1 / 47

Water Power Peer Review

Water Power Peer Review. Rob Cinq-Mars, President. Free Flow Energy, Inc. (800) 928-0435; Rob@FreeFlowEnergy.com 6 September 2011. Project Number: DE-EE0004567. Design of Submersible Generator for MHK. Purpose, Objectives. The design of a submersible generator – key features:

gad
Download Presentation

Water Power Peer Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Water Power Peer Review Rob Cinq-Mars, President Free Flow Energy, Inc. (800) 928-0435; Rob@FreeFlowEnergy.com 6 September 2011 Project Number: DE-EE0004567 Design of Submersible Generator for MHK

  2. Purpose, Objectives The design of a submersible generator – key features: • designed by motor/generator industry professionals • work with multiple turbine styles • critical subassembly of current energy conversion systems Objectives: • accelerate MHK • improving performance • lowering cost, and • improve operation and maintenance

  3. Project Team

  4. Industrial Partners

  5. Technical Approach - Tasks • Assess resources tidal and river for: • proper sizing • form factor • power rating • ambient operating conditions. • Determine appropriate topology • Electromagnetic circuit design • Mechanical design • Investigate Manufacturing Requirements • Cost Analysis • Commercialization and future research

  6. Technical Approach – Key Issues • MHK Generators - where wind generators were in ‘70s • Eliminate gearbox (Rim Mount Design) • Get topology, sizing, power and form factor right • Components designed/manufactured by industry • Work with multiple turbines • Design for harsh marine environment • Coupling method

  7. Schedule & Budget Schedule • Initiation date:11/1/2010 • Planned completion date: 10/31/2011 • Design Completed, report published, paperwork complete Budget: • On schedule, on budget, additional cost share provided

  8. Project - Preliminary • Differences between renewable and conventional generation • Appreciate difference between power, energy and nameplate capacity • Differences between tidal and inland stream flows • Design for common siting conditions not extreme / rare • Lessons learned from wind • Many different turbine styles, sizes, & stages of development • Review and understanding of MHK state of art • Understanding of regulatory, permitting, siting • Acceptance of 35% efficiency • Baseline estimate of “realistic” siting conditions

  9. Resource Assessment - Tidal What’s Realistic?

  10. Resource Assessment - Area Area & # Turbines to Generate 1 MW Assumes 35% eff (Gorlov)

  11. Resource Assessment – Distribution & Area

  12. Resource Assessment - Tidal UK Current Predictions

  13. Resource Assessment - Tidal Tacoma Narrow Currents

  14. Resource Assessment - Tidal Maine, Washington, and AK Velocity Frequency Histograms

  15. Resource Assessment - Tidal Most recently – Georgia Tech / DOE Model, Mid Atlantic Currents

  16. Resource Assessment - Tidal Mid – Atlantic Depths

  17. Resource Assessment - Inland

  18. Resource Assessment – Inland USGS Field Descriptions

  19. Resource Assessment - Inland Channel Velocity (mps)

  20. Channel Area - Inland USGS Inland Data – Channel Area (m^2)

  21. Channel Depth - Inland

  22. Channel Discharge CMS

  23. Resource Assessment Cont. Depth: 10 – 30 m (Top: Nav Clearance, Bottom: Permitted Sites) Salinity: 35 ppt Temp: 35-90 F, 2-32 C

  24. Analysis of turbines Proprietary data was shared with FFE based upon completed NDAs. Data included CAD, test data, estimated torque / speed, TSR, etc. This data was used to design a generator with a 2 meter diameter rated at 20 kW to connect to a 3m x 7m GHT, or an equivalent FloDesign turbine which presents a 5 m diameter to the flow. This is approximately 21 m^2 in cross section. Comparable dynamic performance…

  25. Selection of appropriate topology Induction or Synchronous? (Field winding not reasonable) AF, RF, or TF? Gearbox for speed? (Rim mount) Iron core or coreless (magnet use and detent torque) Pole Count: more poles more voltage more power (balancing act) Cost and manufacturability Selection: RFPM Synchronous as wind is evolving to.

  26. Gearbox Issue Shaft seals are an issue, bow wakes, velocity fluctuations we selected rim mount speed enhancement with 2 m diameter

  27. Generator Topology AF or RF

  28. What others do…

  29. What others do… Air core? Transverse Flux? Weight reduction? Increased magnet use

  30. What others do… SmartMotor Claims: concentrated windings, higher fill factor, higher efficiency It appears from the description that this generator uses large gauge wire, hand inserted.

  31. What others do… VIEG – Variable Input Electrical Generator This appears to be a “stacked generator.” They appear to be dynamically connecting windings in series at low speed and parallel at high. This appears to be quite costly, like purchasing multiple generators for one site.

  32. Our generator Radial flux, permanent magnet, synchronous, three phase, rim mount (2 meter diameter, 20 kW in 2 m/sec flow) A conventional, buildable, cost effective approach capable of coupling to multiple turbine designs. The design leverages established and simple manufacturing processes.

  33. Concept with Single GHT

  34. Concept with Double GHT

  35. Concept with Ducted In-flow turbine

  36. Electromagnetic Circuit Design

  37. Electromagnetic Circuit Design (cont)

  38. Mechanical Design – Segment Lam

  39. Mechanical Design – Segment Core

  40. Mechanical Design - Magnets

  41. Mechanical Design - Rotor

  42. Mechanical Design - Other

  43. Mechanical Design – Winding Diag.

  44. Other Work Completed Cost Analysis Manufacturability Tooling and Fixturing Requirements Protective Coatings Refer to Final Report

  45. Conclusion Delivered what was proposed… the design of a submersible generator capable of coupling to multiple turbine styles, designed by motor/generator design engineers specifically for MHK Needed: Turbines to move closer to production Diversions to accelerate flow A greater indication of commercial viability

  46. Moving Forward – Latest News…

  47. Moving forward: embracing diversions http://www.youtube.com/watch?v=hEnANV8laRU

More Related