340 likes | 545 Views
Tom Overbye Fox Family Professor of ECE University of Illinois at Urbana-Champaign Jim Gronquist Bonneville Power Administration (BPA). Validation and Accreditation of Transient Stability (TS) Results. Overview.
E N D
Tom Overbye Fox Family Professor of ECE University of Illinois at Urbana-Champaign Jim Gronquist Bonneville Power Administration (BPA) Validation and Accreditation of Transient Stability (TS) Results
Overview • Goal of project is to perform validation of the transient stability (TS) packages • Commonly thought that different TS packages give different results for the same system conditions • Software validation is (according to DOD), “The process of determining the degree to which a model or simulation and its associated data are an accurate representation of the real world from the perspective of the intended uses of the model.” • This project is just focused on validating the packages against each other, as opposed to with real world data (which would be a natural follow-on)
Project Importance • TS looks at the time-domain response of a system following a disturbance (contingency) for several seconds to minutes • Integration used here was ¼ cycle • Assessing angular and short-term voltage stability • System stability is a growing concern, partially because of more wind integration • PMUs providing more dynamic observability
Background • Project grew out of PSERC effort from 2010 to 2011 funded entirely by BPA involving UIUC and WSU to research the validation of the PSLF, PSSE, TSAT, and PowerWorld Simulator TS packages • UIUC took the lead with PSSE and PowerWorld, WSU with PowerTech, and BPA with PSLF • Most of the PSLF solutions were done by BPA, with just several of the earlier (2010) PSLF runs provided by WSU. Just solution results were provided to UIUC. • None of the results presented here involve PSLF solutions done by UIUC.
Project Challenges • Key challenges include the sheer number of models that need to be validated. • WECC case has more than 3300 generators, 8200 loads, more than 70 different dynamic models (in PSLF) • Individual dynamic models can have dozens of parameters that can substantially affect the behavior of the models • The PSLF and PSSE packages often use different models to represent the same generators/loads • PowerWorld Simulator implements both sets • Model parameters are sometimes incorrect, with values often automatically “corrected”
PSERC Project Caveats • Project required a deep knowledge of the TS solution process and the ability to solve large systems using the different TS packages • Net gain to industry when students graduate, but there is also a loss of university expertise • Project focused primarily on PSLF and PowerWorld, and on the WECC system • Pointing out problems is not meant to imply they are “worse” than others, such as the Eastern Interconnect model; it just wasn’t studied
Data Confidentiality • Many of the studies done for this project utilized confidential information that was provided to UIUC and WSU under NDAs • Data presented in these slides uses WECC results. Public release can be made at the discretion of WECC
The Starting Point In May 2010, as the projectwas just beginning, we wereable to do comparisons for a full WECC case (provided by BPA)between PSLF, TSAT andPowerWorld Simulator. The plot on the right showsthe variation in a bus frequency following thedouble Palo Verde generatortrip contingency for the three packages We moved forward with both a top-down(full system) and bottom-up (individualmodel) approach
The Top-Down Approach Within a week or two we were able to determine that abug in how the frequencydeviations for the inductionmotor loads were beinghandled by PowerWorldwas causing some of thefrequency variation. Thenew run is shown on the right. The oscillation in thePowerWorld frequencies weretracked down to a model error. Model error was associated with a generator line dropcompensation; fixed by auto-correction
Bottom Up Approach • The bottom-up approach consists of creating two bus equivalents for the most common WECC generator models, and then running them in the PowerWorld and PSSE packages. • This has resulted in several PowerWorld changes with the new code often giving quite close matches Graph shows a comparison of thefield voltage at generator for a fault on thetwo bus equivalent system betweenPSSE, and two versions of PowerWorld Simulator
The Bottom-Up Approach • While there are lots of models, project initially focused on the most widely used models. • WECC case has a total of 17,709 models in 77 model types. But the 20 most common model typescontain 15,949 (90%) of these models. These are the key focus areas for the bottom-up analysis.
Post-PERC Work • Since the PSERC project finished in August 2011, UIUC and BPA have continued the validation work focusing on comparisons between PowerWorld and PSLF • The bottom line is the two packages now agree quite closely for the studied scenarios, certainly within the bounds of variability due to input data errors. • This close match allows for detailed comparisons!
Power Flow Solutions • The power flow solution provides the starting point for the TS. PSLF and PowerWorld have very similar solutions. • Key difference is the distribution of reactive power at multi-generator buses. The net bus injection is the same, resulting in the same power flow solution. But the algorithms to distribute reactive power to the generators differ, resulting in slightly different initial transient stability generator field voltages
Initial TS Variable Values • Power flow operating point is back-solved to determine the initial TS states and related variables. Ideally this should result in an equilibrium point, so without a disturbance none of the variables should change. But some may if there is an initial limit violation. • Largest field voltage change in two seconds was 0.34 pu in both packages at gen 42177 due to an initial Vr limit violation.
