1 / 17

Drive Beam Linac , surface building and equipment

Drive Beam Linac , surface building and equipment. B. Jeanneret, G. McMonagle August 2010 With material thanks to E.Jensen , R. Wegner , A. Aksoy , D. Siemaszko & D. Nisbet , J. Osborne, N. Baddams. parameters. Cell structure R. Wegner , E. Jensen, A, Aksoy , D. Schulte.

gordon
Download Presentation

Drive Beam Linac , surface building and equipment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Drive BeamLinac , surface buildingand equipment B. Jeanneret, G. McMonagle August 2010 Withmaterialthanks to E.Jensen, R. Wegner, A. Aksoy, D. Siemaszko & D. Nisbet, J. Osborne, N. Baddams

  2. parameters

  3. Cell structureR. Wegner, E. Jensen, A, Aksoy, D. Schulte • RF active section : 20 cells × 0.1m = 2m • Coupler, interconnect : 0.5 m • Quad, MBCO, BPM : 0.6 m • TOTAL : 3.1 m • May needadjustement ( Vacuum equip. for pressure p ~ 5 10-11 Torr, … ) 15 MW klystrons Acc. V/module 3.2 MV 819 cells / linac Total length 2540 m Plug-power for RF (2 linacs): 290 MW ( 0.115 MW/m) 3100 Linac 1

  4. Magnets – quadrupoles • N=819 Q, spaced by 3.1m for eachLinac (total Linaclength 2540m) • R = 3.7 10-2Ω, Imax = I0 = 414 A, pmax = 6.3 kW • Gradient must follow the beamenergyincrease • I(n) = nI0/N • Power schemesimilar to DECEL_Q advisable • Total power : P = Npmax/3 = 4 MW I(n) I0 = 414 A 1 (s=0) N=819 (s=2540m)

  5. Power & Cooling • Total plug power for RF : Ptot = 290 MW • 140 MW to beam150 MW to heat • Total power for magnets (Quad + Sol): 9 MW to heat • Total installed power : • Pinstalled = (1+ ε) × ( 290 + 9 ) • withε the 18kV conversion yield (seewith Daniel/Cesary) • Add for light, cranes, safetysystems, … • Total cooling power (tunnel & surf. Blg) : • Pcool = (1+ ε) × ( 150 + 9 )

  6. DB Linac, tunnel • Total lengthnow : 2540 m • conflictwith EHN1 •  move towards top of the drawing, seebelow Water cooling pipes, Cabletrays Loads 1200 3000 1000 1000 800 6000

  7. 2m DB Linac building Top view (half) 3.1m Width: 23.5m Height: 9m ? Length : 2540 m 0.75m 3m 5m 3m Klystrons are transported along the central path. A technical area without RF must beforeseenat crane extremities End view (half) 11.75m 3.5m ? 3m 1.5m 2.5m 4m 2m

  8. Top View of DB Linac xx • A small building isneeded for 18kV station ~ everyyy = 40 m ? • Size : xx by xx , xx = ? • Installed power 4.6 MW/40m xx Awaiting data From RF and EL ~yy 23000

  9. Top view of DB Linac buildings 2140 m 23 m 30 m Fixed point (beforedelayloops) 420 m Underground & surface (slide 6 & 7) Underground, Same section as in slide 6 (CDR, to berevised for TDR)

  10. Site implementation DB Linac (undergroud and surface) - Long segment : 2140 m - Short segment : 420 m Loop : underground - radius : 30 m Axis separation of the segments : - 30 m

  11. 500 GeVdelayedtransfer for the drive beam B.Jeanneret , July 2010

  12. Input data • Time delaybetween e+ & e- DB train : • The two sets of 5 trains each 240 ns are produced one after the otherwith a single Linac • Δt = 5 × 24 × 240 ns = 28800 ns Δ = 8640 m • The trains must besynchronouswhen passing along the end of the Main Linac

  13. Coming back to surface Case 1 G D C I H F TA • Case 1 : • e+ trains come first and go through : AFGHI-TA-IHGFBCD • e- trains go through : AFGHI • Case 2 : • e- trains come first and go through : ABCD-TA-DCBFGHI • e+ trains go through : ABCD r x From CR2 B A Blue : additionalbeam line Red : additional tunnel D,I : end of ML Case 2 G D C I H F x TA r From CR2 B A • AG = 770 • GH = 1449 • HI = CD = 25 (500GeV) • AC = 2117 • AB = 2r = 524 • TA = 146 • With y = AG+GH+AC+2*HI • x = (Δ + 2r – y –TA)/2 • x(case1) = x(case2) = 2316 m See ~/clic/CDR/500gev/bypath.sce

  14. Impact for hardware / through surface • Case 2 simpler • x / Lsector = 2316/877 = 2.64 sectors • one extra DB line to behoused in the main tunnel • Civ. Eng. : • one-quartercircle of surface tunnel to beadded • Line e+ down to tunnel : • wideenough to accomodate a 3rd beam line. • 1 additionnalturn-around , of type ‘DB’ • Additionalbeamlines: • 3909 m (AC-2r+x) of type ‘DB-LTL’ • 1 dedicatedturn-around , of type ‘DB’

  15. Use a by-patharound IP • D,I : end of ML (500 GeV) • e+ in D & e-in I : synchronous • Δdb = 8640 • ID = 2×1870 , TA = 146 • δbp = 14 • x = (Δdb - δbp - ID –TA)/2 = 2361 m • x / Lsector = 2361/877 = 2.70 sectors IP I D C x TA From CR2 A see :/Users/Bernard/clic/CDR/500gev/bypath_ugnd.sce

  16. Impact for hardware / underground by-path • x / Lsector = 2361/877 = 2.7 sectors • one extra DB line to behoused in the main tunnel • Civ. Eng. : • 374 m of tunnel to beadded for by-path • 1 additionnalturn-around , of type ‘DB’ • Additionalbeamlines: • 3740 m ( DI ) of type ‘DB-LTL’ • 1 dedicatedturn-around , of type ‘DB’ • Beamlines not needed : • Surface loop & descent down (2460 m) • Advantage : disconnectedfrom surface changes for Main Beam

More Related