L2 Status James T. Linnemann MSU Collaboration Meeting September 14, 2001
Who? • Now commissioning: • Arizona, Columbia, Maryland, Michigan/CDF • MSU, Munich, Nebraska, NIU, Oklahoma • Saclay, Stony Brook, UIC, Virginia • Fermilab ESE (Green, Kwarciany, Zmuda) • Coming Soon • BU, Florida State, Orsay • A lot of good, hardworking people are responsible for L2 progress.
Infrastructure • Power, cooling, cabling all in place except • Intra-crate cables • Last run of muon cables being re-cut • Safety clearance for power in process • All cards needed built and on site except • last 11 alphas being assembled this week
FIC: G-link receiver(all crates but muon) • FPGA code being tweaked • Some vme problems remain • commissioning modes only; progress being made • Extra data word in G-link? • Fix being tested • FPGA compiler problems probably resolved • Distraction: “test” version used nonexistent resources • Fermilab/ESE support for commissioning • Met this week with Saclay experts
MBTworkhorse I/O card • 31 cards in hand (24 work; 16 at Fermi) • 4 need diagnosis/repair; 3 dead; 11+6 needed • Before install: stable SCL firmware • Estimate: September/October installation • firmware all written; being debugged (good turnaround) • Scl_init sequence; L1, L2 busy (easier) • Multi-card broadcast: need testing at FNAL • 128 bit fanout needs testing at FNAL with Edmunds: Oct • Some marginal timing being chased • Results write to Global: needs to be re-integrated • May need to tweak output amplitude • Monitoring functions: need to test at FNAL
Alpha • First Production: • 4-6 fully work (7 max); 2 back soon; break/fix about 1/week • Most: multiple vias fixed and a BGA replaced • 17+2 abandoned • Broken CIA BGA not replaceable (center of board; vias too fragile) • PIO to Alpha not working (firmware)early October • concentrate on 1 Alpha/crate • Second Production: • Pre-production boards work • DMA fixes incorporated in layout • Learned can successfully replace CIA BGA (better than unreliable socket!) • new supplier for raw boards, better assembly (failures diagnosed; site visits) • 11 more being built now: earliest end September • Need 15 for nominal system (+7 for test stand)
Betareplacement processor • Intel Compact PCI card • 2-3 Alpha in CPU • First card received and being tested • Hold in 9u card with custom devices (3 BGA’s) • Universe Chip VME interface • commercial 64-bit PCI interface chip • Mbus and other logic in FPGA • Good start on low-level software • Prep for PCI device drivers • Schedule: (quote soon) • Schematic done; starting layout • Firmware specs written; starting Verilog coding soon • Prototypes available for testing December • Production: early summer
CIC and SFO • CIC (L2Muinput card) installed; inputs cabled • SFO (fanout): all but 2 at Fermi • Needed by Muon system, and test stand • Very useful for commissioning • May have other uses during running • All cards work in most important modes • For one mode, have to hand-select cards • Only need 2 working in 1:12 fanout mode • Investigating why only half do, but half of 25 is plenty
SLIC • Basic Operating System done • First algorithm tests (Mu Central) OK • Meet speed and efficiency requirements • Other algorithms ready for download • tested in emulator • Implementing monitoring scheme
Miscellaneous Interface Hardware • 16 to 128 bit mux add-on to MBT (UMd) • Returns L2 trigger mask to L2HWFW Sep/Oct • L1HWFW to L2 Global (via FIC) (MSU) • Optical Split: L1 trigger mask Aug/Oct • dummy content: fixed + event ID • Monitoring of Alphas by L1 Scalers (MSU) • Passive cable formatting card Oct
CommissioningAt Last • L1SCL-MBT-Alpha-VBD-L3 milestone met • One channel “data”, real frame software, in MCH • Need to verify format from SAM • Muon system has seen real inputs-CIC-SLIC • L1 format needs correction • Scint format OK but L2&timing interfere: errors • MDT format OK • PDT unformatted: October? • Current tests: • SCL_INIT for MBT-Alpha (for permanent MCH running) • Add 2nd channel of data (FIC-MBT-Alpha-VBD-L3) • real algorithms into SLIC; timing Fwd Mu already • Muon: 2nd or 3rd input: CIC-SLIC-MBT-Alpha-VBD-L3 • One event pushed through STT prototype vertical slice • FRC, STC, TFC: CTT roads, SMT clusters, fit
Arrival of L2 Inputs When inputs steadily available (subset, full) • L1 Trigger Mask to Global (August, October) • Cal (September?, November?) • Muon • Trigger (L2 software not tested) (June, November) • Detector (August,October?) • CTT,CPS (October,November) • FPS (November,December) • COOR programming September?
Online Software ( & Risks) • Alpha: • Much of structural software exists in simulation • Control/data flow for preprocessor and global • Loader and modified Linux kernel; • Developing drivers in EBSDK (fast turnaround); check in Linux • Draft drivers/setup for MBT and event loop • Some alpha firmware problems (PIO needed for A-W split) • SCL_INIT—in progress (complex) • VME driver, buffer allocation (OK) • Verify byte order etc to L3 • Error logging and beginnings of monitoring: testing • Linking, downloading to Worker; Linux 7.1 releases needed • Admin/Worker control; data flow software • few Alphas, so concentrate on 1-alpha crate for now • SLIC: • Basic operating system in place • monitoring; algorithms need download; scl_init
Online Software Plans Event data flow late Aug • Worker with filter code Sept • Multi-alpha (as available) Oct/Nov • interrupts for speed as needed Dec/Jan • Coor script downloading via TCC: Late Sept • Till then, configure from hand-edited file • Online and in TSIM • Data Flow Monitoring test Sept/Oct • Errorlogger to screen/S.E.S. Oct/Dec? • Global + Preprocessor Oct-Nov • FILTERING! (if have enough inputs…) • Verification: online vs. TSIM • 1st version running now; testing data capture • Needs pretty good data to be useful Oct/Nov?
