Update on TBL status CTF3 committee 17.09.2009. Several runs with beam, slowly increasing the current Arrived at 10 A beam current and 20 MW 12 GHz power extracted Got experience with beam optics and handling for TBL

gene
Download Presentation

Update on TBL status CTF3 committee 17.09.2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on TBL statusCTF3 committee 17.09.2009 • Several runs with beam, slowly increasing the current Arrived at 10 A beam current and 20 MW 12 GHz power extracted • Got experience with beam optics and handling for TBL • Commissioning of instrumentation, BPM’s, BPS’s, RF-diagnostics for amplitude and phase, movers • Conclusion so far: • 12 GHz production in good agreement with theoretical predictions PETS is well behaved so far, transmission, vacuum • Beam handling rather simple • Some problems with BPM electronics

  2. TBL run with 7 A but long bunches suspected BPM 150 to predict BPM 310 to predict

  3. TBL run with 4 A and good agreement BPS 210 to predict

  4. TBL run 15.9. with 10 A into the PETSForm factor 0.9 Good transmission but noisy signals from the BPS’s

  5. TBL run 15.9. with 10 A into the PETS Optimized for peak power, Form factor = 1

  6. Next steps • Commissioning: • Higher current : 20 A, 100 MW (delay loop needed) • Better BPS performance to measure resolution and to play alignment games with the movers • Finishing TBL: • Finishing the beam line in the next shutdown 21.9 – 16.10 (all Quads, BPS, vacuum system and spectrometer) • Series production of tanks launched ( Two tanks expected to be installed during the winter shutdown ) • Norwegian collaborators expected to work on TBL commissioning in 2010

  7. Status on BPS’s from IFIC Valencia Angeles Faus-Golfe • Status: • BPS finished, calibration measurements ongoing • Electronic droop compensation by Gabriel Montero next week (week 39) • Juanjo will come to CERN week 41 and 42 to help with the installation