290 likes | 477 Views
L. Pontecorvo. 4. 6. 3. 7. 2. 8. 1. 9. 16. 10. 11. 15. 14. 12. MDT Status: Installation and Commissioning. 5. Missing 9 stations. Outline. Installation and infrastructure status Commissioning Status Sector Commissioning strategy Integration with other ATLAS sub-detectors
E N D
L. Pontecorvo 4 6 3 7 2 8 1 9 16 10 11 15 14 12 MDT Status: Installation and Commissioning 5 Missing 9 stations
Outline • Installation and infrastructure status • Commissioning Status • Sector Commissioning strategy • Integration with other ATLAS sub-detectors • Results from Toroid run in November
Installation and Positioning • 673/682 installed: missing 6 sideA + 3 side C • After installation on the rails must be positioned • specs:~2mm; 2mrad • Main limitations: Interference with other sub-systems services and access • Very tricky: BIR/BIM in sectors 11 and 15and BMS all sectors and BOL/BOS external chambers • It goes very fast once we have access + OK from TC • 575/682~84% of the barrel is positioned Feet region Gray: not installed Light green: installed Dark green: installed AND positioned
Cables and Gas • All MDT optical and control cables (~200) from USA15 to barrel PP installed in 2005 - All patch panels installed - All Alignment, - All CANBUS DCS cables - All MDT RO and TTC fibers • All LV and HV cables installed • All DCS daisy chain installed on positioned sectors • > 70 % of Optical patch cords installed Rack dressing for upper sectors well under way
Gas system status • All manifolds and valves installed • 15 UX racks operational • All (~300) pneumatic valves ok; • All barrel racks equipped with zeolite filters • Connection of chambers to manifold following chamber positioning • Systematic leak tests of combined system using PVSS control: • Leaks found in: • BIS S2: two chambers • BIS S8: one chamber Repaired • BIS S10: five chambers • BOL S1: not identified yet • BOLS15 Repaired
Power supply: LV/HV • In 2007 CAEN will deliver: • 80% of RPC and barrel LVL1 PS (HV/LV) • 80% of TGC • 40% of the LV for MDT • 25% of the HV for MDT-CSC • MDT Commissioning issues: • HV/LV boards for sectors 5 & 6 Available • Need more boards for the commissioning of other sectors Followed by A. Lanza
USA15 - DCS and Alignment • TTC Crates ready both for Barrel and End-Cap (E. Pasqualucci) • All ROD-ROB fibers routed (Italian Techs) • CANbus PS and DCS PCs for all Barrel • Full Barrel alignment system • HV-LV DCS-PCs for Barrel (also for RPCs) (P. Valente, G. Aielli) • Sectors 5, 6, 3A & 4A RODS are available and cabled
Commissioning Strategy All stations arrived at ATLAS after cosmic ray certification and retested at SX1 (now dismissed) Due to late availability of services level-by-level strategy adopted in the pit • Level I:fast test of station integrity: gas tightness, broken wires • Level II:check basic functionalities with provisional services: DCS, FE elx. behavior, in some cases also noise runs • Level III:check full functionality and sign-off of complete sectors – done only whenfinal services available MDT+RPC/LVL1: • Full test up to cosmic ray run • First determination of optimal working point • Dead channels maps, … After Level III Full SECTORS ready to be integrated in ATLAS: commissioning Phase II
MDT test up to Level II • MDT: 216/630 tested • Mainly Inner chamber difficult to access later (BIL and BIS) • Up to now test done using provisional services • Since January moved to final services sector 5 and 6 DONE with FINAL services • Many problems found and fixed: mainly damaged components: ELMB, CSM, cables, fibers,…
LVL III -Full Sectors commissioning schedule • Constraints • Possibility/Access to position stations • Availability of services + CAEN Power supplies • Strategy: start from top sectors • Schedule • Sector 5 and 6: April/May (Under way) • Sectors: 3–4 7-8 1-2 9-10 13-14-12 11-15-16 • Month: June July Aug Sept Oct. Nov. • PS schedule: October ‘07 ~80% of RPC/LVL1 and only 40% of MDT LV expected: • After sector 5/6 move around “Jolly” set of CAEN boards to commission all other sectors (depending on delivery from CAEN) • Only part of the barrel integrated in ATLAS by fall 2007
Phase II commissioning: Integration in ATLAS • Integration of sector 13 in March combined ATLAS run: • MDT: ROD-ROS readout – HV/LV DCS integrated • RPC/LVL1: VME readout – muon trigger via MUTCPI-CTP • Starting from June integrate sector 5A & 6A (after we have commissioned it): • Use these sectors as benchmark for phase II to include all final features needed in ATLAS: DCS, DSS, chamber initialization, configuration DB, high level muon trigger, Data analisys • 1 FULL CAEN PS set left on this sector • Other sectors can be added later once are signed off depending on PS availability
