1 / 20

Transmission Planning Code – Design Margin Update

Understand the revised Design Margin used in long-term planning analysis for gas transmission. Learn about the purpose, application, and effects of the Design Margin. Review of 2008 findings and recommendations for components in the planning process.

garyparker
Download Presentation

Transmission Planning Code – Design Margin Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Transmission Planning Code – Design Margin Update Transmission Workstream, 4th February 2010

  2. Introduction • National Grid NTS has revised the Design Margin used in long term planning analysis following a review by Advantica (now GL Industrial Services UK Ltd.) • Intention is to consult on the required changes to the Transmission Planning Code in February 2010 • Following slides describe the Design Margin and how it is used, to supplement the consultation process

  3. Design Margin – Brief Overview (1) • National Grid NTS must be able to maintain sufficient pressure for gas leaving the NTS, to ensure safety and security of supplies to downstream parties (DNOs, directly connected customers) • Planning and development of the system is undertaken over a ten year timescale but must consider uncertainties present ahead of and within the gas flow day such as • NTS supply levels, flow profiles, distribution and supply availability • NTS demand levels, flow profiles and distribution • Plant availability • Design Margin is applied as a % uplift to forecast flows within long term planning analysis to account for uncertainties or unplanned events • Key assumption is that Operating Margins gas is available within 2 hours of the event occurring and will be used to support the system from this time onwards

  4. Design Margin – Brief Overview (2) • Design Margin in use since 1986, reviewed in 2000 and 2008 • Level of design margin required is calculated through statistical modelling of within day events and network analysis to verify proposed design margin • Applied automatically within planning software to increase the flows used within network models • Effect is to slightly exaggerate the pressure drops across the system • Provides a small degree of pressure cover across the system for a limited time until Operating Margins gas can be deployed • If system is constrained, or only just meets required pressure and flow obligations, introducing a Design Margin may signal that a reinforcement is required

  5. Design Margin Review 2008 • National Grid NTS recently commissioned a review from Advantica to consider • Previous flow margin studies undertaken in 1986 and 2000 • Statistical analysis of within day variations over a 2 year period • Network modelling to confirm level of design margin required • Rationale behind the design margin and the operating margin, and whether these could overlap • Main conclusion was transmission component no longer required due to • Development of contractual/market-based commercial regime • Increased use of supply and demand scenarios to understand sensitivity away from Base Case flows • Additional pressure cover at system extremities was recommended • Study confirmed that the design margin and operating margin are used for different purposes and therefore do not overlap

  6. Design Margin Components

  7. Transmission Component • Typical lead-times for NTS investment projects are 3-4 years from inception • Peak day supply and demand forecasts may change in this period • NTS must be maintained to the 1-in-20 peak day security standard and to ensure gas is delivered at the required pressures to downstream parties • Transmission component intended to counteract annual plan changes due to • Geographical redistribution of supply between entry points and demand between exit points • Demand variation due to changes in economic assumptions • Supply level variations • Uncertainty in model pipe efficiency parameters • Original requirement for transmission component driven by uncertainty around central case planning assumptions • Increased use of scenario planning has reduced the requirement to model uncertainty by use of a fixed uplift factor

  8. Transient Component • Long-term planning analysis is conducted assuming 100% plant availability including upstream infrastructure • Plant failures and supply outages may occur in reality • Daily balancing regime means that instantaneous/cumulative NTS supply and demand levels are often not balanced within day • Total supplies may lag behind demand especially if back-loading is present • Linepack (NTS gas stock) may be depleted in some areas and increased in other areas as a result • Transient component allows for within-day effects (and is still required) • LDZ demand forecast error • Offshore supply outages leading to temporary reductions in supply • Supply (re)nominations requiring NTS reconfigurations • Compressor trips

  9. DesignMargin - prior to 2008 review • Varies from 0-5% depending on type of analysis undertaken

  10. Design Margin – recommendations from 2008 review • Review concluded Transmission component not required due to • Development of contractual/market-based commercial regime • Increased scenario analysis to understand sensitivities around TBE Base Case flows • Additional pressure cover for sensitive geographic locations required

