Design and Construction of Main & Crescent Bridges. 9 th Oct. 2008. Location . Palm Deira. The World. Palm Jebel Ali. Palm Jumeirah. Dubai Waterfront. C1. L=380m 3Lanesx2. C3. L=380m 2Lanesx2. C4. L=380m 3Lanesx2. M1. M3. L=1,200m 4Lanesx2. L=1,450m 4Lanesx2. Site Layout.
E N D
Design and Constructionof Main & Crescent Bridges 9th Oct. 2008
Location Palm Deira The World Palm Jebel Ali Palm Jumeirah Dubai Waterfront
C1 L=380m 3Lanesx2 C3 L=380m 2Lanesx2 C4 L=380m 3Lanesx2 M1 M3 L=1,200m 4Lanesx2 L=1,450m 4Lanesx2 Site Layout A = 11,600,000 m2 Frond Trunk PC Yard Site Office Nakheel Site Office
Contract Project Name Main and Crescent Bridges Project, Palm Jebel Ali Construction Period 2007.4.1 ~ 2010.11.30 (44months) Contract Design & Build (Lump Sum) Contract Amount US$ 350,286,921 (AED 1,285,553,000) Employer NAKHEEL Consultant PARSONS PTG Halcrow International Partnership Designer COWI 3rd Party Checker
Main Bridge 23.5m 23.5m
Crescent Bridge 19.35m 19.35m
Work Programme 32%
PC Production / PC Yard Layout Stock yard 2 1 5 3 Office 4 6 Workshop PC Yard area : 700m x 200m 1 2 3 Seg Transporter Steam Curing Chamber Rebar Jig Casting Cell (Mould) 4 5 6 Launching Girder Batch Plant Steel Shop Gantry Crane
PC Production / PC Yard Overview Gantry Crane Batching Plant Workshop Casting Mould Match Casting Steam Curing Rebar Jig Manipulator
M1 M3 1500m 850m 800m 1600m PC Erection / Transport Transporter Carrying Path - Self weight of transporter : 44ton - Carrying capacity : 170ton - Length : 27.1m - Width : 4.68m - Carrying speed : 3km/hr Hydraulic cylinder 27.1m Transporter
PC Erection / Launching Girder Lateral View Winch Group 127m (1023 ton) Plan View Typical Section Image of Launching Girder
Progress / Manpower Daily Manpower On Site Manpower Nationality 719 Manger / Engineer 90 Bangladesh 219 India Supervisor / Foreman 55 84 Operator 48 Thailand Electrician / Mechanic 25 32 Pakistan 35 Philippines Worker / Etc. 1,128 271 China / Etc. 1,353 1,353 Worker Camp Tool Box Meeting Refreshing Shelter
Progress SEGMENT PRODUCTION YARD SEGMENT TRANSPORTATION SEGMENT ERECTION MAIN BRIDGE 1 SPAN 24
Progress CON’C BATCH PLANT CRESCENT BRIDGE 1 ABUTMENT BORED PILE BRIDGE PIER HEAD