An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Decadal Survey Mission Planning Presentation to CLARREO Workshop Steve Volz October 21, 2008

  2. Agenda • Decadal Survey Missions • Overall Decadal Survey study objectives • Mission Development Approach

  3. NASA Near-Term Missions (4/15 total)

  4. NASA Mid-Term Missions (5/15 total)

  5. NASA Late-Term Missions (6/15 total) *Cloud-independent, high temporal resolution, lower accuracy SST to complement, not replace, global operational high-accuracy SST measurement

  6. NRC Decadal Survey Recommendations • NRC made 29 different recommendations in many areas for Earth Science • NASA is working to address the many recommendations • Within the Flight group we are addressing only a few of them • DS missions • Venture class development • TSIS & CERES recovery • Completion of current portfolio • Other ESD groups are addressing • Technology development (ESTO) • R&A issues • Applications science

  7. Earth Science Division Organization Michael Freilich, Director Peg Luce, Deputy Director, Flight Randy Friedl, Deputy Director, Science 1 CS Mgmt Analyst, 2 Program Support, 1 Secretary SMD-wide Education Stephanie Stockman, Head 2 IPAs Research Flight Programs Applied Sciences Earth Science Technology Office (@ GSFC) Steve Volz, Associate Director Steve Neeck, Deputy Associate Director Teresa Fryberger, Associate Director (Vacant), Deputy Associate Director Jack Kaye, Associate Director Lucia Tsaoussi, Deputy Associate Director George Komar,Associate Director Amy Walton, Deputy 14 CS Program Scientists, 5 IPA PS, 2 Detailee PS In, 1 Detailee PS Out, 1 Secretary 6 CS Program Executives,1 IPA PE, 2 Detailees, 1 Secretary (w/Applied) 4 CS Program Officers 10 CS Technologists (badged to GSFC) Nov. 28, 2007

  8. Flight Program Management Michael Freilich, Director Peg Luce, Deputy Director Steve Volz, Associate Director Steve Neeck, Deputy Associate Dir ESTO IIP, AIST, ATI Airborne Science R&A ESSP Program Ed Grigsby, PM ESM Program Gil Colon, PM JPL LaRC Applied Sciences GRACE (JPL) CloudSat (JPL) CALIPSO Venture Class OCO (JPL) Aquarius (JPL) Decadal Survey Pre-Formulation Development Phase A/B/C/D Operations Multi-Mission Ops Climate Sensors POES/GOES ICESat II DESDynI (JPL) CLARREO (LaRC) NPP LDCM GPM SMAP (JPL) Glory Terra EO-1 Aqua ICESat Aura QuikSCAT SORCE Jason (JPL) TRMM Acrimsat (JPL) OSTM (JPL) Multi-Mission Ops EOSDIS TSIS CERES (LaRC) NOAA N’ GOES-O, -P

  9. SMAP & ICESat II • SMAP and ICESat II are the first two Decadal Survey (DS) missions the ESD and NASA will implement. • SMAP project is being conducted out of JPL, and completed its transition to Formulation in September 2008. The projected / planning launch date is now early 2013. • ICESat II project is being conducted out of GSFC, and is working to its Mission Confirmation Review in early 2009. The launch date is under study, expected between 2014 and 2016 • Both missions (and all DS named missions) are directed science missions with individual budget lines. They are managed out of the Earth Systematic Missions (ESM) Program Office located at GSFC.

  10. CLARREO & DESDynI • CLARREO & DESDynI are the next Decadal Survey missions to be addressed by the ESD • Both missions are directed science missions with individual budget lines. They are managed out of the Earth Systematic Missions (ESM) Program Office located at GSFC • The CLARREO mission is led by LaRC, with GSFC support • Draft level 1 requirements & initial international partnership discussions, Fall 2008 • Initial mission concepts, Spring 2009, • Full technology readiness assessment, MCR October 2009 • The DESDynI is led by JPL, with a significant GSFC contribution • Draft level 1 requirements & initial international partnership discussions, Fall 2008 • Mission configuration down select, Spring 2009 • Full technology readiness assessment, MCR October 2009

  11. What about the Venture Class? • NRC Decadal Survey recommended a “Venture Class” line of small, cost- and schedule-constrained, competitively selected “missions” to complement the identified strategic missions • Higher risk posture allowed, Class C missions, single string instruments allowed • High risk, high return demonstration technology a consideration • Creative spacecraft & launch options considered • FY09 budget does allow a “Mission of Opportunity” with start in FY10 and launch NET FY14 -- with only a small amount of money • The named missions in the Decadal Survey will not be Venture Class, but will be executed through the Earth Systematic Missions Program Office • Class B or Class C missions • NASA certified launch vehicles • 3+ year mission life, with commensurate reliability requirements • High TRL for instruments required at confirmation

