An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. All Experimenters’ Meeting October 01, 2012

  2. Shutdown 2012 Machine Status: All machines off until the beginning of November 2012 TeV & Muon Rings – Partially available for tours with approval and appropriate training Site is currently being powered from Kautz Road SubStation. Master SubStation will be back this month!

  3. Power Outages • Master SubStation • Monday, October 22nd @ 0700-0730 • Take Master SubStationoff KautzRoad SubStationbackfeedand reconnect to transmission line 11120. • Impacts – Most of site except Main Injector and Village. • Kautz Road SubStation • Monday, October 29th @ 0700-0730 • Put jumpers on 14419 • Impacts – Main Injector. • Feeder 40 (AD Linac & Cross Gallery) • Saturday, November 3rd @ 0700-1630 • Perform maintenance on Feeder 40 • Impacts – Linac, Cross Gallery, MCR, & AD Computer Room. • No Controls System from Friday, November 2nd @ 1700 until Monday, November 5th @ 1200

  4. Cooling & Power Outage • Feeder 44 (Wilson Hall) • Sunday, November 4th @ 0700-1630 • Perform maintenance on Feeder 44 • Impacts – Wilson Hall, WH5NW, WH8E (Fiber Central), LHC ROC (Remote Operations Center) will not have network • Generator Power – Telecommunications Equipment Room, Communications Center & ROC • “Ask a Scientist” moved to CDF • CUB Cooling (Wilson Hall & AD Areas) • Sunday, November 4th @ 0700-1700 • Install electrical barrier in 4160 cabinet • Motors and pumps will be shut down • Impacts – Wilson Hall, MCR, Mac Room, Cross Gallery, Booster Tower and Galleries, AD Computer Room, and all Accelerator cooling systems • Spot Coolers – Telecommunications, Communications Center, Mac Room, & MCR

  5. Shutdown 2012 Power Curtailment • One hour test occurred on Wednesday, September 12th • We stayed below our 25MW level • Our readings show us at 19.5MW for the duration of the test • Haven’t heard any feedback from Energy Curtailment Specialists (ECS)

  6. Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.html ANU - http://www-cons/ Proton Source -http://www-ad.fnal.gov/proton/protonsched/shutdown2012.html