Weekly SummaryTevatron Department Meeting Tevatron Coordinator Xiolong Zhang/C.Y. Tan June 10, 2011- June 24, 2011 Tevatron Coordinator - FNAL 6/24/2011 1
Store Summary Tevatron Coordinator - FNAL 12/24/10 3
Store Summary Tevatron Coordinator - FNAL 12/24/10 3
Problems • T:HC49 trip aborting store 8805 • Pbar long. blown up for store 8809. • Pbar blown up during injection for store 8809 and 8810. • Store 8809 was cleanly abort due to a bad vacuum indication at B3. • St 8816 lost from lightning. • St 8830: C4 BPMs died, hard reboot did not bring it back.
Studies/Work Completed • HC49 PS replaced. • TRF3 trip during store 8812. • F4 flywheel repair (end of st 8820) • Topped up Tev LCW water. • C4 BPM processor replaced. • Have been smoothing much more aggressively between stores (all the way through lbseq 25). • Proton tune optimization @collision to reduce halo losses and improve lifetime; orbit smoothing. • Luminosity levelling
Initial Luminosity Tevatron Coordinator - FNAL 7
Pbars does not seem to blow up as much after 8635 (Apr 11) Apr 14 TRF2 PA changed. Correlated??? Tevatron Coordinator - FNAL
Luminosity Delivered for the Week Record week: Monday to Monday 78.4 pb-1. 13 Jun to 20 Jun. Accelerator Status 9 Friday, May 6, 2011
Studies Request • Hollow beam studies - Part of End of Run studies this week • Dedicated: Pbar longitudinal damping studies (Tan) • Shot set up: Proton damping (Tan) • EOS/MOS: Separator scan • Dedicated: Check DC beam at injection with bumper magnet (Hanna) • SOS: Luminosity Leveling (Moore) Tevatron Coordinator - FNAL 11