1 / 15

Michael Swider Manager – Research & Development New York Independent System Operator

NYISO U.S. Department of Energy Smart Grid Investment Grant Project. Michael Swider Manager – Research & Development New York Independent System Operator Advanced Energy Conference 2013 New York City, NY April 30, 2013. Topics. Introduction to the NYISO Project Overview

gerik
Download Presentation

Michael Swider Manager – Research & Development New York Independent System Operator

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NYISO U.S. Department of Energy Smart Grid Investment Grant Project Michael Swider Manager – Research & Development New York Independent System Operator Advanced Energy Conference 2013 New York City, NY April 30, 2013

  2. Topics • Introduction to the NYISO • Project Overview • Project Participants • Accomplishments • Project Schedule • Challenges & Lessons Learned • Road Map

  3. NYISO Roles • Reliable operation of the bulk electricity grid • Managing the flow of power on 11,000 circuit-miles of transmission lines from more than 300 generating units • Administration of open and competitive wholesale electricity markets • Bringing together buyers and sellers of energy and related products and services • Planning for New York’s energy future • Assessing needs over a 10-year horizon and evaluating projects proposed to meet those needs • Advancing the technological infrastructure of the electric system • Developing and deploying information technology and tools to make the grid smarter

  4. SGIG Project Summary • Budget: $75,710,733 • Timeline: July 1, 2010 – June 30, 2013 • Equipment: Phasor Measurement Units, Phasor Data Concentrators, Phasor Measurement Network, Capacitors • Applications: Enhanced State Estimator, Voltage Stability Monitoring, Situational Awareness (Visualization), Post-Mortem Analysis • Benefits: Improved Grid Reliability & Power Flow Efficiency, Reduced Costs, Reduced Likelihood of Disturbances

  5. Project Participants • NYISO as the Primary Awardee for the Grant • New York Transmission Owners as SubAwardees • Quanta Technology as the primary consultant, providing Engineering and Technical expertise • Crowe Horwath LLP as a subcontractor to provide Grant Administration and Compliance expertise • PMOLink, LLC as a subcontractor to provide Project Planning and Management services • Utilicast, EPG, & ABB for Application Development, Integration, Testing & Deployment • EPRI & EnerNex to conduct Controlled System Separation Feasibility Study and Dynamic Model Calibration Study

  6. New York Control Area

  7. Accomplishments • PMU Design & Build-Out • 40 (of 41) Substations Covered • 47 (of 48) PMUs Installed • PDC Design & Build-Out • 8 (of 8) TO Control Center PDCs Installed • Capacitor Installations • 458.2 (of 938.2) MVAr of Capacitors Installed • Phasor Measurement Network • Wide Area Network Build-Out Complete for 10 (of 10) Sites • 6 (of 8) Transmission Owner Control Center PDCs Networked Photos courtesy of Central Hudson Gas & Electric and New York Power Authority

  8. Accomplishments • Situational Awareness (Visualization) Applications • Began testing EPG base product in early 2012 • Development continued to meet NYISO requirements • Currently Executing Site Acceptance Testing • Enhanced State Estimator Applications • Development / Testing in 2012 • Q1 2013 Deployment • Voltage Stability Monitoring Applications • Development began in late 2012 • Currently Executing Site Acceptance Testing • Q2 2013 Deployment

  9. Visualization

  10. Accomplishments • System Studies: Controlled System Separation • Conducted by EnerNex • All deliverables received in 2012 • Final approval by NYISO in Q1 2013 • System Studies: Dynamic System Model Calibration • Conducted by EPRI • All deliverables received in 2012 • Additional scope added to be complete by June 2013

  11. Anticipated Benefits • Situational Awareness • Enhance NYISO’s ability to detect system vulnerabilities and disturbances in real time and to potentially mitigate their impact • Phasor Enhanced State Estimation • Addition of time-synchronized data will improve the existing state estimation function • Reduction in Transmission Losses • Capacity and energy savings as capacitors reduce losses by improving power factors and voltage profiles

  12. Challenges & Lessons Learned • Project Execution Challenges • External Dependencies • Coordination Among Multiple Entities • Schedule Delays • Business Owner Acceptance • Technical Challenges • Knowledge / Experience • Performance / Support • Cyber Security • Data Retention • Lessons Learned • Shared Requirements/Goals • Expansion

  13. Road Map • People • Post-Project Support from IT & Operations • Show Benefits to Stakeholders • Process • Ongoing Planning for NYS and Beyond • Data Analysis & Technology Growth • Technology • Ongoing Equipment Installations • Redundancy • Advanced Applications

  14. The New York Independent System Operator (NYISO) is a not-for-profit corporation responsible for operating the state’s bulk electricity grid, administering New York’s competitive wholesale electricity markets, conducting comprehensive long-term planning for the state’s electric power system, and advancing the technological infrastructure of the electric system serving the Empire State. www.nyiso.com

More Related