BQM-167A Parachute Recovery System Lean Event 8-12 Jan 07 Joseph Thibault 691 ARSS. 728 Armament Systems Group. BQM-167A Chute. Background. Current LMSI Contract Requirements : 210 SSATs Annually with a max surge of 16 per week Current Systems: MQM-107 & BQM-34A Capability
E N D
BQM-167A Parachute Recovery System Lean Event8-12 Jan 07Joseph Thibault 691 ARSS 728 Armament Systems Group
Background • Current LMSI Contract Requirements: 210 SSATs Annually with a max surge of 16 per week • Current Systems: MQM-107 & BQM-34A Capability • Pack 8 -- 10 per week with surge to 16 for both systems • MQM-107 -- 8 hour pack & 16 hour soak time • BQM-34 – 4 hour pack • BQM-167A Parachute System (June 2006) • 1.5 - 2 packs per week max • 45 total consecutive hours from start to finish to pack • Total of 75 – 100 sorties per year at a rate of 1.5 - 2 per week
WHY SO LONG? • BQM-167A Chute Designed To Recover worst case configuration (EA pod) • Requires: • Robust Reefing Line System -- Install Reef Line & Cutters & Verify • Vented Main Canopy • Main Canopy Is 5’ Diameter Larger But Must Fit In Same Size Can As MQM-107 • Drogue Chute – Similar Process As Main
Lean Event Charter • Sponsors: • Col Netzer – 728 ARSG (Eglin) • Col Winslow – 53d WEG (Tyndall) • Facilitator: Mr. Keith Johnson and Mr. David Arnsdorf, New Vectors • Team Leader: Mr. Joseph Thibault – 691st ARSS Logistics IPT Lead • Scope: Understand the process of packing the parachute system from out of the box until it is in the bag and certified • Team Goals: • Identify current workflow • Reduce time to prepare/pack AFSAT Parachute • Identify efficiencies/minimize workload impact to parachute shop • Results: • Identified current workflow • Evaluated preparations and pack times • Identified efficiencies/waste • Other recommendations and changes to reduce process and flow time
Team Participants AETC
Definitions • Flow time • Time it takes from Start to Finish to pack a complete parachute (from Supply) • Touch Time • Workers time actually touching the parachute • Includes two workers, working both the drogue and main parachute (Consecutively and collectively at times throughout the process) • Press and Soak Time • Total time both the drogue and main parachute were being pressed under the pressing ram • Soak Time is the time the parachute is sitting under pressure • Includes the 2 hours overnight soak for the drogue and 12 hours overnight soak for the main
Shop Processes Spaghetti Diagram
Design Improvement Opportunities (1) • Design Engineering Opportunities to eliminated or eased packing difficulties by system design changes • Key constraint is not to impact system form, fit, function, performance or qualification status • Main canopy deployment bag diameter • ¼ inch increase in diameter leads to 5% increase in available volume • Could lead to a significant reduction in soak time • Could impact consistent integration with the aircraft • Build oversize deployment bag and assess value and risk
Design Improvement Opportunities (2) • Design improvements / changes noted during review • Main and Drogue Canopies • Reefing cutter pocket changes • Slip on/off protective sleeve in place of fiberglass tape wrapping • Reduce amount of stitching to retain reefing cutter • Consider ring on anvil end of reefing cutter and use clip in place of stitching • Consider Velcro for cutter pocket closure in place of hand stitching • Investigate reusable temp tie to replace maroon cord on main canopy • Drogue Canopy • Install kill line during manufacture • Continuity check and daisy chain lines and as part of manufacturer’s final QA check
Design Improvement Opportunities (3) • Design improvements / changes noted during review (cont’d) • Reefing Line assembly / installation • Assess (test) potential for reduction in number of splice stitches • Use Teflon tape wrap only if Teflon grommet is not present • Use common consumables and techniques for installation of drogue and main reefing lines • Drogue Canopy Riser • Identify and use rubber grommets instead of taping Cut Knife • Supply with new equipment, and stock as consumable item • Other consumables / equipment issues • Source de-cored 550 lb Nylon (MIL-C-5040 Type IIa?) • Supply pre-cut 80# tapes for suspension line ties • Provide scissors designed to cut Kevlar • Manufacturer to pack refurbishment kit items in ‘ready to use’ state • Design and supply re-useable temporary ties (use Velcro or a buckle) • Design and supply ‘Extraction Fixture’ for packing press
Design Improvement Opportunities (4) • Design improvements / changes noted during review (cont’d) • Main Canopy Deployment bag • Reinstate application of Serial Numbers • Increase size and evenness of stow loops • Drogue Canopy Deployment bag • Reinstate application of Serial Numbers • Increase size and / or number of stow loops • Add hand tacks during manufacture to bag handle • Increase size of loop on canopy compartment closure flap • Increase size of slit in opposite canopy compartment closure flap • Reefing Lines (Main and Drogue) • Make markings bolder and less subjective (avoid color coding)
