1 / 10

The Engineering Test Facility for nLC

The Engineering Test Facility for nLC. ALCPG Victoria, BC July 30, 2004. Introduction. Linear collider project goals: Construct a collider with an initial energy of 500 GeV that can be upgraded to 1 TeV later Deliver 500 fb -1 in the first four years of physics operation

gallia
Download Presentation

The Engineering Test Facility for nLC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Engineering Test Facility for nLC ALCPG Victoria, BC July 30, 2004

  2. Introduction • Linear collider project goals: • Construct a collider with an initial energy of 500 GeV that can be upgraded to 1 TeV later • Deliver 500 fb-1 in the first four years of physics operation • Begin physics operation in 2016 (one year commissioning) to ensure concurrent operation with LHC • Discussion of project risk earlier this morning • R&D program should be focused on reducing project risk • Different stages of development process • Fundamental R&D – technology development or beam physics understanding • System engineering/integration – can it go together and does it work together • Industrialization and mass production – can components be produced

  3. The Engineering Test Facility(s) • Critical elements that the ETF must address: • E+ source target/capture • Damping ring beam physics • Main linac rf system production • Main linac emittance/jitter control • BDS collimators/stabilization/machine-detector interface • Some additional long-lead time or difficult components • Cannot and do not want to do this in a single test facility • Final configuration is subject to constraints due to resources and schedule and must be chosen with a goal of reducing the project risk

  4. Damping Ring Test Facilities • Beams are stored in the rings for a long time • Small (subtle) effects can have a large impact • Many novel effects will be important due to small emittances and tight stability requirements • Rings are quite different from other operating accelerators • ATF has been a very important test facility • Probably not possible to duplicate for cold design  adds some risk but how much and what can be done in other studies?

  5. Main Linac e-control • Given tolerance specs, instrumentation, and algorithms, the emittance performance is similar in warm and cold • Dge ~ 10nm over 5 to 10 km • Very hard to measure in a small facility • Complicated source – ATF is the only source that comes close • Not simple to scale to lower energies or amplify the effects • Real issue is performance/interaction of diagnostics and controls • Most algorithms are local  use dedicated tests of local systems • Rf structure girder alignment test • Cryomodule alignment study

  6. Main Linac RF Systems • Need to produce some number of complete rf sub-units • Rf subunit has 5-m of structures in X-band • Rf subunit has 36-m of structures in L-band • Demonstrate stable operation of a few units • With/without beam? • Beam is desired to verify rf operation stability and gradients • Forces a more rigorous approach • Be nice to use beam for centroid studies of trajectory control and verify instrumentation • Need engineering studies to optimize fabrication and lifetime • Don’t need to produce every component though

  7. Possible Examples of a big RF ETF

  8. e-control: Wakefield Effects • Primary tolerance is set by short-range wakefields • Girder of 4 structures must be aligned at 3 um level for NLC • In the ETF with a 300 um bunch length and 7.5e9, the kick of the beam tail is roughly 80 V * sqrt(Nrf) • At 1 GeV, this is ~0.1 urad as compared to the beam angular divergence >1urad for an emittance of 2e-8 • Very difficult to verify performance from emittance growth alone • Ways to increase the sensitivity: • Increase bunch length or bunch charge by ~5x • Use long-range wakes with 4- and 8-bucket spacing • This is a dedicated test of an rf-girder not a test in a long (or short) linac

  9. ETF Luminosity Study Implications • Even with nominal GLC/NLC emittances and 50-meter ETF cannot verify tolerances with emittance • ATF-III is still factors of five too insensitive to verify GLC/NLC performance requirements • Jitter measurements are best done with accelerometers • Alignment tolerance verification: • Bunch centroid or beam tilt for wakes and dispersion • Beam tilt: • 1.7 mrad in 300 um bunch  close to desired tolerances • Beam centroid • Works fine for dispersion • Use dedicated facility to verify wakefields and e-control

  10. The Engineering Test Facility(s) • Small scale (~1 GeV) rf test facility with multiple rf units • Include beam to verify low-level rf control and gradients • Include good (but not nLC) beam for e-control studies • Many other test facilities of smaller but similar scale • Dedicated studies of most relevant systems • Focused test can yield scientifically relevant information • Do NOT try to focus all effort (and resources) on one large showpiece which demonstrates little (but an ability to spend money – important but not essential at this time) • Caveat: major schedule delay would increase the importance of a large showpiece for political reasons

More Related