1 / 9

Pranjal Bora Group Head Luthra & Luthra Law Offices

Risk Management and Contract Structuring for Infrastructure Projects. Pranjal Bora Group Head Luthra & Luthra Law Offices. Project Risk Risk during construction period Risk during operating period Mitigation of risks through adequate provisions in contracts Political Risk

gilda
Download Presentation

Pranjal Bora Group Head Luthra & Luthra Law Offices

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Risk Management and Contract Structuring for Infrastructure Projects Pranjal Bora Group Head Luthra & Luthra Law Offices

  2. Project Risk • Risk during construction period • Risk during operating period • Mitigation of risks through adequate provisions in contracts • Political Risk • Political risks in large scale projects may include land acquisition issues and political intervention • Political risks are typically addressed through carefully drafted ‘force majeure’ provisions in project contracts • Also, obtaining requisite permits and approvals, local labour laws, changes in laws are at times viewed as political risks • Certain political, financial and commercial risks coverage may be obtained from export credit agencies

  3. Tendering and pricing • Realistic time frames • Realistic costing • Technical qualification • Precise details – the owner should clearly specify the technical requirements of the project • Close out all deviations from the bid documents at the tendering stage • Lump sum pricing

  4. Bankability Issues • Contractual Risk Allocations • Factors affecting bankability • a fixed completion date; • a fixed completion price; • no or limited technology risk; • output/performance guarantees; • liquidated damages for both delay and performance; • security/guarantees from the contractor and/or its parent company; • caps on liability; and • restrictions on the ability of the contractor to claim extensions of time and additional costs.

  5. Step in Rights/ Cure Rights of Lenders • Direct Agreement • Assignability of sub-contracts in cases of termination • Contractor’s Solvency and Security Packages • Contractors consortium / Single Contractors • Lock in Restriction • Security packages • Advance payment guarantee • Performance guarantee • Parent company guarantee

  6. Contract Structuring • Single consolidated EPC Contract • Split EPC Contracts • Onshore Supply and Services Contract • Offshore Supply and Services Contract • Wrap Contract • Single Point Responsibility

  7. Contract Administration • Organization Structure of the Contractors • Designated representatives • Kick off meetings • Hand over / transition policy • Dynamic policy – ability to improvise

  8. Disputes / Managing Claims • Multi-tier Dispute Resolution Mechanism • Technical Experts • Proper Documentation • Notice Period • Professional and Lawyers having substantial project / construction experience

  9. THANK YOULuthra & LuthraLaw Offices

More Related