Preliminary Test Plan for Asphalt Overlays on CC2 Rigid Pavements. Trafficking completed on CC2 test items December, 2004. Rubblizing of north side completed January, 2005. Five-inch P-401 asphalt overlay completed June, 2005. Plan View of Single PCC Test Item. Shoulder. 15 ft x 15 ft Slabs.
E N D
Preliminary Test Plan for Asphalt Overlays on CC2 Rigid Pavements • Trafficking completed on CC2 test items December, 2004. • Rubblizing of north side completed January, 2005. • Five-inch P-401 asphalt overlay completed June, 2005. 1
PlanView of Single PCC Test Item Shoulder 15 ft x 15 ftSlabs 60ft Transition Transition 75ft 2 Shoulder
Profile of Test Items Before Rubblization and Overlay MRC MRG MRS 17in. T5 T6 12 in. Concrete 12 in. Concrete 12 in. Concrete 17in. ~4 Feet of Rebuilt Subgrade CBR 7-8 (total subgrade depth of 9 feet) 6 in P-306 econocrete 10 in. P-154 subbase 6 in P-154 subbase 3
Rubblized on the Left (North) and As-Trafficked on the Right (South) Before Overlay 6
Trafficking CC2-O • Trafficking will start after the asphalt has reached temperature consistently above 70 deg F – about the middle to end of June. • Trafficking will end when the temperature of the asphalt has dropped consistently below 70 deg F – about middle to end of October. • Load in both wheel tracks will be four-wheel at 54-in dual spacing, 57-in tandem spacing, and 55,000 lb wheel loads. 8
Additional Activities During Trafficking of CC2-O • Transverse profiles for each test item and each wheel track. • HWD measurements for each test item and each wheel track. • Visual surveys. • PSPA measurements of asphalt modulus as frequently as possible. 9