SPSRB Project Plan on “MIRS-Based Tropical Cyclone Intensity and Structure Estimation”. Project Lead: John Knaff Backup Project Lead: Liqun Ma August 8, 2013. Outline. Integrated Product Team (IPT) Requirements Capabilities Assessment IT System Architecture Plan of Operations
E N D
SPSRB Project Plan on “MIRS-Based Tropical Cyclone Intensity and Structure Estimation” Project Lead: John KnaffBackup Project Lead: Liqun Ma August 8, 2013 V14.1 Jun 2009
Outline Integrated Product Team (IPT) Requirements Capabilities Assessment IT System Architecture Plan of Operations Project Milestones Funding Spending plan and tasks V14.1 Jun 2009
Integrated Product Team (IPT) IPT Lead: John Knaff (STAR) IPT Backup Lead: Liqun Ma (OSPO) NESDIS team: STAR : John Knaff, Mark DeMaria OSPO : Liqun Ma, Gregg Gallina, Antonio Irving OSD : Tom Schott Others : Jack Dostalek (CIRA), Andrea Schumacher (CIRA) User team Lead: Gregg Gallina (NESDIS/OSPO/SAB) Others: Sam Houston (NOAA/NWS - CPHC), Edward Fukada (DOD, Joint Typhoon Warning Center), Christopher Landsea (NOAA/NWS – NHC) Oversight Panel (OP) lead: ICAPOP V14.1 Jun 2009
Requirement Requirement(s) This project is justified by a 2001 SPSRB request for Microwave tropical cyclone intensity product There is support though no requirement from NHC, CPHC and JTWC since the requirement has been met. User community: Tropical cyclone forecasting centers (NHC, CPHC, JTWC, WMO Regional Meteorological Specialized Centers RMSCs), Marine forecasters NOAA Mission Goal supported: Serve Society's Needs for Weather and Water Information Mission priority: Optimal Supports JTWC/NHC/CPHC requirements to estimate tropical cyclone intensity Supports JTWC/NHC/CPHC requirement to determine whether a cyclone is tropical, subtropical or extratropical Supports JTWC/NHC/CPHC requirements to estimate and forecast radii of 34-, 50-, and 64-kt winds Supports secondary users at other global tropical cyclone warning centers V14.1 Jun 2009
Capabilities Assessment V14.1 Jun 2009
SHORTFALLS Timeliness The increase in the number of AMSU A instruments from 3 to 6 should improve the timeliness of microwave intensity estimates from approximately 8 to 9 hours to 5 to 6 hours on average. Metop’s orbit fills the 930LST POES data gap. Accuracy of Product Accuracy is expected to remain the same as the current products Define how product development addresses shortfalls The addition of Metop and additional POES via MIRS will increase the timeliness of the AMSU-based tropical cyclone fixes Since the TC structure algorithm uses a 700 km data swath (~1/2 of the data) additional satellites increase the overall number of TC intensity/structure estimates. Benefit These products are used at JTWC, NHC, CPHC and WMO RMSCs for the diagnosis of tropical cyclone structure including intensity, size and warm/cold core structures Impact if not funded If not funded the AMSU intensity and structure products will continue to have the same timeliness and may actually degrade if NOAA 15, 16 or 18 instruments should fail. AMSU-A instrument capabilities on Metop and additional POES will remain underutilized. No AMSU-based TC estimates near 930 LST V14.1 Jun 2009
Algorithm Status and Approach Current status of algorithms being considered in your project Algorithm is documented in Demuth et al. 2004, 2006 Include expected performance Overview of technical approach of the algorithm and its implementation Statistical temperature retrievals along with boundary conditions supplied by NCEP analyses are the basis for the physical retrieval of pressure and wind fields that are statistically corrected to provide estimates of the maximum 1-minute sustained winds, MSLP and radii of 34-, 50- and 64-kt winds. Automated Tropical Cyclone Forecast databases, AMSU antenna temperatures, NCEP analyses. For each active tropical cyclone globally ingest the most current MIRS retrievals, use NCEP boundary conditions to perform a physical retrieval of pressure and winds. Statistically correct those estimates and disseminate them to users from OSPO Validation of the product is conducted versus the final tropical cyclone best track values of intensity, MSLP and wind radii when aircraft have recently monitored the tropical cyclone. Validation was performed by SAB for the first two years, but is currently done by CIRA in collaboration with NHC. Note this is already an operational product. V14.1 Jun 2009
SATEPS Security at ESPC/NSOF Production Zone Development Zone Distribution Zone (DMZ) External User Zone IT System Architecture, Data Flow, Security NOAA-19 MIRS Retrievals DDS IBM P550 HDF/NetCDF Files ftp Pull Metop-A,B MIRS Retrievals DDS IBM P550 Operational vmtcfpprod Linux Distribution DDS IBM P550 PNGs ftp Push NCEP GFS Model Data SATEPSDIST5 IBM P550 Remap Svr Development Vmtcfpdev Linux ATCF, ascii, netCDF ftp Pull WMO GRIB Files SFTP Pull NHC, NWS, JTWC, Other Users JTWC, CPHC, NHC ATCF Advisory “b-decks” SATEPSDIST1 IBM P550 Remap Svr ASCII rsync Pull vmVM CM Repository server Linux V14.2 12 Jan 2010
Research and Operational System Environments * ESPC target architecture platform is IBM P6 for science production systems ** ESPC target OS is AIX with Redhat Linux partition *** IDL and MATLAB are not supported in ESPC for science algorithm processing, only for post-processing tasks Red font indicates new IT resource requirements for this project Blue font indicates existing IT resources will be used for this project V15.0 November 2009