Design Improvement Opportunities (5) • Soak times • Investigate the potential of reducing soak time based upon measurable parameters (30 minutes,1 hr, 2 hr and 12 hour soak times) • TO change to allow riggers options to soak as require, as long as pressure is not exceeded • Pressure can not substitute for Time • Collate data on ‘packing difficulty’ (subjective) as a function of perceived key measurable parameters: • Parachute weight • Temperature • Humidity • Track significant sample by parachute and deployment bag serial numbers • WEG to track the baseline over time
Action Plan53d WEG • Create a pan with foam cutouts for tools to allow easy movement from locked cabinet to cart • Procure needed specialty tools: - T- Handles, Hemostats, Packing Fids, Bodkins, Sewing Palms, Line Hooks, etc. • Put sewing machine on wheels • Review manning options to meet current requirements • Third person for folding main canopy, to pre-assemble leash and as a support/repair person • Second shift • Track status of parachutes being packed • Land/Water recovery and issue by Supply • Track flow times and press and soak time to establish baselines Possibility of one to one and a half hours (1 to 1.5) savings in process time
Action Plan691st ARSS • Engineering Study via the AFSAT contract: • Look at all options to improve efficiencies and eliminate waste during the packing of the parachute • Look at all of the recommendations documented during this Lean Event • Status: 691st plans to task the contractor to provide recommendations and cost estimate; will review and make cost effective changes, as appropriate • Establish procedures to allow fast response to technical questions from packers to engineers • Status: Via on-site CEi CLS representative Possibility of up to seven (7) hours savings in process time and four (4) hours of Touch Time
Impacts • Current LMSI Contract Requirements: 210 SSATs Annually with a max surge of 16 per week • How many Riggers do we need? • 53d WEG review total workload with LMSI • Takes two people, two days and one over night soak to pack one chute • Should be able to pack 2.5 chutes per week • 80 hours (2 people x 40 hours) • Use 80 hours per week to produce 2.5 chutes as a guide until specific data can be collected and validated • Variables • BQM-167A Parachute Packing Options • 117 Chutes Annually • 3760 hours (2 people x *1880 hours) • 176 Chutes Annually • 5640 hours (3 people x 1880 hours) • 210 Chutes Annually • 6720 hours (3.57 people x 1880 hours) * 1880 hours is the normal standard used to document one man-year of effort
Summary • Overall Future State Estimated Reductions • Flow time: 2 hrs 20 min (8%) to up to 8 hrs 20 min (30%) • Touch Time: 4 hrs and 20 min (15%) • Press and Soak Time: 49 minutes (3%) to up to 6 hrs 40 min (24%) • Flow Times: Current and Future State 28 Hours Jan 2007 20 Hours Future State
Lessons Learned • Use the SMEs to analyze and improve each step • Benefited from Irvin design and production personnel as team members • Stay out of the way of the workers when observing • Limit team sidebars – stay focused • Synergy – brainstorm methods of reduction • Allot enough time to do the event (45 hour process) • Technical expertise in process and design for materials is needed • Break into 2 groups to analyze drogue and main chute simultaneously • Record times on brown paper when timed at press
Reefing Line & Cutter Box Stitch reefing line splice Reefing Line Cutter
Leash Assembly Leash Assembly 125’ Long
Current/Future State TimesExpected Improvement Current State Times – 28 Hours and 1 Minute Future State Times – 25 Hours and 45 Minutes • Expected improvements represents a reduction of 2 hours of overnight soak times and 4 hours 20 minutes reduction In touch labor; reducing Flow Time by 2 hours and 16 minutes
Current/Future State TimesBest Case Improvement Current State Times – 28 Hours and 1 Minute Future State Times – 19 Hours and 40 Minutes • Best Case represents a reduction in 7 hours of overnight soak times and 4 hours 20 minutes reduction In touch labor; reducing Flow Time by 8 hours and 21 minutes
Variables to Packing Times • Variables • BQM-167A only, no other work load considered • Best case time of 28 hours for packing a parachute • Will take longer to pack a parachute from land or water recovery • Does not consider finding damage and repairs • Touch time is 17 hours; other times the parachute is being Pressed and Soaked (top two sub bullets will off set this time) • Does not consider normal set up, clean up, inventory, phones, e-mail, meetings, etc. • Hours observed were documented while workers were under a stop watch and they took very few breaks, hardly answered the phone and no other interruptions • Establish Metrics to track times • Validate times after changes are made and learning curve completed