Efd at Gen 42117 PowerWorld includes an option to automatically modify the limits to provide a “flat” solution
Initialization Pmech: Match is Good • The initial values for the governor mechanical power input and Efd were compared for all generators. Very little difference was observed • Largest differences for mechanical power were 4 MWs at the wind turbines (wndtrb), which was associated with how the rotor losses are modeled
Initialization Efd: Match is Good • For the Efd values, the average error was just 0.003761 per unit (typical Efd values of 1 to 3) • Just 200 units (out of a total of 2322) had initial differences greater than 0.01 per unit. • In a small number of comparisons between PSLF, PowerWorld and PSSE; PowerWorld and PSSE matched closely • Example gen #QF at 24815 PW had Efd=1.8409, PSSE 1.8404 and PSLF 1.8691 (Qg=-72.4 Mvar) • Example gen #G1 at 24815 PW had Efd= 1.0459, PSSE had 1.0471 and PSLF 1.013.(Qg=-2.9Mvar)
Simulation Comparison Methodology • Study involved the Double Palo Verde contingency • The case comparison methodology involved looking at time results for selected values, and differences between the min/max values for different time periods for all key variables (Efd, Pmech, stabilizer output) • Case is quite stressed so small variations can significantly impact the results
Validation Issues: IEEEG1 With the IEEEG1 governor, PowerWorld “auto-corrects” high K1to K8 values. Gens 56503, 57503 and 58503 have K1=20.4, whichcauses very high Pmech outputs in the PSLF results
56503 Output PSLF vs PowerWorld Graph compares the Pmech between PSLF and PowerWorld with K1=20.4 or auto-corrected. Note the turbine rating is 71.2 MVA. Behavior is similar at 57503 and 58503.
Unexpected PSLF Behavior Graph compares the Pmech between PSLF and PowerWorld for G1 at 40559 (Ice Harbor). Unit is modeled with an IEEEG3 Governor. Turbine rating is 103 MVA. PowerWorldcannotcompensatefor thisdifference.To some extent itoffsets theK1 issue.
40687 (Malin) Freq. Comparison Note whether the K1 issue is corrected has a large impact on the resultant frequency. The two PowerWorld results mostly bracket the PSLF results. The 40559 issue also has a significant impact.
40687 (Malin) Volt Comparison Again the two PowerWorld solutions mostly bound the PSLFresults
24801 (Devers) Freq. Comparison Results are similar for a bus in Southern California. Again the PowerWorld results (with the K1 issue either high or fixed) bracket the PSLF results.
Potential EXST1 Issue • In comparing the initial field response for the four units at 36405/6 (Moss Landing), PSLF may be ignoring the feedback term for the EXST1 exciter when Ta = 0
Gen 36406H Efd for Varying Ta Note changing Ta slightly has little impact on the PowerWorld results but gives a significantly fast PSLF response. The ratefeedback should limit the change in Efd.
Key Differences: Modeler Intent • Some key differences in the packages arise in how they handle “modeler intent” in cases in which the input data is either ambigous or wrong. • Example: At gens 56503, 57503 and 58503 the IEEEG1 governor has K1=20.2, which means the maximum output of the units is 20 times the normal value • PowerWorld catches this as an error, allowing the value to be autocorrected
Key Differences: Modeler Intent • Other examples include • Handling exciter saturation when SE1=0 and SE2 > 0. PowerWorld fits a quadratic to these two points • Issues when GV/PGV data is not increasing. PowerWorld raises a validation error. • Reading in models with blank IDs. PowerWorld had defaulted if there was one gen at the bus • WSCCST stabilizer behavior when vcutoff < 0. PowerWorld ignores the parameter, PSLF sets stabilizer response to zero (33141/2/3)
Possible Issue with PSLF EXAC1 Graphs compares the field voltage for the generator at 15914. This generator uses an EXAC1 exciter. The limit on Ve should prevent a negative field voltage. The PSLF results show negative values, with PowerWorld clamping the value at zero.
Conclusion • PSLF and PowerWorld match quite closely and both can be used for WECC studies. • Using multiple packages can help to track down issues either within the packages or within the data. Hence there is a net gain. • Individual package innovation, such as improved error checking or options, can result in better results for all.
Moving Forward • The PSERC project has concluded, but this work is too important to stop. • We are continuing to move forward with funding provided by the Illinois Center for a Smarter Electric Grid (ICSEG) • Industrial participants are invited to join us • BPA has already expressed an interest to continue participating in this effort • Email overbye@illinois.edu if interested