An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PH electronics “Headquarters”Refurbishment status

  2. Refurbishment • Air-conditioning in labs • Completely new infrastructure required: • Central cooling unit on roof of bat 13 • New water distribution network • Cooling units in labs • Completed, but 2 labs not yet connected • New electrical installation in labs • Completed • Corridors: • New ceilings: Not yet fully finalized • Paint doors and walls: Done • New lights: Done • New fire detection: Not yet fully finalized • (decoration) slide 2

  3. Offices: • Painting: Done • Entrance: • New floors: Done • Painting: Done • New ceiling (partial): Done • New radiators: Done • New lights: Done • Automate “corner”: Done, Furniture to be installed • “Murs de affiche”: “Done”, Good idea but bad execution. • Vitrine: Awaiting final order • Outside: Awaiting CERN master plan • Two benches for “smoking corner”. • Bike parking places to be moved to back court slide 3

  4. New bath rooms • Completed but lots of minor problems: • Leaks: Holes in new tiled walls to find cause • Ventilation: Smelling from new toilets • Cellars: • Refurbishment of SS-14 for pool storage: Done • SS-13: • Storage area for LHC spare parts: Done • Technical installations for cooling system: “Done” • Renovation of floors (with asbestos): Partially done • Renovation of electrical installations: Planned • Flooding problems: Not solved • Technical investigations ongoing • Multiple causes • Painting and renovation of wooden walls on hold because of flooding problems • Installation of flooding detection/alarm to firebrigade • Cellar unusable until real solution to flooding problem found. • Affected users: PH-ESE storage and labs, LHCb, CLOUD, DT slide 4

  5. 13-2-005: Auditorium refurbishment • Painting: Done • New ceiling with new lights: Done • New ventilation system (with aircond.): To be finalized • Old system removed • Airconducts in room itself done • New ventilation/aircond. system be installed (before summer 2014) • Awaiting video conferencing system finalization • New ceiling in corridor to be installed. • Roof of Bat 14 • In bad state and this seems known since long time • Leaks • Repairs of bad quality • Major repair required • May require scaffolding around whole building !. • Refurbishment should have been done when scaffolding installed for window replacement !. slide 5

  6. Stores/blinds: • In general bad state: Every storm destroys a few • With danger of somebody getting injured ! • Continuous localized repairs made • General refurbishment required • Should have been done when installing new windows ~5years ago slide 6

  7. Summary • Most of our refurbishment work finalized • Remaining: • Flooding in cellar -> Seriously affects works and our use of cellar • Roof of bat. 14, • Finalize 13-2-005 auditorium • Refurbish Stores/blinds • Small things to finalize: Ceilings, toilet problems, etc. • Comments • Work not of “Swiss quality”: Always take cheapest offer ! • Work has taken a loooong time to finish. • We should have made a global refurbishment of whole building • Very difficult/impossible when people still living/working in building • Not enough money • Interface between “players” not always clear: • Client (us) • PH-AGS-SI • GS and the many different parts of GS • Companies • Who follows up on what ? • Memory in system seems limited: Known problems forgotten • Lots of knowledge seems to have disappeared when “old generation” has retired from GS • Significant delays when frame-contracts change • Clearly not enough money for CERN infrastructure refurbishment • Many thanks to: Marie-Noel, Jacques, Bart and Juny slide 7

  8. Presentation from 1 ½ years ago slide 8

  9. Reminder • Reasons for relocation (and making one group) • Get people closer together to enable good daily exchange of experience/expertise/ideas in the electronics domain related to all the different projects we are doing in a large variety of domains (micro-electronics to standard instrumentation) • Assure appropriate lab infrastructure for all our different activates: Clean room – IC testing - opto – general labs – mini mechanical workshop – storage – etc.. • But also keep in mind: • Maintain close/regular contacts with our clients/project partners (experiments) slide 9

  10. Offices • General principle • Long term staff gets individual office to the extent possible. • Large rooms used for multiple students/visitors/fellows/etc. • Air-conditioning • CERN does not any more “allow” to have air-conditioning of individual offices unless for specific reasons. • Exceptions in ESE: • Top floor that can get very hot in summer • 5th floor installed before new “CERN rule” on this. • Offices on south corner getting exceedingly hot in summer because of bad general thermal insulation of our old building. • Comment: Air-conditioning in labs not intended to cool offices via corridor keeping all doors open. • All offices have been painted and should be in good shape. • Remaining: • New lightning • Radiator thermostats • ? slide 10

