Tevatron Decommissioning WGM

Tevatron Decommissioning WGM. Status 1/23/2012. Winterization. Water FESS working with the AD Mechanical Support Department, changed various sump pump discharge lines to prevent freezing and subsequent potential flooding.

judah-potts
Download Presentation

Tevatron Decommissioning WGM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tevatron Decommissioning WGM Status 1/23/2012 Paul C. Czarapata

  2. Winterization Water • FESS working with the AD Mechanical Support Department, changed various sump pump discharge lines to prevent freezing and subsequent potential flooding. • Mechanical Support working with Operations and FESS are evaluating a scheme that will allow all but two service buildings to have their pond pumps turned off • First attempt showed faster than expected rise in LCW temperatures • Situation being analyzed and a new idea has been put forth that will be implemented. Paul C. Czarapata

  3. Harvesting Removal of components continues as requested with all requests being documented. All work requests automatically generate an email to me which I archive so we know the state of the components in the tunnel. Example below: • A request has been made in an area you are subscribed to or have asked to receive notification in regards to an 'attention of' entry http://www-ad.fnal.gov/cgi-worklist/worklist_form.pl?id=14144 -- Entry 14144 Requestor: Chris Jensen Shutdown: Short-Term with the 'do-now' flag set Priority: Normal Call In: No Area: Tevatron Type: Kicker Systems Title: Drain FC-40 from magnets Description: Drain FC-40 from magnets Location: F17 Kicker Magnets Duration: 6 hours over 1 day Attention of: Mech Support Tevatron Manpower: Technicians Keys: 2 Tev F sector Crew: SaliSylejmani, Chris Jensen Loto: None Moratorium for now on things that would change Sectors F – B pending ORKA work. Paul C. Czarapata