New Offshore Wind Tenders in Denmark. 1,450 MW before 2020. Presentation today. Danish ambitions on future offshore wind power. Lisbeth Nielsen Danish Energy Agency. Peter Sehestedt Danish Energy Agency. Two new offshore tenders: 400 MW at Horns Rev and 600 MW at Kriegers Flak.
E N D
New Offshore Wind Tenders in Denmark 1,450 MW before 2020
Presentation today Danish ambitions on future offshore wind power Lisbeth Nielsen Danish Energy Agency Peter SehestedtDanish Energy Agency Two new offshore tenders: 400 MW at Horns Rev and 600 MW at Kriegers Flak Tone MadsenDanish Energy Agency Tender of 450 MW nearshore projects Betina Haugaard Heron Energinet.dk Pre-investigations and grid connection
Denmarks’ ambitiousgreen energypolicy Ambitious green energy policy: long-term goal for 2050 – independence of fossil fuels Stable regulatory framework to 2020 Offshore wind broad political support – 95 % of the Danish Parliament Effects in 2020 50 percent of our electricity consumption from wind power
New Offshore Wind projects in Denmark • Horns Rev 3: 400 MW • Kriegers Flak: 600 MW Tender for 450 MW near shore wind farms 50 MW turbines for research and development
The Danish offshore approach A track record of political stability Planning and pre-investigations Predictable income DEA is one stop shop Grid connection – large scale and near shore No requirement for local content Transparent and flexible tender process
Integration of wind power Strong interconnectors A well functioning international market for electricity Flexible electricity consumption
Horns Rev 3 and Kriegers Flak The most attractive sites The sites chosen for tender ranked the highest in the economic ranking Horns Rev 3 Kriegers Flak
Horns Rev 3 400 MW in the North Sea Denmark's 14th offshore wind farm Local competences and network of suppliers North Sea has good wind conditions Sea depths of less than 20 metres
Kriegers Flak 600 MW in the Baltic Sea Denmark's largest offshore wind farm Located in the Baltic Sea close to borders of Sweden and Germany Will also be linked to the German farm - power can be led to both countries Kriegers Flak Good wind conditions
We are transparent Tendering for Horns Rev 3 and Kriegers Flak: Dialogue and negotiation
Common timeline both projects 2013 February to April 2013 Pre-technical dialogue From May 2013 Technical dialogue
Horns Rev 3 timeline February to April: Pre-technical dialogue From May: Technical dialogue 2013 2014 2015 … 2020 September 2013 Contract notice 2 September 2014 Deadline for preliminary tenders From 1 January 2017 Guaranteed connection to the grid Early 2015 Concession contract and construction permit 1 December 2014 Deadline for binding tenders Early 2020 Full operation of offshore farm 29 November 2013 Deadline for prequalification
Horns Rev 3 timeline February to April: Pre-technical dialogue From May: Technical dialogue 2013 2014 2015 … 2020 Early 2015 Concession contract and construction permit From 1 January 2017 Guaranteed connection to the grid Early 2020 Full operation of offshore farm 2 September 2014 Deadline for preliminary tenders September 2013 Contract notice 29 November 2013 Deadline for pre-qualification 1 December 2014 Deadline for binding tenders
Kriegers Flak timeline February to April: Pre-technical dialogue From May: Technical dialogue 2013 2014 2015 … 2020 From 1 July 2018 Guaranteed connection to the grid February 2014 Contract notice 29 April 2015 Deadline for preliminary tenders Early 2020 Full operation of offshore farm 29 April 2014 Prequalification 31 August 2015 Deadline for binding tenders September/October 2015 Concession contract and construction permit
Kriegers Flak timeline February to April: Pre-technical dialogue From May: Technical dialogue 2013 2014 2015 … 2020 September/October 2015 Concession contract and construction permit From 1 July 2018 Guaranteed connection to the grid Early 2020 Full operation of offshore farm 29 April 2015 Deadline for preliminary tenders February 2014 Contract notice 29 April 2014 Prequalification 31 August 2015 Deadline for binding tenders
Nearshorewindprojects Sæby Total of 450 MW North Sea (north) Each farm max. 200 MW North Sea (south) Sejerøbugten Smålandsfarvandet Bornholm
Nearshore wind projects The tendering model will be published this year Dialogue and negotiation Call for tenders September 2015 Pre-investigations: Geological, EIA and MetOcean Grid connection Local joint ownership
The Danish TSO - Energinet.dk Independent public enterprise – owns and operates highways of energy (electricity and gas) Energinet.dk is to ensure security of supply Our finances must break even – non-profit We develop a more flexible power system
Roles of Energinet.dk in OWF Finance, construct and operate platform and sea cable Bringing power from new OWF ashore and strengthen grid Secure that grid connection is available in due time During the last year requested by DEA to conduct pre-investigations and EIA for future offshore wind farms
Investigationsconducteduntilnow- Horns Rev 3 and Kriegers Flak UXO-deskstudy(UnexplodedOrdnance on/belowseabed) Geophysicalinvestigations in wind farm areas Geotechnical tender EIA-surveysinitiated
Horns Rev 3 App. 190 km2pre-investigationarea
Kriegers Flak 110 km2 App. 250 km2pre-investigationarea 69 km2 Kriegers Flak
Grid Connections Energinet.dk establish the offshore platform, the sub-sea cable and the onshore grid connections The developer is responsible for inter-array cabling in the OWF and connecting to the platforms OWF will be connected to the platforms at 33 or 66kV Expenses of Energinet.dk is paid by Danish consumers; not the developer/owner of the OWF’s Construction of the platforms will be initiated in 2014 and finalized in 2016/2018
Upcoming events Technical information meeting in Copenhagen 27th of February 2013 Kick-off meeting for the tendering process May 2013 Followupdated information at www.ens.dk/offshorewind
You can find us at the Danish pavilion 1,450 MW before 2020