1 / 31

TS Department

TS Department. Utilities Safety Access SU - a plea for co-ordination of co-activities. Utilities - Electricity. Readiness: General services are being installed and commissioned to the installation schedule and will be available for the LHC commissioning.

gaius
Download Presentation

TS Department

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TS Department Utilities Safety Access SU - a plea for co-ordination of co-activities T.Pettersson - EDMS: 574663

  2. Utilities - Electricity Readiness: • General services are being installed and commissioned to the installation schedule and will be available for the LHC commissioning. • In the tunnel the F1 (400 V) line will be ready: power boxes with socket outlets, power line for the monorail, power line for the local users and the UPS power line. • The UPS is overshadowed by a not too well performing contractor which requires permanent attention from the TS/EL management but no major problem is expected. • In the power centers: US, UJ, UA etc are on schedule and problems are not expected. T.Pettersson - EDMS: 574663

  3. Electricity - risks • 400 kV system, 66 kV system: Most equipment recent (<20 years) and in good condition. Only slight worry might be 66/18 kV transformers from Zaporoshtransformator. However, they seem to be in good condition and they are thermally over-dimensioned, so they should age very well. • A breakdown would be critical, but is considered to be very unlikely. Repairs will be long. • 18 kV system: LHC system is in good condition, well maintained and less than 20 years of age for the oldest parts. Repairs will be rapid (days ) if a fault should occur, which is not likely. • SPS 18 kV is the subject of a consolidation project starting next year T.Pettersson - EDMS: 574663

  4. Electricity - Monitoring Operation and operative readiness of existing applications will be given priority over new applications. Support comes from EFACEC (ENS supervision system supplier) and is contracted already. T.Pettersson - EDMS: 574663

  5. Electricity – power and cabling issues • Sufficient electrical power will be available everywhere. • UPS will be available as requested… • Power consumption will have to be actively monitored (60MVA available from EOS, additional power comes from EDF). Power consumption needs to be projected from July 2006 to July 2008. The Energy Management Panel is looking into how to ensure the supply of power but needs user input. Presently many activities in the machine and the experiments looks to be parallelized …. • The last arc cabling campaign ends in September 05! Any new campaign will have to be planned in close collaboration with IC. • Campaigns in the long straight sections still possible later. • Connectique will be done in the shadow of other activities. T.Pettersson - EDMS: 574663

  6. Utilities – CV • Systems concerned: • Demineralized water cooling • HVAC (air conditioning) system in the underground and their hydraulic connections. • Status of CV systems: • Piping commissioned at all points except Pt 5 and IR7, • Flexible connections installation according to coordination schedule (CS), • Underground cooling plants commissioned at even points. Ongoing at odd points (May), • Primary cooling towers commissioned and running for cryogenics for last months already, • HVAC installation ongoing (110 + lots!). Commissioning at the end of installation of each lot, according to CS. Of particular interest to HCWG are the REs and UAs. CS reviewed recently to take into account HCWG requirements. • Future 24 h hardware test run will serve for validation of performance. T.Pettersson - EDMS: 574663

  7. Utilities – CV • Problems? • Installation: None anticipated, although very tight schedule, • Operation: Once commissioned, systems handed over to CV M&O contractor – TCR and Stand-by duty service 24/7. T.Pettersson - EDMS: 574663

  8. Utilities – CV • Systems operation parameters: • Primary, demineralized, mixed and chilled water cooling as defined in ESs LHC-FB-ES-0001, LHC-FW-ES-0001, and LHC-FG-ES-0001 respectively. • HVAC and compressed air as defined in ESs LHC-UA-ES-0001 and LHC-FA-ES-0001 respectively. • CV operation parameters retrievable from CV’s monitoring systems via web pages. T.Pettersson - EDMS: 574663

  9. Utilities – CV • Interactions with other systems: • Survey: Low tunnel ventilation mode (9,000 m3/h) is planned. Possible interaction in UJs or RRs due to local HVAC systems for racks. Possible if required to stop these systems during a limited time for SU operations. • Power converters, warm magnets and water cooled cables: procedure for hydraulic connection of these elements and powering after intervention to be determined with groups concerned. Hydraulic balancing pre-set. Final adjustments, if necessary, after connection of elements. T.Pettersson - EDMS: 574663

  10. Utilities - Access • LHC Access – • Access Control System (LACS) • Access Safety System (LASS) – outsourced, contract to be awarded in August 2005. • Access supervision in CCC – does the HWC need control of the access locally? • Interfaces LASS- EIS (machine elements), all elements finally known, commissioning is now under study • When to start replacing old LEP system… new cards and access controls…? T.Pettersson - EDMS: 574663

  11. LACS Planning 1/2 T.Pettersson - EDMS: 574663

  12. LACS Planning 2/2 T.Pettersson - EDMS: 574663

  13. ACCESS CONTROL ACCESS SAFETY LHC Access Safety LHC Access Control T.Pettersson - EDMS: 574663

  14. Utilities – Access & Security • Security is on schedule • Automatic Fire detection, AUG • ODH, Evacuation, Red Telephones, CSAM (7/34 zones done) • RAMSES – not required for HWC, but certainly before the beams arrive. • Safety Information Panels (SIP) – will be made available but not before mid-end 2006. T.Pettersson - EDMS: 574663

  15. T.Pettersson - EDMS: 574663

  16. Safety – Red telephones LHC tunnel: All done except for: - TI 12 : 1 telephone missing (will be installed during the test period) - P 6 : UD 62 and UD 68 - TI 8 : pending on CNGS work, normally foreseen end July. These are covered by provisional installations and are operational. The final installation depends on the installation of the security cable tray. A general test and verification period is foreseen on weeks 18 and 19 in 2005. - Points 2, 4, 6: No requests for red telephones received. In some places old telephones not been dismantled by the end of LEP, are still operational. - P 1: USA15 and UXA15 are finished - P 5: USC55 and UXC55 provisional cabling, alarms L3 not connected - P 8: UX85 finished, alarms L3 not connected. T.Pettersson - EDMS: 574663

