Highly Modified Binder Yield Performance Gains for I-40 Project 17th Annual Conference & Workshop Grand Hyatt Seattle, Washington February 9-11, 2016 Kenneth Ray Hobson, P.E.
Outline • NCAT 2009 Cycle N8 • Caddo County I-40 • 3 Year Fatigue Research at OU • LTPP SPS-10 • Wagoner County GTR • Conclusions
NCAT 2009 Cycle N8 OK Sections http://pavetrack.com/construction.htm
NCAT 2009 Cycle N8 • 2006 Cycle Perpetual 10″ thick Experiment • Failed after 10 MESALs • 2009 Cycle • Milled and Replaced 5.0″ • Two Fabric Types • Delay Bottom-up Fatigue
NCAT 2009 Cycle N8 • After 3.5 MESALs • Mill and Replace (PG 76E-28) • 1.25″ — 3/8″ [9.5 mm] NMAS • 3.25″ — 3/4″ [19 mm] NMAS • 1.25 ″ — 3/8″ [9.5 mm] NMAS • RIL (+0.2% Pb)
NCAT 2009 Cycle N8 • Lasted 16.2 MESALs
Caddo County I-40 – 10/12 • Mill 5″ & Replace (PG 76E-28) • 3/4″ — OGFSC (PG 70-28 OK) • 1.5″ — 3/8″ [9.5 mm] NMAS S5 • 2.5″ — 3/4″ [19 mm] NMAS S3 • 2.5″ — 3/4″ [19 mm] NMAS S3 • 1.5″ — 3/8″ [9.5 mm] NMAS S5 • RIL (+0.2% Pb)
Caddo County I-40 – TFHRC Damage
3 Year Fatigue Research at OU • Select Best Fatigue Test for ODOT • Specify Fatigue Test Limits • Draft Fatigue Test Method if Needed
3 Year Fatigue Research at OU • Purchase and Install Fatigue Test Equipment at ODOT • Purchase and Install AMPT at ODOT • Train ODOT Personnel
3 Year Fatigue Research at OU • Chose SCB-LTRC Test Method • Delay Final for LTPP SPS-10 Research
LTPP SPS-10 Min.
Wagoner County GTR • ODEQ Sponsored Research • OU GTR Literature Review • ODOT FWD Tests • ODOT GTR Mix Designs • OU SCB-LTRC Tests
Conclusions • Based on N8 and Caddo County Experience and NCAT SN of 0.54 • Design Thickness -20%
Conclusions • ODOT Adopt Fatigue Test 2018 • Dynamic Modulus • LTPP SPS-10 Fatigue Tests Complete Late 2016 • Wagoner County GTR • Construct Spring 2016 • Fatigue Performance is Key
Questions? khobson@odot.org