Activity 5. Drawing a Gantt chart for the development of a school attendance system. Suppose when developing a school attendance system, the following activities are identified. Activity 5. Drawing a Gantt chart for the development of a school attendance system.
E N D
Activity 5 Drawing a Gantt chart for the development of a school attendance system Suppose when developing a school attendance system, the following activities are identified.
Activity 5 Drawing a Gantt chart for the development of a school attendance system Suppose when developing a school attendance system, the following activities are identified. Complete the Gantt chart using the above information.What is the minimum number of weeks required to complete the project? 12