1 / 33

The Impact of Ice

The Impact of Ice. Nebraska Public Power District 2006-2007. Christmas Storm Outcome. 10 transmission lines out – made temporary repairs to 8 – 2 remained out of service 4 telecommunications fibers inoperable – no telecommunications west of Holdrege 2,500 retail customers impacted

gil-brady
Download Presentation

The Impact of Ice

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Impact of Ice Nebraska Public Power District2006-2007

  2. Christmas Storm Outcome • 10 transmission lines out – made temporary repairs to 8 – 2 remained out of service • 4 telecommunications fibers inoperable – no telecommunications west of Holdrege • 2,500 retail customers impacted • 21 NPPD technicians assist Dawson PPD • $1.0 Million in damages (approximate)

  3. New Year’s Storm Timeline Friday – December 29 • Rain, freezing rain, icing, wind Saturday – December 30 • Severe icing conditions and wind • Widespread, extensive damage • Crews respond to numerous outages Sunday – December 31 • Major effort to assess damage and restore power

  4. Back-to-Back Storms Christmas Storm: New Year’s Storm:

  5. Normal NPPDTransmission System Grand Island Lexington Kearney Hastings Holdrege

  6. System Condition January 1

  7. System Condition January 4

  8. Kearney Holdrege Kearney Area Damage Assessment # # -Wood Structures -Steel Towers -Shield Wire Miles # 63 2 42 125 314 2 18 10 43 54 5 1 10 34 52 53 109 1

  9. Early Priorities • Kearney • Lost 4 of 5 transmission feeds • Priority restoration of second feed • Rolling blackouts during initial restoration • Holdrege • Lost all 3 transmission feeds • Mobile generation located within the community • Key Messages • Energy conservation • Fragile system • Safety

  10. System Status – March 2, 2007 InitialCurrent • Miles assessed 2,650 • Customers without power • NPPD Retail (service restored: 1/6/07) 11,612 0 • Wholesale customers 31,000 0 • (service restored: 1/19/07) • Transmission System (approx, 71% repaired) • Number of line segments out 37 7 • Transmission miles out-of-service 1,053 184 • Number of substations out 18 0 • Miles of conductor down 301 86 • Number of structures damaged 1,136 473 • GGS east flow limitation 224 MW 990 MW • Communities on Mobile Generators 14 0 • More than a dozen public power utilities impacted by storm • Contractors on site throughout reconstruction 260 - 320 Up to Up to *These MW will depend on transmission system status, loading conditions and regional transmission system conditions.

  11. FEMA Disaster Declaration FEMA-1674-DR

  12. Ice on a guy wire

  13. Engineering Design Criteria • National Electrical Safety Code 1997 • Heavy combined ice and wind loading, ½ inch radial ice, 40 mph wind, 0°F • National Electrical Safety Code 2007 • Heavy combined ice and wind loading, ½ inch radial ice, 60 mph wind, 15°F • New Year’s storm • 2 inch radial ice, winds averaging 21 mph, gusts up to 40 mph, temperatures hovering around freezing

  14. Effect of Ice on Power Lines • Typical weight of conductors without ice – ½ to 1 pound per foot • Weight of lines with ice can increase by 4 - 8 pounds per foot • Weight on structures increased up to 8 - 10 times after ice storm • Example: 115kV structure load went from 3,000 pounds to 26,000 pounds (2-inch radial ice)

  15. Size of ice one week after storm

  16. The ice mangled 345-kilovolt structures like twist-ties

  17. More than 40, 345-kilovolt structures were destroyed

  18. The storm snapped H-frame structures like twigs

  19. More than 300 miles of line and 1,137 structures were damaged

  20. Ice on Substation near Holdrege, Neb.

  21. Emergency Restoration

  22. Emergency mobile generation was brought in for 14 communities

  23. Mutual aid near Elgin, Neb.

  24. Day-after-day diligence for more than 30 days. The last community on emergency generation was restored line service on Jan. 29, 2007.

  25. Reconstruction

  26. Restore Transmission System • Material procurement and delivery • Focus on primary reconstruction efforts • Hire and assign contractors • Parallel efforts (Customer Service Priorities) • System Network Priorities • Watch the weather • Ensure equipment functions

  27. More than 3,000 wood poles ordered.

  28. Unloading conductor at NPPD’s York Operations Center for 400 + miles of line

  29. Contractors Reconstructing South of Holdrege, Neb.

  30. Restoration efforts near Prosser, Neb.

  31. Questions?

More Related