Algorithms: in TSIM, downloadable; some L1SIM problems • Mu L1; Central alpha, DSP working, ready to download output fmts need update Fwd DSP in CVS; next release (alpha already there) • CTT base algorithm , tau working Tau tuning, slow movers waiting for postdoc hirewhen? • PS • CPS running in TSIM; needs better L1 • FPS written not released (no L1PS) when? • Cal all running in TSIM • e = Run 1B L1.5 • j merge needs work (interference with beta) • MET = L1for now • Global some running in TSIM now • e(cal,cps,track), j(cal); tracks; deta, dphi (e: fps-ready) • Ht, Mass, MET; rsep coming • Mu(with ctt), but no tau • Need Studies, Timing, Tuning! Lost 2 maintainers
Summary • Commissioning is underway in earnest • Some real inputs—need more to do physics • Mu, cal, ctt, cps is probable order • Most hardware in hand • Remaining alphas soon, I hope • Firmware written; commissioning it now • MBT, Alpha, FIC • Crucial scale-up tests in coming weeks • All hardware in crates • Multiple inputs • Algorithm downloads
Board Summary:Dates, Risks • SLIC January 2001 • Monitoring software • Crates/Power/Cables September • ORC; CIC crate • FIC September? • Commission; FPGA code problems? • MBT September? • FPGA code • Alpha now; September • Fragility of 4-6 from 1st production • PIO firmware • Fallback: Beta—next year • CIC,SFO August; September? • Install/Commission • Crate population, intra-crate cablingSeptember/October
Progress since Feb • Alpha • cards for commissioning; start final production • Fixed DMA; Beta started • FIC • Fixed output signal; FPGA work resumed • MBT • All firmware written/drivers (being debugged) • Integration testing with Alpha at 2 sites • multi-channel DMA, capture of SCL input info • CIC/SFO built • All power, most cabling • Software • Drivers for all devices written (being tested) • Most algorithms in TSIM • Real data sources in mu • data flow L1SCL to L3
Where do we put our Alphas?Staging; rotating tests; A+W Aug-Sept (5-10) • 1 Maryland • 2 Test Stand/UIC • 1-2 Global • 1-2 Mu/Cal (turns?) Oct-Nov (5 to20) • 2-4 Mu • 1-4 Cal • 1-2 Global • 2-5 CTT,PS • 1-2 Test stand • 1 Maryland/Va • 1-4 UIC/Test Stand
L2 Cards & Namesbuild/operate • FIC G-link to Hotlink Renardy, Mur (Saclay) Buehler, Kostas, Heinmiller (UIC) Kwarciany (FNAL) • MBT Hotlink, MBus, other I/O Giganti, Bard, Baden (Maryland) +Toole/ Schwienhorst • Alpha main processor (Campbell, Miller UM); Buehler,Heinmiller,Kostas, Varelas (UIC) Hirosky (UVa) Kwarciany/Zmuda (FNAL) • SLIC ProcessorSippach, Evans (Nevis/Columbia) Kothari, Christos (CU); Maciel, Fortner,Uzunyan(NIU) Christiansen, Strohmer, Trefzger, Schaile (Munich) • CIC, SFO SMB to RJ45 Hotlink; Hotlink fanout Lewis, Snow (Nebraska) Tester: Johns (UAZ) Hansen, Baldin, (Anderson) FNAL Maciel, Kothari, Fortner • VBD; Bit3 L3, TCC Zeller, Cutts; Commercial Mattingly (Brown); Schwienhorst (MSU)
Commissioning • Limiting factors: • Stable, fully functional L2 Cards (ouch) • MBT’s with full functionality • FIC: lack of on-site expertise • Lack of reliable system to modify firmware • Alpha: lack of firmware expertise on-site • Manpower (trained—getting better) • Big conflict with • Prototype testing (MBT, CIC, SFO) • Production debugging (Alpha) • Beta (fallback plan for Alpha) • Rick Kwarciany is part-time integration engineer • Alpha software for commissioning • Limited, in turn, by above problems • Availability of inputs • Real, or test; becoming limiting factor
Preprocessor Chains:Commissioning Scale ..20..40..60..80..100% • 0%Connectivity not tested • 20Signal compatibility demonstrated • 40Correctdata transfer once or usually; or physical layer (BIST?) full speed, error rate OK • 60Fake data, repeated transfers, error rate OK • 80Full speed fake data, error rate ok, >1 day • 100%Real data full cards, in system, full speed, errors OK, > 1 week
Preprocessor Chains 0%..20%..40..60..80..100% • L1DFE FIC..SFO MBT Alpha L3 (test stand) • L1Cal FIC SFO MBT Alpha VBD L3 (DAQ) • MuFE CIC SLIC SFO MBT Alpha L3 • Mutest CICSFOSLIC SFO MBT Alpha L3 • Alpha MBTMBT Alpha (2 crates) • Alpha Alpha • L1SCL MBT Alpha VBD L3 • MBT SFO patch panel MBTAlpha VBD L3 (test stand) • L1SCL MBT SFO SLIC MBT Alpha • L1FW FIC MBT Alpha • Alpha MBT L2FW ….