g2p/GEp Beamline

g2p/GEp Beamline. Tim Michalski Project Lead. Overview. Facilitate the design, procurement, and build of the beamline – up to the target chamber g2p/GEp Beamline Overview Experimental Plan Project Overview Project Status Project Challenges with Risk Mitigation

gino
Download Presentation

g2p/GEp Beamline

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. g2p/GEp Beamline Tim Michalski Project Lead

  2. Overview Facilitate the design, procurement, and build of the beamline – up to the target chamber g2p/GEp Beamline Overview Experimental Plan Project Overview Project Status Project Challenges with Risk Mitigation Project Schedule and Milestones

  3. Beamline Overview A second configuration will have the target at the pivot and a longer articulating arm.

  4. Experimental Plan Target Elevated by 9cm *** - FZ1 and FZ2 in position for 2.2 GeV run, but with half field strength on FZs and Target magnets Rev 3

  5. Run Trajectories FZ1 Target Target FZ2 FZ1 FZ2

  6. Region 1

  7. Slow Raster/Calorimeter Stand

  8. Regions 2 and 3

  9. Upside Down Girder – Region 2

  10. FZ1 Magnet Stand – Region 3

  11. Viewer – Region 3

  12. Beam Diagnostics Girder “Articulating Arm” – Region 3

  13. Project Overview • Design, procurement, component calibration and testing • Now through May, 2011 • Some components arrive after May • Access to Hall A for installation • May 16, 2011 • Installation completion – start of Physics • November 19, 2011

  14. Project Status • Regions 1 and 2 designs complete and material ordered • Region 3 design complete – procurement under way • Calorimeter controller repaired and SW upgrades complete • I&C electronics designed and being built • New Transport electronics being built for existing BPMs in Hall A • Safety systems for experiment reviewed • Resource planning integrated into 6MSD schedule

  15. Project Challenges • BPMs and BCMs for Low Current data • Mitigation • BPM – short M15 style, new electronics, tested in North LINAC • BCM – new receiver, tested in Hall A • FZ Magnet PS requirements evolving • Need up to 4 kG, requiring 231A for FZ1 • Need up to 8 kG, requiring 465A for FZ2 • Mitigation – assessed capabilities of magnet power supplies in Hall C – meet requirements – assembling spares

  16. Project Challenges • Acquisition of equipment from various sources • FZ magnets, corrector magnets, slow raster, new BPMs, power supplies, controllers • Mitigation – get control as soon as possible, test and calibrate early (before installation) • Resurrection of Tungsten Calorimeter • Reposition in beamline, re-establish functionality, recalibrate • Mitigation – Controller extracted from Hall A, repaired, SW complete

  17. Project Challenges • Slow Raster control issues in previous experiment • Mitigation – New function generator – Testing in Progress by Physics Fast Electronics Group • Installation at the same time as 12 GeV upgrades during 6 month down • Mitigation – tied to detailed 6MSD planning – all resources identified in schedules – have ~3 weeks float

  18. Project Challenges • Not all material for installation on site yet • Mitigation • FZ2 Stand procurement being managed – potential impact to 6MSD installation reviewed • Viewer and Articulating Arm Girder / Positioning – manage through Machine Shop and local vendors

  19. Safety – PSS / FSD • Uses standard BLA system components • Monitoring FZ magnet PS current – limits set to ensure beam is controlled successfully through the chicane • FSD masking for Calorimeter Operation • Viewer in chicane – allows MCC Operators to view beam for steering confirmation • Thermocouples on LC dump • Viewer on LC dump – allows MCC Operators to view beam for steering confirmation • Update PSS sweep procedure as required after walk-through, equipment installation • “Lock Out” FZ2 stand control – remove controller

  20. Beamline Installation Schedule

  21. Beamline Installation Milestones