  17. Factory acceptance tests T.Pettersson - EDMS: 574663

  18. RAMSES in the field • CERN collaboration SC/RP-TS (EL, CV, CS) -IT (co-ordination by CSE) • Installation planning started 10/2004 • First equipment on site 18/04/2005 (Water Pts 1, 5, 7 & 8 + Aerosol Sampler pt 5) • Further installation split into 4 time frames • Ventilation Pt 1 by 30/06/2005 (5 monitors) • Water pts 2, 3, 4, 6 by 18/07/2005 (4 monitors) • All other surface equipment Pts 1, 7 & 8 by 01/09/2005 (20 monitors) • All other surface equipment Pts 2, 3, 4, 5, 6 by 01/02/2006 (52 monitors) T.Pettersson - EDMS: 574663

  19. RAMSES in the field T.Pettersson - EDMS: 574663

  20. Piquet – intervention delays T.Pettersson - EDMS: 574663

  21. SU - a plea for co-ordination of co-activities Objective of SU - final magnet alignment – requirements: • Delay is 8 (initially 12 planned) weeks/sector, 2 teams in parallel as soon as magnets are cooling down (<200 K). • Authorisation to touch and to move the magnets on their jacks!. • Max 9.000 m3/h of air movement, with all door closed and no lateral ventilation in the RR’s. If required for alignment purposes, air conditioning has to be turned off for at least ½ day two times. • Does this pose a problem with rack cooling? • Easy passage for surveyors through all access zones. • Equipment transport required ( motorised please) • No passage of vehicles during measurement periods (except bicycles – and then not too many). T.Pettersson - EDMS: 574663

  22. Not SU’s favorite tunnel transport vehicle T.Pettersson - EDMS: 574663

  23. FM- Facilities support T.Pettersson - EDMS: 574663

  24. FM – Facilities support • Guards only at Pt2, Pt4 ,Pt6, Pt8. • Note: cleansing etc. requires access to underground transport…. • No large amount of waste – ( only paper at this stage we presume)? T.Pettersson - EDMS: 574663

  25. Questions • Point 4 RF commissioning – access control issues? • Access Safety – Only limited to radiological protection, no impact on the HWC since there is no beam yet? T.Pettersson - EDMS: 574663

  26. Conclusions – Utilities, Safety, Access • Electricity and power – on schedule • Cabling – last campaign this summer! • Cooling/Ventilation – on schedule (but tight) • Safety (CSAM, RAMSES)- on schedule. • Access – on (tight) schedule but no doors/gates in the tunnels will be installed, access control will depend on the professionalism of the staff. • Issue on date of LEP –> LHC access hw migration. • Other utilities – lifts, sanitary facilities etc. are ok. • Piquet services – support in 1-4 hours@24/24 regime. T.Pettersson - EDMS: 574663

  27. Access - Going to Operation 1/3 • Definition of “Transition phase” • The transition phase goes from the day the first access point is set in operation until all the LHC is accessible via the LACS. • During this phase, the current system (old LEP+experiment access) and the LACS will CO-EXIST. • During this phase the access conditions and operations are NOT THE SAME as the one required for the operation of the LHC. • Scope of the “overlap” • The current system covers the access to all the LHC pits. T.Pettersson - EDMS: 574663

  28. Access - Going to Operation 2/3 • Problems to be solved • The LACS uses a RFID identifier that is NOT compatible with the current magnetic card readers.Possible solutions: • Use a temporary magnetic card reader installed in parallel on the OVERLAP. • Initiate the production of the CERN cards with the RFID technology ($$$) • It is required to define a team for the operation and maintenance during the transition phase: • This team will carry out all the tasks for the normal operation and maintenance • This team will be supported by the B1221 contract for all maintenance. • This team will ensure the information to the users during the transition phase T.Pettersson - EDMS: 574663

  29. Receives a CERTIFICATE Receives a AUTHORISATION Access - Going to Operation 3/3 1 • NOTE: • TODAY: • The CERN card is used for accessing all the sites (also LHC) including the building and the gates. • The FILM BADGE is only used for accessing the SPS primary areas Person getting at CERN registration Receives a CARD + FILM badge (not ALL) 2 DB Safety Course 4 3 Authorization 5 A person can only access once the steps 1,2, 3 and 4 are completed T.Pettersson - EDMS: 574663

  30. Receives a CERTIFICATE Receives a AUTHORISATION Going to Operation (TRANSITION PHASE) 1 Receives a NEW CARD? IF NOT Person getting at CERN registration Receives a CARD + Film Badge (not ALL) Receives a NEW CERTIFICATE? 2 DB INSTALL temporary readers Safety Course 4 3 Receives a NEW AUTHORISATION? Authorization 5 A person can only access once the steps 1,2, 3 and 4 are completed T.Pettersson - EDMS: 574663

  31. Going to Operation - WHEN? • OPTION 1 (End 2006 ?): • Delay as long as possible the replacement of the existing LEP access points. • Start installing the equipment in the underground and leave the doors open. • Prepare the registration office with the RFID badges and training for the use of the new system • OPTION 2 (End 2005 ?): • Start installing the system also replacing the existing LEP access points. • Temporary install a magnetic card reader to cover the transition period • Prepare the registration office with the RFID badges and training for the use of the new system T.Pettersson - EDMS: 574663

More Related