1 / 16

Tevatron lcw cooling Reconfiguration Analysis Tevatron Decommissioning Activity Meeting 2

Tevatron lcw cooling Reconfiguration Analysis Tevatron Decommissioning Activity Meeting 2. Abhishek Deshpande 10/2011. Overview. A0’s flow requirements Flexible scenario that accommodates for HX cleaning; redundancy Scenarios simulated: Scenario A: 2 pumps at E4 and 2 pumps at F1

gali
Download Presentation

Tevatron lcw cooling Reconfiguration Analysis Tevatron Decommissioning Activity Meeting 2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tevatronlcw cooling Reconfiguration AnalysisTevatron Decommissioning ActivityMeeting 2 Abhishek Deshpande 10/2011

  2. Overview • A0’s flow requirements • Flexible scenario that accommodates for HX cleaning; redundancy • Scenarios simulated: • Scenario A: 2 pumps at E4 and 2 pumps at F1 • Scenario B: 2 pumps at F1 and 2 at F2 • Scenario results • Reconfiguration of F1 and F2 service buildings to have 2 pumps • Conclusion

  3. A0’s flow requirements finalized • Spoke to John Reid about A0’s flow requirements • John stated that the current flows are higher than what is actually necessary • John also said that the 4” LCW header at A0 would need a minimum of 60 GPM @ 75 Psig • One of the major loads: 3.9 GHz Klystron, that needs 25 GPM of flow, most probably will be moved to NML • Also, the heat load at A0 is very small: 24 kW

  4. Flexible scenario that accommodates for HX cleaning Service building 1 Service building 2 Pump 1: On Pump 2: Off Pump 1: On Pump 2: Off Normal operation Service building 1 Service building 2 Pump 1: Off Pump 2: Off Pump 1: On Pump 2: On Service building 1’s HX being cleaned Service building 1 Service building 2 Service building 2’s HX being cleaned Pump 1: On Pump 2: On Pump 1: Off Pump 2: Off

  5. Scenarios simulated:Scenario A:2 pumps at E4 and 2 pumps at F1 • All the flow rate requirements of the loads leading up to F4 enclosure were satisfied, however, if 2 pumps were being operated at E4 while F1’s HX was being cleaned, the following flows were predicted at F4 and A0:

  6. Scenarios simulated:Scenario B: 2 pumps at F1 and 2 pumps at F2 • All the flow rate requirements of the loads leading up to F4 enclosure were satisfied, and F4 and A0 flows are as below: Normal operation, one pump at F1 and one at F2

  7. Scenarios simulated:Scenario B: 2 pumps at F1 and 2 pumps at F2 F1 service building’s HX being cleaned, 2 pumps running at F2:

  8. Scenarios simulated:Scenario B: 2 pumps at F1 and 2 pumps at F2 F2 service building’s HX being cleaned, 2 pumps running at F1:

  9. Reconfiguration of F1 and F2 service buildings to have 2 pumps • Unfortunately, F1 and F2 service buildings have only one pump per building: Continued..

  10. Reconfiguration of F1 and F2 service buildings to have 2 pumps Continued..

  11. Reconfiguration of F1 and F2 service buildings to have 2 pumps • In order to get a fairly good estimate of installing another pump, I am currently working with SEA contractor Jose Rangel • Jose said: • All the connecting piping would be stainless steel and not aluminum • To install one pump, and re-pipe the headers such that two pumps would run in parallel, it would require: • Two contractors working full time • Total number of 6” welds= 20-25

  12. Reconfiguration of F1 and F2 service buildings to have 2 pumps • The completed service building would look something like: Continued..

  13. Reconfiguration of F1 and F2 service buildings to have 2 pumps

  14. Reconfiguration of F1 and F2 service buildings to have 2 pumps • Importance of redundancy: • According to Paul Czarapata, redundancy is not as important as it was during Tevatron’s Run II • However, it is desirable because the following experiments would be expecting beam: • The neutrino program • 2 test beams at Meson • Special projects • It costs close to $60,000/hr to run the accelerator complex, and if there is no redundancy the accelerator complex would have to be down for 3-4 days • Thus, a comparatively small investment to accommodate redundancy would prove to be fruitful from an operations perspective

  15. Conclusions • Using E4 service building would not provide sufficient flow to all the loads in the MR remnant • Having 2 pumps at F1 and F2 would work for us • Redundancy is not as important as it was, but its still desirable • Future plans: • There is talk about using the A and B Tevatron sectors for a Plasma Accelerator project • There is also talk about IARC (Illinois Accelerator Research Center) using Tevatron’s cooling system water • If these plans get approval, then Scenario B (2 pumps at F1 and F2) will not work

  16. Questions, comments..

More Related