  12. Technology Readiness Level TRL levels defined in NPR 7123.1A High Maturity TRL 6 is the desired minimum level for integration of new technology TRL required fordirected missions atConfirmation Review TRL possible forexploratory mission at Confirmation Review Low Maturity

  13. New Decadal Survey-Related IIP Awards

  14. Where do we expect to be by October 1, 2009? • For each of the Near- and Mid-Term missions in the Decadal Survey: • Quantitative assessment of the readiness to proceed to Formulation (Phase A) • Draft level 1 science requirements, baseline mission concept, draft formulation authorization document, partnership evaluations, technology readiness level assessments • Mission Confirmation Review (MCR) readiness expected for CLARREO and DESDynI based on FY09 budget, but to be determined by teams’ demonstrated progress • Mission maturation plan for FY10 and beyond, through launch and ops • Life Cycle Cost, independent cost and schedule estimates • Decadal Survey Program assessment, including: • Cross cutting mission analyses, constellation measurement requirements, ground systems, platform, and ground networks • Definition of scope and implementation approach for the Venture Class of small mission opportunities

  15. BACKUP

  16. Chief Engineer (K. Ledbetter) Safety & Mission Assurance (P. Martin) Programmatic Implementation within SMD Associate Administrator (AA) (Ed Weiler) Deputy AA (Chuck Gay) Deputy AA for Programs(Mike Luther) Deputy AA for Management(Roy Maizel) Chief Scientist (Paul Hertz) - Lead for Research (Max Bernstein) - Lead for E/PO (Stephanie Stockman) AAA for Strategy, Policy & International (Marc Allen) Senior Advisor(Colleen Hartman) AstrophysicsDivision Dir. (J. Morse)Dep. (R. Howard) Earth Science Division Dir. (M. Freilich)Dep. Programs (M. Luce)Dep. Science (R. Friedl) HeliophysicsDivision Dir. (R. Fisher)Dep. (V. Elsbernd) Planetary Science Division Dir. (J. Green)Dep. (J. Adams) Resource Management DivisionDir. (R. Maizel-Act)Dep. (Vacant) Strategic Integration & Management DivisionDir. (R. Maizel-Act)Dep. (Vacant) Research (J. Kaye) Mars Program(D. McCuistion) Applied Science (T. Fryberger) Flight (S. Volz) Decadal Survey Directed Missions Competitively Selected Venture Class missions Draft: July 22, 2008

  17. ESD Execution of Decadal Survey Missions • All Decadal Survey Missions concepts studies are directed by the ESD and will be managed by the Earth Systematic Missions (ESM) Program Office at GSFC • All mission development will have a study management team, led from HQ ESD by the HQ Program Scientist and Program Executive, and including representatives from ESTO, data systems, applied sciences, and the ESM program office • All members of the mission study ESD teams should be involved in all relevant study discussions, and the PS and PE are expected to participate in cross mission science and mission trades

  18. NASA Hierarchy of Directives • NPR 7120.5D - NASA Space Flight Program and Project Management Requirements governs the processes associated with formulating and implementing a new flight project • Important details for GEO-CAPE: • Defines the Major Milestones • Identifies all requirements for each phase of the Project • Identifies all gate products for each phase • Defines roles and responsibilities • Identifies all major reviews

  19. Flight Project Life Cycle Extracted from NPR 7120.5D

  20. Mission Requirements for Pre-Phase A Scope of Major Pre-Phase A Activities: Headquarters • Approve a Formulation Authorization Document • Develop DRAFT Level 1 Requirements • Conduct Acquisition Strategy Planning Meeting Technical Activities: • Develop and document preliminary mission concepts • Conduct internal Reviews • Conduct Mission Concept Review Project Planning, Costing and Scheduling • Develop and document a DRAFT Integrated Baseline, including: • High level WBS • Assessment of Technology Readiness Levels • Assessment of Infrastructure and Workforce needs • Identification of potential partnerships • Identification of conceptual acquisition strategies for proposed major procurements KDP Readiness • Obtain KDP A Readiness products • Approval through the governing PMC Areas the Science Community must work: • Development of DRAFT Level 1 Science Requirements • Support development of preliminary mission concepts • Support the assessment of Technical Readiness Levels • Identify potential partnerships

  21. Key Pre-Phase A Questions • What science MUST this mission achieve? • What specific measurements? • To what accuracy? • What are the required data products? • What mission parameters can achieve the science? • What orbit (inclination/altitude)? • Which instruments? • What is the baseline mission duration? • How can NASA achieve these measurements? • Are there other missions required/desired to achieve the science? • Who can NASA partner with to achieve this mission? Should be resolved ~ 12 months prior to KDP A Should be resolved ~ 6 months prior to KDP A

  22. Notional Mission Timeline NOTE: The time for each phase is considered nominal - could be accomplished earlier