An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FP420 NCC From Design to Installation courtesy R. Folch S. Atieh TS / MME

  2. New Connection Cryostat D. Swoboda @ FP420 meeting

  3. Critical Components • shuffling box bottom trays cold feet etc. busbar and cables D. Swoboda @ FP420 meeting

  4. Design and Manufacturing Issues • Material requirements • Vacuum requirements • Cryogenic calculations • Integration of beam screens • Integration of cold/warm transitions • Electrical specification and calculations • Instrumentation and cabling • Standard required tests • Cold test (if required) D. Swoboda @ FP420 meeting

  5. Important components • Beam screens • Cold-warm transitions • Vacuum chambers and vacuum systems • Standard LHC components (cold feet, bottom trays, AL-SS transitions, etc.) • Instrumentation devices D. Swoboda @ FP420 meeting

  6. Critical components/delays • Superconducting bus-bar and cables (to be produced) • Shuffling box (problematic if not from LHC) • Supporting beam ~ 3-4 month delay • Vacuum vessel ~ 4 month delay D. Swoboda @ FP420 meeting

  7. Minimal Project Schedule • Installation constraint by LHC shutdown periods • Replacement of a connection cryostat requires warm up of complete sector! D. Swoboda @ FP420 meeting

  8. Starting conditions • Approval of FP420 & funding • WP approval (EDMS 823322) * • Pre-design approval • Pressure equipment ⇒ AWP’s and welder qualifications • Assembly in bldg. 112 is desirable &possible • Transport and alignment (available in TS department) • * detailed cost evaluation required; i.e. Bus-bars, instrumentation, tooling, ... D. Swoboda @ FP420 meeting

  9. D. Swoboda @ FP420 meeting

  10. D. Swoboda @ FP420 meeting