1 / 23

Introduction To Critical Chain Project Management

Introduction To Critical Chain Project Management. Hilbert Robinson, Afinitus Group, LLC Robert Richards Ph.D,, Stottler Henke Associates, Inc. Are You A Responsible Person?. Scenario: You live in New England and It’s late Winter Time to airport varies from 45 minutes to 3 hours depending…

ghita
Download Presentation

Introduction To Critical Chain Project Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Introduction To Critical Chain Project Management Hilbert Robinson, Afinitus Group, LLC Robert Richards Ph.D,, Stottler Henke Associates, Inc.

  2. Are You A Responsible Person? Scenario: • You live in New England and It’s late Winter • Time to airport varies from 45 minutes to 3 hours depending… • Most times it takes a little over 65 minutes • You are Joining the President at 9:00 AM Question: • How early should you leave? __________ • Why?_____________________________

  3. Presentation Outline • Background • Triple Constraints • Murphy’s Law • Complexity • Problem [What to Change] • Localized Risk Management • Task Level Insurance Policy • Student Syndrome • Parkinson’s Law • Multi-tasking • Solution [What to Change to] • Governing Principle - Global Risk Management • Project Level Protection • Systems Perspective • Execution Control

  4. Background • Triple Constraints [Binding Commitments] • Time [Minimize] • Capacity [Minimize] • Content [Maximize]

  5. Background • Murphy’s Law [Disruption Event] • Number of unknowns • Range of possibilities • Frequency of repetition • Complexity [Amplification factor] • Degree of integration required • Number of dimensions to be integrated

  6. Presentation Outline • Background • Governing Principle or Paradigm Shift • Triple Constraints • Complexity • Murphy’s Law • Problem [What to Change] • Localized Risk Management • Task Level Insurance Policy • Student Syndrome • Parkinson’s Law • Multi-tasking • Solution [What to Change to] • Governing Principle - Global Risk Management • Project Level Protection • Systems Perspective • Execution Control

  7. The Problem Localized Risk Management Strategy • Task level insurance policy See opening scenario – answers? And if it was a task in a project?? ** How safe is safe enough?** • Student Syndrome The dog ate my homework • Parkinson's Law Self-fulfilling prophecy [good estimating?] • Multi-tasking [absence of priorities] Hero or villain?

  8. Problem: Localized Risk Management One Resource, Four Task, from Four Different Projects Multi-tasking causes delays to spread across all projects, adding as much as 20% to all projects 9

  9. Presentation Outline • Background • Governing Principle or Paradigm Shift • Triple Constraints • Complexity • Murphy’s Law • Problem [What to Change] • Localized Risk Management • Task Level Insurance Policy • Student Syndrome • Parkinson’s Law • Solution [What to Change to] • Global Risk Management • Project Level Protection • Systems Perspective • Execution Control

  10. Solution Governing Principle Behind CCPM is: Aggregation of risk… Benefits: • Lower overall protection needed • Higher degree of “coverage” achieved • Leading to lower incidence of “failure”

  11. SolutionGlobal Approach to Risk Management • Planning • Project Level vs. Task Level Protection • Systems Perspective for Multiple Projects • Should load for multiple projects be considered? • Why? • How? • Execution Control • Promote and encourage team culture • Controlled work queues • No multi-tasking work rules • No batch processing work rules • Task assignment prioritization • Management by Exception

  12. Critical Chain Planning Process From Task to Project Protection 1. Traditional Plan 2. Safety Excluded 3. Resource Leveled 4. Critical Chain Marked

  13. . Aggregation Principle • The Concept of Risk Pooling: • Can someone explain why this works? • Health Care Example: • larger pool = lower cost

  14. Aggregation Principle Insurance is designed to work by spreading costs across a large number of people. Premiums are based on the average costs for the people in an insured group.  This risk-spreading function helps make insurance reasonably affordable for most people. http://www.insurance.wa.gov/legislative/factsheets/PoolingRiskReducingCost.asp

  15. Critical Chain Planning Compared to 60days traditional PB = Project Buffer FB = Feeding Buffer • Aggregation Principle [where did some of the safety go?]: • Pooled protection provides more coverage • Location is just as important as amount • Sizing Rule of Thumb  2/3rds to 1/3rd • Buffer is half of preceding chain

  16. Critical Chain in Execution Schedule Before Execution Starts “AS OF DATE” • T8 experienced a 5 day increase in scope or delay • Results in a 2.5 day impact to the project buffer • The rest was absorbed by the Critical Chain gap 4. 35-32.5=2.5 7% Complete and 14% Buffer Consumed

  17. Not “rear view mirror watching” Predictive/Preventative/Leading Indicator Mechanism to Promote and encourage Team Work Collaboration / Communication Incentive Mechanism Measuring device – Neutral, Normalized Metrics Real-time Risk Meter Encourages an holistic/goal oriented perspective Perspectiveon Buffers

  18. Critical Chain Priority Metric Project Status Trend Chart or “Fever” Chart

  19. Multi-Project System Systems Perspective for Multiple Projects • Should load for multiple projects be considered jointly? • Obviously • Why? • Prevent System Overload/Multi-tasking • How? • By taking a Systems Perspective

  20. Creating a Multi-Project Schedule Finite Capacity Pipeline Due Dates Are Derived Ingredients: • CC Plans [shorter] • Strategic Pacing Mechanism • Strict Priority Scheme • Rate Limit Policy/Guidelines

  21. 1007 1003 1005 1006 1004 1002 1001 1009 1008 0 % Buffer Consumed 100 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | % Critical Chain Completed 0 100 Multi-Project Execution ControlPipeline Status Snap Shot In Execution, Buffer Status Drives Priority Decisions, not Project Importance 1010 By Portfolio of Projects

  22. The Upshot… Benefits • Operational Coherence – Stability • 20% Shorter Cycle-Times – Speed • On-time Performance – Reliability • More throughput – Growth Challenges: 1. Simple but not easy to grasp – too simple? • Requires a change in mindset • Takes 120 days for typical 100 person team • We don’t need that much improvement

  23. Questions??? Hilbert Robinson, Afinitus Group, LLC www.afinitus.com Robert Richards Ph.D,, Stottler Henke Associates, Inc. AACE2009.R.RichardsPhD@Neverbox.com www.StottlerHenke.com

More Related