100 likes | 271 Views
FP420 NCC. From Design to Installation courtesy R. Folch S. Atieh TS / MME. New Connection Cryostat. Critical Components. shuffling box. bottom trays cold feet etc. busbar and cables. Design and Manufacturing Issues. Material requirements Vacuum requirements
E N D
FP420 NCC From Design to Installation courtesy R. Folch S. Atieh TS / MME
New Connection Cryostat D. Swoboda @ FP420 meeting
Critical Components • shuffling box bottom trays cold feet etc. busbar and cables D. Swoboda @ FP420 meeting
Design and Manufacturing Issues • Material requirements • Vacuum requirements • Cryogenic calculations • Integration of beam screens • Integration of cold/warm transitions • Electrical specification and calculations • Instrumentation and cabling • Standard required tests • Cold test (if required) D. Swoboda @ FP420 meeting
Important components • Beam screens • Cold-warm transitions • Vacuum chambers and vacuum systems • Standard LHC components (cold feet, bottom trays, AL-SS transitions, etc.) • Instrumentation devices D. Swoboda @ FP420 meeting
Critical components/delays • Superconducting bus-bar and cables (to be produced) • Shuffling box (problematic if not from LHC) • Supporting beam ~ 3-4 month delay • Vacuum vessel ~ 4 month delay D. Swoboda @ FP420 meeting
Minimal Project Schedule • Installation constraint by LHC shutdown periods • Replacement of a connection cryostat requires warm up of complete sector! D. Swoboda @ FP420 meeting
Starting conditions • Approval of FP420 & funding • WP approval (EDMS 823322) * • Pre-design approval • Pressure equipment ⇒ AWP’s and welder qualifications • Assembly in bldg. 112 is desirable &possible • Transport and alignment (available in TS department) • * detailed cost evaluation required; i.e. Bus-bars, instrumentation, tooling, ... D. Swoboda @ FP420 meeting