Operational Agency System Requirements Red font indicates new IT resource requirements for this project Blue font indicates existing IT resources will be used for this project V15.0 November 2009
Plan of Operations Product Storage Plan NHC will archive the output at NHC, all fixes will be archived on the ATCF, data is available via ftp for 3 days All output data Base Long Term Maintenance Plan Product maintenance is fairly minimal Maintained by OSPO Quality Monitoring Plan Define Quality Control (QC) tools to be developed/used CIRA will work with NHC to perform seasonal verifications based on best track wind intensities and aircraft measured pressures NHC, CPHC, JTWC will continue to monitor daily. Documentation/Metadata Plan Prepare SPSRB required documentation User Involvement Plan Users have been involved with this product over the last several years as it has been a Joint Hurricane Testbed project, a PSDI project and a current operational product. The evaluation and monitoring of the product will continue in a similar manner. V14.1 Jun 2009
Project Milestones and Key Tasks Product Delivery/Tracking Name: AMSU-Based Intensity and Structure Estimation from Aqua and Metop May 08 (May 08) (May 08) (May 08) (May 08) (May 08): Development Phase Begins Jan 08: IPT Branch Lead informed to begin product development Jan 08: Obtain aqua and Metop AMSU-A retrievals May 08: Begin to develop the BUFR scripts to obtain the Aqua and Metop AMSU-A data on the NCEP IBM. July 09: Obtain NOAA-19 retrieval Jul 09: Modify operational retrieval code to use the new data streams Aug 08 (Aug 08) (Aug 08) (Aug 08) (Aug 08) (Aug 08): Pre-operational Phase Begins Aug 08: Begin to work with TPC and NCO to update the operational scripts May 11: Move updated retrievals, BUFR code and scripts to the NCEP IBM Jan 12: Test cases (during the later part of the hurricane season). Feb 12: Implement the new code in the NCEP operational suit of products Mar 12: run code in real-time on the IBM… possibly in parallel. Mar 12: Update SPSRB Oversight Panel(s) on product status Apr 12: Brief SPSRB capability is ready to operational May 13 (May 12) (May 11) (May 10) (Apr 09) (Apr 09): Operational Phase Begins May 13: SPSRB manager and secretaries notified update/upgrade went into operations. SPSRB Secretaries/manager update the SPSRB product metrics web pages May 13: OSD notified to update Satellite Products database May 13: Product declared operational. Terminated V14.1 Jun 2009
Project Milestones and Key Tasks Product Delivery/Tracking Name: MIRS-Based Tropical Cyclone Intensity and Structure Estimation May 13 (May 13): Development Phase Begins May 13: IPT Branch Lead informed to begin product development May 13: Local MIRS database developed Jul 13: Modify existing code to use MIRS input Aug 13: run code in real-time at CIRA Nov 13 (Nov 13): Pre-operational Phase Begins Nov 13: Begin to work with IPT to install the ingest and code Jan 14: Test cases on global TCs. Jan 14: Implement the new code in the OSPO/NSOF operational suit of products Feb 14: run code in real-time… possibly in parallel. Mar 14: Update SPSRB Oversight Panel(s) on product status Apr 14: Brief SPSRB capability is ready to operational May 14 (May 14): Operational Phase Begins May 14: SPSRB manager and secretaries notified update/upgrade went into operations. SPSRB Secretaries/manager update the SPSRB product metrics web pages Jun 14: OSD notified to update Satellite Products database Jul 14: Product declared operational. V14.1 Jun 2009
Product Deliverable Details N=New E=Enhanced R=Replacement T=Tailored O=Other Demuth, J., M. DeMaria, and J.A. Knaff, 2006: Improvement of Advanced Microwave Sounding Unit Tropical Cyclone Intensity and Size Estimation Algorithms, Journal of Applied Meteorology and Climatology, 45:11, 1573–1581. V14.1 Jun 2009
MIRS-Based Tropical Cyclone Intensity and Structure Estimation (K) V14.1 Jun 2009
FY13 Purchases and Tasks J. Knaff and M. DeMaria covered by base funding and will assist CIRA efforts (below) (80K from Polar-PSDI): Grant to CIRA for 1 person at 3/4 time from May 13 to Apr 14 Modify operational code to accept MIRS retrievals as the input source Provide modified operational code to enable the use of the MIRS data source Develop operational scripts Test the new products Coordinate with OSPO on the operational implementation (Use existing contract funds): OSPO Software Contractor for 1 senior programmer at 10% time from May 13 to Sep 13 Assist with software code reviews Assist with system admin to configure operational/development server for this product. (Use existing contract funds): OSPO System Contractor for 1 senior programmer at 10% time from May 13 to Sep 13 Build and configure operational/development server for this product. (10K from Polar PSDI): Hardware(disk) V14.1 Jun 2009
FY14 Purchases and Tasks (30K from Polar PSDI): OSPO Software Contractor for 1 senior programmer at 25% time from Oct 13 to Jun 14 Install this product to OSPDO servers Review product documentation Install or create monitoring system for this product (4K from Polar PSDI): IT Security V14.1 Jun 2009