370 likes | 499 Views
Project Cost Estimating A Synthesis of Highway Practices. Presented by: Christine M. Fiori, Ph.D., P.E. Arizona State University. Arizona State University Research Team. Clifford J. Schexnayder, Ph.D., P.E. Eminent Scholar Sandra L. Weber, Ph.D., P.E. Associate Professor
E N D
Project Cost Estimating A Synthesis of Highway Practices Presented by: Christine M. Fiori, Ph.D., P.E. Arizona State University
Arizona State UniversityResearch Team • Clifford J. Schexnayder, Ph.D., P.E. • Eminent Scholar • Sandra L. Weber, Ph.D., P.E. • Associate Professor • Christine M. Fiori, Ph.D., P.E. • Assistant Professor • Jonathon E. Burns • Graduate Student
Overview • Introduction • Methodology • Data Analysis • Results • Recommendations • Conclusions
Why Estimate? • Estimates influence: • allocation decisions • influence long-term spending plans • serve as a framework for accounting and control • Serves as a baseline to measure project management performance • Estimate also works the project into the DOTs five (5) year project plan
Research Focus • Review of DOT estimating practices • Primarily concerned with pre-bid estimates • Conceptual estimating procedures were also examined • Current challenges of large transportation reconstruction projects in urban environments.
Methodology • All fifty DOTs were contacted and interviewed • Points of contact were generated using an AASHTO committee member list and by researching state DOT web sites. • Each DOT was electronically forwarded an advance copy of the survey and an interview was scheduled.
Interview Goals • Document estimating practices of state DOTs • Ascertain methods for the resolution of discrepancies between DOT estimates and bid prices • Identify problems that remain largely unresolved across the country • Determine practices that produce estimates within a + 5% variability between the DOT estimate and contractor bid.
Data Analysis • Project ranges were established, allowing differentiation between DOTs • Determined program size • Efforts were made to maintain a sufficient number of DOTs in each category to support the validity of conclusions
Project Data • Four Ranges of Project Cost • $10 to $25 Million • $25 to $100 Million • $100 to $200 Million • Greater than $200 Million
DOT Program Classification • Projects Greater than $10 Million • Small DOTs < 20 projects • Medium DOTs - 21-75 projects • Large DOTs - 76+ projects
How are DOTs Estimating? • Conceptual Estimates • Contingencies • Life Cycle Cost • Pre-Bid Estimates • Computer Use • Personnel • Training
Conceptual Estimates • 31 DOTs use estimating cost data that are based solely upon historic cost averages for similar projects • 18 other states determine quantities based on the conceptual design and follow the same procedures that are used for pre-bid estimates • 3 of these states prepare detailed estimates based on preliminary design information. • One state reported allowing engineers to use whatever method they thought best to generate conceptual estimates.
Life Cycle Cost Analysis • 27 DOTs complete on pavement materials only • 14 DOTs perform during the conceptual phase • 9 DOTs were unaware of any analysis performed during project development
Pre-Bid Estimates • Three methods • Historical Data • Detailed Estimate • Combining historical data with actual cost development
Detailed Estimating • Requires a great deal of knowledge • Construction methods • Supply systems • Labor markets • Method productivity • Requires more time to prepare a detailed estimate • 19 states perform detailed estimates for major work items, using historic databases to track costs • Dedicated estimating sections whose personnel have the necessary construction experience. • Use computer software that supports estimate development.
Computer Use • Most widely used estimating software is the TRNS*PORT Estimator module • 23 were using the software • 7 using Bid Tabs • 1 uses HCSS Heavy Bid • 1 uses AutoCAD – quantity takeoff • 18 use their own in house program
Personnel • Experience <1 year to >40 years • Some DOTs facing a shortage of qualified estimators due to retiring of experienced personnel • 26 DOTs have separate dedicated estimating sections • 24 DOTs personnel prepare estimates as an ancillary duty
Training • 10 DOTs have formal estimator training programs in place or under development • Mentoring and on the job training (OJT) are used extensively by all DOTs • 16 DOTs have manuals that cover estimate preparation • 2 DOTs are in the process of developing estimating manuals • 32 DOTs do not have formal written guidance for estimate preparation that can be referenced by the estimator
Estimate Items • Overhead • Contractor Mobilization • Demolition Work • Traffic Control • DOT supplied materials • Unique and Specialty Items
Incentive Funds • 26 DOTs have incentive funds programmed in the construction estimate • 9 DOTs have incentive funds that come from other projects that are below budget • 10 DOTs have incentive funds that are paid out of project contingency funds • 5 DOTs currently have no incentives program in place
Other Estimating Considerations • 23 DOTs operate with contingency budgets, 27 DOTs without • 33 DOTs adjust their estimate based on schedule, 17 do not • 38 DOTs adjust their estimates based on special conditions, 12 DOTs do not • 38 DOTs adjust their estimates based upon the location within the state, 12 DOTs do not
Project Award • 26 states require no action for award on bids below DOT estimate • 12 DOTs require justification if it is more than 10-30% below DOT estimate • Bids 5-25% above DOT estimate must be reviewed depending on the state laws • 8 DOTs require all projects be reviewed prior to award
Collusion Detection • 7 DOTs do not actively attempt to detect • 11 DOTs require contractors to sign a form that is submitted with the bid • 34 DOTs run a bid history for each project and contractor to see if there is a pattern in project awards
Releasing Information • 20 DOTs release during project planning an anticipated project cost range • 22 DOTs release after award all bidder information and total project amount • 10 DOTs release the information at the bid letting • 19 DOTs release a copy of the DOTs estimate including quantities and unit costs
Challenges of Major Projects • Stretch available resources to the limit ─ labor, material, management skill, and information systems • Have a high profile with political subdivisions and the public • Are very noticeable by regulators • Are unusually long duration projects and there is less likelihood of maintaining continuity of management
Reasons for Cost Overruns • Protection of the natural environment from the effects of the project • Protection of the public health and safety from the effects of the project • Controls on the use of labor or procurement • Other government standards or regulations • Whether or not the project embodied any first-of-a-kind technology.
Recommendations • Estimating Guidance • Conceptual Estimates • Design Phase Cost Control • Pre-Bid Estimates • Award • Release of Estimate • Design Build Projects • Projects Valued Over $100 Million
DOT’s must consider: • How are estimates usually done? • What do we need to do to get a valid estimate? • How do we develop a reliable cost estimating and validation process? • The estimating process must evaluate variability and risk using logical, reasonable statistical (probability) methods
To ensure future success DOT’s must . . . • Avoid false precision • Relate contingency to the layman’s everyday experiences with uncertainty • Invest in continuous and transparent QA/QC of your estimating processes