An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TEAM 1 On Wings like a penguin

  2. Team Members Phil Baah-Sackey, Joe Englin, Chris Lowell, Eu Sung Chung

  3. Project Description • Build an amphibious air cushion vehicle • Approximately 12 x 6 ft, triangular shape • Two engines: one for thrust, another for lift • Lift engine will duct air into skirt using air splitters • Should seat two passengers (~400 lbs) • Attain at least 5 mph

  4. Hull Design • In order to best use resources, a donated engine will be used to lift the craft. • Hull dimensions were determined based on the engine horsepower. • The hull was constructed primarily out of donated insulating foam.

  5. Propeller Design • First the drag on the craft at the desired speed was determined. • From this the required thrust from the propeller was determined. • Using this data the angle of the propeller blade was determined.

  6. Status • Hull completed. • Lift duct installed. • Lift fan completed. • Thrust duct construction started. • Thrust propeller construction started • Hubs and backing plates being made • Engine mount construction begun.

  7. What’s Next? • Cut thrust propeller. • Install thrust duct. • Construct cockpit. • Build rudders and steering. • Cut and install skirt. • Finish metal component fabrication. • Cruise for chicks.