ASHRAE Guideline 0-2005 The Commissioning Process

ASHRAE Guideline 0-2005 The Commissioning Process. Building Commissioning Association Northeast Chapter Thomas Anderson, CCP. Purpose of Guideline 0-2005. Describe the Cx Process to verify a facility meets the Owner’s Project Requirements. Utilization. Guideline Describes the “Process”

Download Presentation

ASHRAE Guideline 0-2005 The Commissioning Process

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ASHRAE Guideline 0-2005The Commissioning Process Building Commissioning Association Northeast Chapter Thomas Anderson, CCP

  2. Purpose of Guideline 0-2005 • Describe the Cx Process to verify a facility meets the Owner’s Project Requirements

  3. Utilization • Guideline Describes the “Process” • Technical Guidelines Detail Technical Requirements

  4. Guideline 0-2005 The Cx Process • ASHRAE Guideline 1-200X • HVACR Cx Process (Tech Requirements) • NIBS Guidelines • 2-200X through 14-200X Requirements • Other Technical Cx Volumes • Roofing, Lighting, Plumbing, Life Safety, Etc.

  5. Pre Design Phase • Develop Owner’s Project Requirements (OPR) • Cx Scope & Budget • Develop Initial Cx Plan

  6. Owner’s Project Requirements • Forms the basis from which all decisions are made… • Design • Construction • Acceptance • Operational Decisions

  7. Owner’s Project Requirements • Primary Tool for Benchmarking Success and Quality • At all Phases of Project Delivery • Throughout the Life of Facility

  8. Owner’s Project Requirements • Owner’s Objectives for a New Facility • Guidance for Design Team & Others • Not developed by Design Team

  9. OPR Should Include… • Schedule & Budget • Cx Scope & Budget • User Requirements • Energy Efficiency Goals • Applicable Codes & Standards • Etc.

  10. An OPR is Dynamic… • Evolves through each Phase • Updated to Reflect Current Project Requirements • Feasibility • Budget Limitations

  11. Design Phase Cx Tasks • Verify Basis of Design (BoD) with OPR • Update Cx Plan • Defining Training Requirements • Perform Focused Design Reviews • Developed by Design Team • CxA Verifies BoD Conforms to OPR • Systems Manual

  12. Basis of Design • Basis of Design (BoD) • Conveys Design Assumptions that Fulfill OPR Intent • Developed by Design Team • Updated throughout Design Phase

  13. Basis of Design Includes • System Selection Reasoning • Assumptions • Narrative of System Selection & Reasoning • Environmental Conditions • Load Calcs & Sizing • Codes • Operations

  14. Systems Manual • Information Needed to… • Understand Systems • Operate • Maintain

  15. Systems Manual Includes • Index of Systems Manual • Executive Summary • OPR • BoD • O&M Manuals • Cx Process Report

  16. Construction Phase • Verify Systems & Assemblies Conform to OPR • Submittal Review (Spot Check) • Develop Test Docs • Witness Tests • Verify Training • Update Systems Manual (OPR, BoD, Etc.)

  17. Occupancy & Operations Phase • Begins at Substantial Completion • Continue through end of Contractual/Warranty Period • Ideally, Continues through Life of the Facility

  18. Occupancy & Operations Phase • CxA Assists in Problem Solving • Guidance on O&M to Achieve OPR • Seasonal Testing • Verify Training • Systems Manual Update • Cx Report