MDT HV-LV DCS integration • MDT HV-LV DCS succesfully integrated in Central DCS. • 1 PC, 1 branch controller, 6 boards in 4 crates in UX15 • Controlled from ATLAS Global Control Station • Project almost completed still to be finalized: • Archiving • Configuration database • Condition database • INFN- University of Athens joint project
BIL BML BOL BOF BOF Sector 13 run: set up Full weekend of data taking with 13 feet chambers during the Barrel Toroid test in November • 13 Muon stations read-out • LVL1 muon Trigger provided by 3 BML RPC/LVL1 and distributed via MUCTPI + CTP to muon system BIL 1 BIL 3 BIL 2 Side A BML 3 h=0 BOL 3 BOF1 BOF3
Sector 13 data • Sector 13 cosmic data used as benchmark to test commissioning procedures for sector sign-off • MDT: • Noise • Dead channels • Drift behavior • Preliminary alignment • RPC/LVL1: • Noise • Efficiency • Working point optimization • LVL1 timing • Automatic tools to perform stations sign-off under preparation
MDT Inefficient tubes from chamber profile dead tubes Silvia Franchino (INFN Pavia)
MDT Noise rates t< t0 per ogni tubo: Offline analysis Typical physical background in barrel ~10kHz GNAM result Online monitoring 1.4% occupancy Silvia Franchino (INFN Pavia) 15 / 12 / 2006
Impact of magnetic field on MDT drift B field expected to change drift-to-radius relationship by Lorentz angle
Installation and Commissioning Coordination • Overall coordination: • F. Cerutti (INFN) & L. Pontecorvo (INFN) • Run coordination: • S. Vlachos (CERN) & D. Boscherini (INFN) • MDT DCS: • P.Valente (INFN) S. Zimmermann (Friburg) • Gas MDT: • T. Meyer (CERN) • RPC DCS : • G. Aielli (INFN) • Gas RPC: • R. De Asmundis (INFN) • DAQ: • E. Pasqualucci (INFN) • Trigger: • S. Veneziano (INFN) • Service Installation: • A. Lanza (INFN)
Conclusions • Installation almost completed • left over only due to interference with other detectors or unavailability of BOG chambers • Services Installation: • Cabling almost finished moving to rack dressing • DCS, Alignment and DAQ systems well under way. • Level III Sector commissioning starting now • Very tight schedule and shortage of final power supply. • Sectors will be available for integration in ATLAS • Toroid test with cosmic rays showed good results
Richieste finanziarie • Nuovo finanziamento per contratti con CAEN (Lettera Referee di A. Lanza): • 55 KEuro per contratto per manutenzione software e aggiornamento firmaware • 12.5 KEuro per Filtri sul sistema di potenza • Costruzioni apparati : Pavia
Alignment Commissioning Systematic check of the 5817 optical lines has started: • Difficulties: mainly conflicts with gas-pipes, cable trays, support structure,… • Main emphasis now on the 117 projective lines (backbone of the Barrel alignment) ~only 20 lines are working today… Clashes with struts found in 28 cases
Cabling II • Inner Layer • Cabling of inner layer is mostly done • 244 LV, 488 HV cables, 244 alignment, 448 pairs of optical patch cords in total • All HV, LV alignment cables installed • DCS daisy chain installed on positioned sectors • Almost all of RO&TTC patch cords installed. • Midlle Layer • 178 LV, 356 HV, 178 alignment cables, 356 pairs of optical patch cords • All LV and HV cables installed • DCS Daisy chain installed on positioned sectors • ~75% of RO&TTC patch cords installed, installation is ongoing
Cabling III • Outer Layer • Cabling of MDT outer layer is mostly done • 202 LV, 404 HV cables, 202 alignment, 404 pairs of optical patch cords in total • All HV, LV and alignment cables installed, few HV cables still to be re-arranged • DCS Daisy chain installed on positioned sectors • ~75% of RO&TTC patch cords installed, installation is ongoing
Leak Test • Systematic leak tests of combined system using PVSS control: • Tested until now: (red = test currently underway) (315 in total) • BIS: S2, S4, S6, S8, S10, S16 • BMS: S2, S4, S6, S8, S10, S16 • BML: S3, S5, S7, S13 • BOL: S1, S3, S5, S7, S9, S11, S15 • BOF/BOG: S14 • Work still to start on : BIL, BIR, BIM, BOS, EIL4 • Leaks found in: • BIS S2: two chambers • BIS S8: one chamber Repaired • BIS S10: five chambers • BOL S1: not identified yet • BOLS15 Repaired • All other leaks (mostly in plumbing) identified and corrected. • Ongoing work: • Connect remaining chambers (~33%) to valves (ongoing - 3 months). • Finish leak tests (synchronous with chamber connection) • Repair work according to damage found.
Muon DAQ Integration • Sector 13A + 2 chambers of sector 5 • 2 crates, 3 MROD • 11 MDT chamber • 2 ROS, 3 s-link • RPC SL board, 1 crate • ROD emulator used • TTC signals sent through ROD prototype • Connected to ROS via Ethernet • Muons + Calorimeters +CTP+MUCTPI partition built • MDT online histogram viewed by OHP • Connection to Data Quality desk