An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Providing Solutions to Improve Business Processes™ iPurchase Implementation Overview for Monday , March 22, 2010

  2. Agenda • ISS Group Overview • Wellman Products Group iPurchase Implementation • Overview of Wellman Products Group • Wellman Products Group iPurchase Objectives • Implementation Challenges Faced • Timeframe of Implementation • Results to Date • iPurchase Software Demonstration • Q&A

  3. ISS Group: Summary • Founded in 1986 (www.issgroup.com) • Implemented ERP for Manufacturers1986 – 2000 • MFG/PRO 1995 – 2000 • Developed 1st MFG/PRO eCommerce application with QAD in 1996 • Today: Web-based Business Process Improvement • Solutions for the QAD ERP User Community • eProcurement • Energy/Asset Management • Sales Force Automation

  4. ISS Group: Clients

  5. Wellman Products Group • Parent Company - Hawk Corporation • Manufactures High Performance/Severe-duty Friction Products - Cat, Deere, Komatsu, Aircraft, Hawk Performance • Brakes • Clutches • Seven Locations • Corporate / R&D - Solon, Ohio • Mfg sites in the US – 3 • Akron and Medina Ohio, Catoosa, Ok • Canada – 1 • Italy - 1 • China – 1

  6. Wellman Products iPurchase Objectives • Streamline the requisition and purchase order process • Cut the time to process a requisition at a minimum in half • Eliminate data entry errors - no double / triple data entry • Electronic Routing for approvals – • Complete tracking of the requisition from Requisition to P.O. • Complete transparency of the approval process. • Electronic data storage and retrieval of requisitions and attachments. • Beneficial in many ways, Sarbanes, ISO compliance. • Saves $ in terms of paper, toner, printer wear etc. • Result in a minimum of 1 FTE in terms of efficiency

  7. Implementation Challenges Faced • Culture • Breaking down of internal barriers • Getting buy in across the sites • Across different levels of users/management • Change Management • Resource Constraints • Learning curve • QAD and Legacy System integration • P.O. Printing • P.O. Configuration • Field alignment from QAD to iPurchase

  8. Timeframe of Implementation • Opening Discussions held in early 2009 • Project approved in May 2009 • Project Kick Off June 2009 • Approval Rules & Configuration July 2009 • SOX – Data Compliance Review / Signoff – Aug 2009 • Training and Testing Scripts completed – Sept 2009 • System Test / User Training – (Oct thru Nov) 2009 • System Live at all sites December 17th 2009

  9. Results to Date • System has been operation since December of 2009 • To date – thru first 3 months ~ 2200 Req’s processed. • Overall positive feedback • Still working thru the learning curves • System integration iPurchase/WPG process tweaks continuing • WPG is seeing the benefits/efficiencies/availability of data • Finish Implementing Punchouts • Implement P.O. Change Order Process Next steps

  10. Industry Analyst’s “On average, e-procurement solutions reduced requisition-to-order cycle cost and time by 49% and 65%, respectively.” The e-Procurement Benchmark Report August 2008 - Aberdeen Performance AreaBeforeAfter Requisition-to-order costs $51 $26 Requisition-to-order cycle time 9.6 Days 3.4 Days Spend under management 42% 60% Percentage of maverick spend 33% 20% Source: Aberdeen Group, August 2008 “For every $1 in sales, a company spends 50 to 55 cents on purchased materials. Reductions in purchasing costs translate into dollar-for-dollar improvement profits.” Tim Minahan, Managing Director Aberdeen Group

  11. iPurchase Integration with QAD – No Data Replication! QAD Tables Purchase Orders Approved Requisitions are converted into QAD Purchase Orders Supplier Master Product Master Codes Comments iPurchase Functions Requisitions iPurchase Tables Approval Process Requisitions

  12. iPurchase: Roadmap • Current version v5.4 • Minor Enhancements and Patches for v5.x through 2010 • Version v6.0 scheduled for release by end of Year 2010 • Partial list of features planned for v6.0 • Sourcing (RFQ process) - Complete • A/P Invoice Reconciliation and Approval • Integration with Infor Asset Management - Complete • Integration with QAD MRP • Enhanced Report Writer

  13. iPurchase: Demonstration • Web 2.0 Technology • eCommerce Punch-out Capable • Hosted Catalog • Rules Based Approval Workflow • Purchasing Analytics (UNSPSC) • Download to Excel • Line Item Approval • Mobile Functionality • Purchase Order Inquiry/Re-print • SOX Compliant

  14. Questions? Contact Us! Andy Weinstein 908-832-1384 aweinstein@issgroup.net