Althea Wilkinson Radio Net Project Manager University of Manchester Jodrell Bank Observatory. Project Manager’s Report & Finance Report Rome September 2008. Madrid schedule. Distribution of funds for next 18 months – Jan 08 FP7 proposals final internal submission Nov 2007

gin
Download Presentation

Althea Wilkinson Radio Net Project Manager University of Manchester Jodrell Bank Observatory

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Althea Wilkinson RadioNetProject Manager University of Manchester Jodrell Bank Observatory Project Manager’s Report & Finance Report Rome September 2008

  2. Madrid schedule • Distribution of funds for next 18 months – Jan 08 • FP7 proposals final internal submission Nov 2007 • Call for preparations for AR4 – end Dec 2007 • Audits for all non-zero finance partners Jan 2008 • Submit documents for 4th Annual Report end Jan 2008 • FP7 proposal submission to EC 15th Feb 2008 • Submit AR4 as soon after 15th Feb as possible Significantly delayed by FP7 activities – delivered 03/04/08 • Acceptance of AR4 and distribution of funds for last 12 months of FP6 • Final Annual Report and audit Feb 2009 • Final distribution of funds – during 2009

  3. 4th distribution of Financing • Amount sent had disallowed for IRAM subtracted – not enough funding • Temporary solution achieved by JBO as co-ordinator taking risk on €105K • IRAM repayed 80K – argued rest with EC • EC have now revised the amount disallowed – still under discussion • Payments notified on 16th Jan 2008

  4. Management activity 1 • 4th Annual Report • Final version on wiki, AR4 • http://www.radionet-eu.org/rnwiki/FourthRadioNetAnnualReport • Delivered on 03/04/08, delayed by FP7 activities • EC comments received on 16th April 2008 • Mostly minor corrections to wording of audit certificates • FG-IGN issue is delaying reply • Requires another contract amendment before October • New issue of finance report sent to all Board members

  5. FG-IGN issue • FG and IGN now deemed to be separate legal entities • Contract now “illegal” (though accepted during time when FG-IGN active in RadioNet) • Contract amendment will mean that all IGN component of funding must be returned to EC • Spain has spent all funding – severe problem • Suggested compromise – funded extension to FP6 RadioNet so FG can do work and retrieve funding – running in parallel with FP7

  6. Activities • Networking Activities • Extremely beneficial for interaction throughout Europe • High demand for funding for meetings • Good way to build European Radio Astronomy community • JRAs • Very successful in getting European technology and software groups to collaborate • Have achieved targets • All running for full 5 years Will report separately later

  7. Finance Report • FP6 RadioNet now apparently overspent • How did this situation arise? • Spend model at beginning of 2008 too low – instead of tapering off, spend has accelerated in some areas • Multiple re-allocations make overall situation hard to assess continuously • Almost completely disjoint process of reporting and requesting funding also not helpful (Form C vs Implementation plan, left to be justified vs actual spend) • Circulation of incorrect budget emails earlier in the year erroneously encouraged spending • PM had no assistance between March and August – working on at least 10 other projects – did not catch situation early enough. • Misunderstanding about use of indirect on JIVE travel funds

  8. Situation at end of 2007 • Given in Review of Financial Status • €1,501,266.65 left to justify in Y5 • Detailed tables of re-allocations by institute and activity produced • Management had €265605.24 left • JRAs had €393763.83 left • NAs had € 1599.46 left • TNA travel had €154077.93 left • TNAs had €898,644.32 left • Plan was to re-allocate €120.000 from TNA travel to NAs and make up any other shortfall from management.

  9. Other PM activities between April and August 2008 • Angles Audit and project end • MERLIN preparation for Steering Committee • EC SKADS annual report and Form C • STFC SKADS parallel report • FP7 RadioNet proposals • Mid Term review for JBO current Rolling Grant • Application for two new JBO Rolling grants in Cosmology and Technology • Planck post launch support case • ASTROGRID issues • Manchester internal technology funding issues • Manchester year end finance