1 / 23

David Stedham

The North Wales MAN. David Stedham. Network Development Manager University of Wales, Bangor. Topics. Background Procurement MAN construction Phase1 Phase 2 Work items The future. 8Mbps Backbone. 2Mbps Links. Topics. Background Procurement MAN construction Phase1 Phase 2

grace-guy
Download Presentation

David Stedham

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The North Wales MAN David Stedham Network Development Manager University of Wales, Bangor

  2. Topics • Background • Procurement • MAN construction Phase1 Phase 2 • Work items • The future

  3. 8Mbps Backbone

  4. 2Mbps Links

  5. Topics • Background • Procurement • MAN construction Phase1 Phase 2 • Work items • The future

  6. Timetable • June/July 2000 Expression of Interest • August/September 2000 Tender • October 2000 Cable & Wireless chosen

  7. Timetable 2 • Spring 2001 BT withdraws 8M lines, C&W re-plan • October 2001 Contract signed • December 2001 Backbone deadline missed • March 2002 Colleges deadline missed

  8. Topics • Background • Procurement • MAN construction Phase1 Phase 2 • Work items • The future

  9. May June July August PHASE 1

  10. May June July August PHASE 2A

  11. May June July August PHASE 2B

  12. May June July August NWMAN

  13. May June July August NOW

  14. NWMAN

  15. NWMAN + LLNW

  16. Timetable 3 • May 2002 Fibre routers in place Some radio links deployed Router & fibre@NEWI to be installed Phase 1 deadline 20th May • July 2002 Phase 2 deadline

  17. Topics • Background • Procurement • MAN construction Phase1 Phase 2 • Work items • The future

  18. Work Items • Finish building network • Appoint full-time Support Officer • Finalise extended hours call-out arrangements • UKERNA Transition Plan • LLNW • WVN

  19. The Future • More HE/FE sites - ELWa sites - Partner sites • Other bodies - Public sector - Private sector • All - fibre backbone • All-Wales MAN

  20. The Future • More HE/FE sites - ELWa sites - Partner sites • Other bodies - Public sector - Private sector • All - fibre backbone • All-Wales MAN • 2005 - Re-procurement

  21. The North Wales MAN

More Related