  11. Pressure Cover • Use of a Design Margin inherently provides pressure cover for operational circumstances as pressure drops are slightly exaggerated in long term planning analysis • Extremities of the system may still be sensitive to unplanned plant failures e.g. where they are immediately downstream of a compressor station • Additional pressure cover can be calculated by simulating the compressor trip at different times during the gas day to determine • The pressure cover implied by the Design Margin • The pressure decay immediately after the compressor trip, up to two hours after the trip • Additional pressure cover is applied as an increment to the Assured Offtake Pressures at the extremity to ensure minimum pressures are not breached within two hours of the compressor trip • Two system extremity points are currently considered

  12. Transmission Planning Code • National Grid NTS has a licence obligation to maintain a Transmission Planning Code to describe how it undertakes the planning and development of the network • Current version available at: http://www.nationalgrid.com/uk/Gas/TYS/TPC/ • During development of the planning code, National Grid discussed its intention to revise the value of the Design Margin used within its long term planning models • Presentations available on Joint Office website (TPC Workshop 3 on 5 June 2008) • Design Margin revised from 5% to 2% following a review by Advantica (GL) in 2008 • Design Margin described with National Grid’s Safety Case for the NTS and therefore required discussion with the HSE before modification

  13. Transmission Planning Code – Required Updates • Modifications to Safety Case are now complete and National Grid will be launching a consultation in February 2010 to update the Transmission Planning Code as required by its NTS Licence • Further consultations are planned in 2010 to reflect changes in the Exit regime and Planning legislation • Please contact Chandima Dutton on 01926 653231 or chandima.dutton@uk.ngrid.com if you wish to discuss any aspects of the Transmission Planning Code • Design Margin will be kept under review • Design Margin value will be stated in Transmission Planning Code rather than the Safety Case • Changes will still require discussion with HSE

  14. Appendix: Example

  15. Example: Design Margin impact after a compressor trip Compressor 1 Supply A Demand C Supply B Compressor 2 Operating Margins gas in store, availability within 2 hours • Example assumes that only one supply/demand scenario used for long term planning • In reality various sensitivities around the TBE Base are considered to ensure that a range of flow patterns and flow levels are modelled • Explicit modelling of sensitivities and obligations reduces level of design margin required

  16. Long Term Planning Case 1: No Design Margin appliedSystem meets min pressure requirements design flow = 40 mscmd Supply A Demand C supply pressure = 70 bar(g) min pressure = 40 bar(g) Supply B modelled pressure = 40 bar(g) design flow = 60 mscmd • Pressure drop calculated across system = 30 bar(g) • Min pressure at Demand C just satisfied • Long term planning analysis identifies no reinforcement requirement

  17. Operations Case 1: No Design Margin appliedWithin-day compressor trip flow = 40 mscmd Supply A Demand C supply pressure = 70 bar(g) min pressure = 40 bar(g) Supply B system pressure = 40 bar(g) before trip decays rapidly after trip flow = 60 mscmd • Compressor trip causes extremity pressure to fall below min pressure before operating margins gas can be brought online Operating Margins gas in store, 2 hours availability

  18. Long Term Planning Case 2: Design Margin applied e.g.5% used in planning analysis design flow = 40 x 1.05 mscmd Supply A Demand C supply pressure = 70 bar(g) min pressure = 40 bar(g) Supply B modelled pressure = 38.5 bar(g) design flow = 60 x 1.05 mscmd • Pressure drop calculated across system = 31.5 bar(g) • Min pressure at Demand C not satisfied • Long term planning analysis identifies that reinforcement is required

  19. Long Term Planning Case 2: Design Margin appliedSystem reinforced to meet min pressure requirements design flow = 40 x 1.05 mscmd Supply A Demand C min pressure = 40 bar(g) Supply B modelled pressure = 40 bar(g) design flow = 60 x 1.05 mscmd • Pressure drop across system = 30 bar(g) after reinforcement • System meets required pressure at extremity • Pressure cover of 1.5 bar(g) at Demand C has been provided by Design Margin for operational use Reinforcement

  20. Operations Case 2: Design Margin appliedWithin-day compressor trip flow = 40 mscmd Supply A Demand C min pressure = 40 bar(g) Supply B system pressure = 41.5 bar(g) before trip and decays rapidly after trip flow = 60 mscmd • Extremity pressure affected by compressor trip, however pressure cover of 1.5 bar(g) is used to absorb impact of trip for two hours • After 2 hours, Operating Margins gas assumed to be available Operating Margins gas in store, 2 hours availability

More Related