts and Cs, MarkeTrak, and Nodal • Resource constraints due to Ts and Cs, MarkeTrak, and Nodal • Eliminate additional Finance charges by placing project on Hold • Allow to move forward in 2009 with implementation that will deliver Failover capabilities (High Availability and Redundancy Goal of SCR) 2) Close project and complete effort as O & M: • Additional funding will be required for remaining efforts • Total Project estimated at $1M approved by Board in 2005 • Committed approximately $885K, will require Board approval for additional funding 3

  4. PR60006_01 Phase 2 ERCOT Update – Outages 4

  5. PR60006_01 Phase 2 ERCOT Update – Outages Based on IT incident Report and SCR Metrics 5

  6. PR60006_01 Phase 2 ERCOT Update – PF Outage Details (3yrs) PaperFree Availability Metrics Prior to March 2008 as a result of 2007 Intermediate Resolutions • Previous Logged incident for PaperFree file server – 02/2007. • Until March, 2008 – Paperfree Application was 100% available due to intermediate solutions (meeting SCR Goal for reliability). 6

  7. PR60006_01 Phase 2 ERCOT Update – TDTWG Recommendations Discussion 7

More Related