An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Laundry planninigguideHotels

  2. DETERMINATION OF DAILY CAPACITY OF HOTEL LAUNDRY INPUT DATA: • Number of beds in the hotel • The hotel occupancy (%) • Number of seats in a restaurant • Number of staff uniforms • Laundry labour time (hours)

  3. Indicative weight of dry linen • Restaurants: 0,5kg per seat Hotel 1 star: (without restaurant) Hotel 2 star: (without restaurant) Hotel 3 star: (without restaurant) Hotel 4 star: (without restaurant) Hotel 5 star: (without restaurant) 1kg/room/day 2kg/room/day 3kg/room/day 4kg/room/day 5kg/room/day 1person 1person 1person 1person 1person • Notes: • Hotel ratio to be multiplied by 1,6kg per extra person • For 4 star or higher hotels we can add an extra 5% extra for the • laundry service for guests

  4. Proportion of linen per type of hotel • Flat linen (bed sheets, table cloths & blankets) to be ironed in ironers • Towel linen ( hand & bath towels, bath robes ) to be dried in tumble dryer

  5. Formul of calculation C = Q * N * O * P * 7 days/ H • C=Capacity of linen to wash per hour • Q=Ratio for the hotel • N=Number of rooms • O=Occupancy • P=Proportion of linen per type of hotel • H=Working hours per week

  6. EXAMPLE • 4 stars hotel, 250 beds • Occupancy 80% • 120 seats in the restaurant • 50% of clients stay at just one night, the others variously • 15 employees • Laundry operating time – 40 hours per week

  7. EXAMPLE 1 -4 stars hotel, 250 beds Room set: C = Q * N * O * P * 7 days/ H 4 * 250 * 0,80 * 0,5 * 7 = 2800 per week Table set Daily restaurant – 120 seats → 30 tables with tablecloths 30 * 0,6kg = 18 kg/day Kitchen staff 15 personnel: 15 * 1kg = 15 kg/day TOTAL KILOS PER WEEK: 2800 + (18 x 7) + (15 x 7) = 3031 kg/week TOTAL KILOS PER DAY: 3031 kg/7 days = 433 kg/day

  8. EXAMPLE 1 -4 stars hotel, 250 beds PROPOSAL OF TECHNOLOGY - WASHING Washing requirements: 433÷ 6* = 72 kg/cycle TOTAL KILOS PER DAY NUMBER OF WASHING CYCLES PER DAY TOTAL KILOS PER WASHING CYCLE WASHING MACHINE FS40 1:10 – 40 kg WASHING MACHINE FS22 1:10 – 22 kg WASHING MACHINE FS16 1:10 – 16 kg 78 kg/cycle * Experiences show that washing machines with electric heating are able to make just 6÷6,5 cycles/shift.

  9. EXAMPLE 1 -4 stars hotel, 250 beds PROPOSAL OF TECHNOLOGY - DRYING Drying requirements: 434÷ 8 x 35% = 22 kg/hour TOTAL KILOS PER DAY NUMBER OF HOURS LAUNDRY IS OPERATED PER DAY % OF TOTAL TO BE TUMBLE DRIED TOTAL KILOS TO BE DRIED TUMBLE DRYER T24 1:35* - 15kg TUMBLE DRYER T16 1:35 - 10kg 25kg/hour Drying time lasts approximately 45 min. + 5 min. cooling time. * Recommended load rate for terry linen.

  10. EXAMPLE 1 -4 stars hotel, 250 beds PROPOSAL OF TECHNOLOGY - IRONING Flatwork requirements: 434÷ 8 x 65% = 35 kg/hour TOTAL KILOS PER DAY NUMBER OF HOURS LAUNDRY IS OPERATED PER DAY % OF FLATWORK CONTAINED IN TOTAL TOTAL KILOS OF FLATWORK PER HOUR For figured capacity we can choose an appropriate ironer with capacity closest to calculated → I50-200 with capacity 50kg/hour.

  11. EXAMPLE 1 -4 stars hotel, 250 beds LAUNDRY PLAN – MIN. AREA 40m²