1 / 7

GLAST TVAC Test Director Organization Update

This update provides information on the organization of the GLAST TVAC test, including the test director, weekly teleconferences, potential face-to-face meetings, and the responsibilities and facilities required. It also includes updates on NRL facilities, mechanical design and fabrication, TVAC preparation and test, and QA and safety. Additionally, it covers the status of NASCOM connectivity, the bakeout of the L-Frame, the GLAST arrival and unpacking, and the NRL test flow.

glorial
Download Presentation

GLAST TVAC Test Director Organization Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Observatory TVAC at NRLAug 1, 2007 Neil Johnson NRL neil.johnson@nrl.navy.mil W N Johnson, NRL

  2. Organization • Brett Pugh has agreed to take on “test director” mantle for organizing NRL option. • Billy Greenrock is GD-AIS Point of Contact • Organizing weekly teleconfs – Mondays, 11:30 EDT • Talking with GD experts for needed info • Potential face to face – GD & NRL – in the next week or two • Scott Clough has agreed to organize turn over fixture • Recover GSFC fixture and get it recertified • Will create ICD or Agreements Document (Pugh, Johnson) • Outlining roles and responsibilities • Defining documentation • Required / provided facilities W N Johnson, NRL

  3. Organization: Continued • NRL Facilities (Mike Van Herpe, Bob Haynes) • Clean tent near TVAC chambers • Staging area in Center High Bay • Need to work power requirements, networking, offices, etc • Mechanical Design, Analysis and Fab – Marc Campell • Turnover fixture adapter plate • TVAC port plates • TVAC Trolley / table adaption to L-Frame • Released drawings – SLAC • Analyses – John Ku • Fab – NRL / SLAC. • TVAC preparation and test: Brett Pugh • GD Rep: Billy Greenrock • Van Herpe will organize chamber, CDAS, power supplies, etc • QA and Safety: ??? W N Johnson, NRL

  4. NRL TVAC Status • No show stoppers except … • Howard Dew suggests that NASCOM connectivity to NRL, if required, will take 240 days • Jack Leibee has action to investigate • Need to understand GD network requirements • NRL Contract • Neil working LAT CR to cover work thru August. • Bakeout of L-Frame at NRL is on the rise – decision 3 Aug. • GD’s first choice does not have needed capabilities • Target date is ~ 24 Aug. availability of L-Frame • Potential assembly and test of WattRod heaters during bakeout • New target for start of TVAC: 15 Oct • Obs arrival at NRL ~ 1 – 7 Oct. • NRL Access and Badging • Should start identifying list of people needing access and begin badging paperwork. Foreign Nationals???? W N Johnson, NRL

  5. L-Frame Bakeout (TBD) Prep Work Network connectivity verification Pathfinding Turnover and TVAC Trolley/Table TVAC chamber verification (part of bakeout?) GLAST Arrival, Unpack EGSE setup and checkout Post-ship checkout GLAST turn over Chamber Installation Open door CPT TVAC ETE and other testing Post TVAC CPT Post TVAC Potential Flow Solar Array ReInst Prop System Checkout ETE test Optical Alignments Final mass properties ETE test Pre Ship Review Ship to Cape NRL Test Flow W N Johnson, NRL

  6. Observatory Turn Over From Scott Clough – GSFC Ransome Table • Ransome Table Details • Model 500-P • Capacity 50,000 lbs • Rotation Torque 600 K in. lbs • Tilt Torque 1175 K in. lbs • C.g. At 12" above and 12" eccentric • Table rotation .007 RPM min .3 RPM max • Weight 25300 lbs • 460 V 3 phase • Plug, 30A. 480V. 3 phase • Issues • Potential conflicting use by another GSFC project • Ownership and documentation • Certification • Need 2x mass and torque test • If Issues can not be favorably resolved, NRL has ICM turn over fixture that could be adapted. Need to quickly resolve the need for this work. W N Johnson, NRL

  7. Summary • Critical Paths? • Network connectivity to NASCOM and GD-AIS(?) • Identification, certification, adaptation and installation of turn over fixture • Adaptation of L-Frame to NRL TVAC Trolley / Table and necessary analyses / certifications to demonstrate safety. • Modification of test procedures / plans for NRL environment • Configuration and programming of thermal control system • Programming of TC monitoring and displays • Procedures, Configurations • Everything done to GD procedures and drawings? • Modifications for NRL facility / processes? • Risk Mitigation • Pathfind with version of L-Frame (#1) and mass model W N Johnson, NRL

More Related