  11. Labs/workshops • All new labs have been refurbished with appropriate flexible electrical installations (power rails at ceiling) and air-conditioning (some not yet connected to global cooling system). • Each lab is run by a lab responsible that takes care of general state of lab. All other users of labs must agree with this “lab master” on how and when to use the lab. • To prevent complete anarchy seen in some labs in the past. • Same principle applies to all our major instruments: https://ph-dep-ese.web.cern.ch/ph-dep-ese/group_internal/instruments/ESE_Inventory.htm • Electronic keys (not yet on all labs in 5/6th. floor) • Default: People in section have access • Additional access can easily be added (Evelyne) • Electronic keys keeps a log of who have had access when (big brother watching you, that we will hopefully never use) • Unexpected “feature”: Cards must be refreshed once per month via dedicated terminal in building entrance (or on terminal in Evelyne’s office) • Some labs will have particular access restrictions for safety reasons: • Radioactive sources, X-ray machines, Laser labs, Mechanical workshop. slide 11

  12. Some of our labs Pool lab Pool/HV lab Pool lab LVPS lab Opto lab1 Opto lab2 slide 12

  13. More Labs SMD lab1 with ESD floor and ventilation FE/Power lab FE lab FE pixel-laser lab ME prober/X-ray lab Medipix X-ray lab ESE group meeting slide 13

  14. Even more labs IC tester lab ME lab Old IC tester lab Clean room/wafer prober Mini mechanical workshop Pool reception slide 14

  15. Storage Group/section storage SS-14 Group/section storage SS-14 Experiment spare Components Storage in SS-13 under finalization Pool storage SS-14 slide 15

  16. Meeting/training/terminal • 14-4-010: Small meeting room • Booking via Indico (by group members) • Projector, Computer, Camera, Microphone, Phone: Equipped for EVO and phone conference. • Will soon get electronic key • 14-5-22: Training/Termial/Meeting/ME library , , room • Booking via Indico (by group members) • Projector • Electronic key slide 16

  17. Common facilities Large meeting room: 13-2-005 Coffee Paradise Central point for many informal discussions. Only kept alive if certain turnaround(should be OK now) • Old and worn out • Seats keeps people awake • Refurbishment in planning. • Painting, projector • Air-conditioning, heating, seats ? • Public meeting room with booking via Indico slide 17

  18. Planned work (2011) • Finalize refurbishment of cellar of 13: • Component storage • Nitrogen protected storage (bare dies, wafers and delicate components) • 1 -2 labs with infrequently used equipment (Egun, climatic chambers, etc.) • Renovation of sanitary installations • Refurbishment of building entrance • Additional parking places when removing old barracks • “Controlled” car access to back yard • Refurbishment of global chilled water distribution in building. New cooling plant and connection of remaining cooling units in our labs. • New ceilings and painting of corridors in 14. • Painting of stair cases • Other: • Renovate small elevator (just replace “wooden” panels) • Noisy escape stairs • ? slide 18

  19. Entrance refurbishment • Entrance very visible from CERN main road • General refreshment strongly needed • Should be more welcoming. • Get rid of bicycle mess in front • Allow smokers to have a decent place outside with appropriate ash trays. • Allow appropriate use of coffee automates with minimal mess generated from this. • Use available space to have small permanent exposition of electronics/detectors for HEP. • Easy to maintain and keep clean • An initial study has been done by an architect. • Asbestos removal in floor glue: 16k (CERN policy to do this now) • Internal refurbishment: 60k (of which~ 10k for vitrine) • External + bicyles + stair case + water fountain + information panel: ? • WHO PAYS: GS, PH, ESE, ? slide 19

  20. Outline slide 20

  21. “3D” slide 21

  22. slide 22

  23. Cost estimate slide 23

  24. Conclusions • I think we are now very well installed and have all required infrastructure available. • There will still be major work to do this year: • Entrance, Sanitary, Chilled water, Corridors, Stair case, Meeting room, Cellar of bat 13. • I hope financial constraints (or asbestos problems) will not delay this work. • Thanks to you all to have made this possible • PH and GS management (funding and support) • PH-SMI: Jean-Loup, Marie-Noelle, Jacques, Sebastian. • GS: Christophe Martel, Barthelemy Gossuin • ESE: Patrick Petit • All of you who have made this relocation smoothly and efficiently. • When all finalized, I can propose that we organize an open day for visits by our colleagues and collaborators at CERN. • Please let me know of ideas/requests for further improvements. • I think we are now very well installed, even though some of you may have been dreaming about this: slide 24

  25. What we did not get Google slide 25