An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Activity 5 Drawing a Gantt chart for the development of a school attendance system Suppose when developing a school attendance system, the following activities are identified.

  2. Activity 5 Drawing a Gantt chart for the development of a school attendance system Suppose when developing a school attendance system, the following activities are identified. Complete the Gantt chart using the above information.What is the minimum number of weeks required to complete the project? 12

  3. Activity 5 Drawing a Gantt chart for the development of a school attendance system

  4. Activity 5 Drawing a Gantt chart for the development of a school attendance system

  5. Activity 5 Drawing a Gantt chart for the development of a school attendance system