380 likes | 394 Views
Learn how to determine relevant cash flows, evaluate project acceptability, set bid prices, and calculate annual costs. Understand various types of cash flows and their impact on investment evaluation. Explore examples and solutions for practical application.
E N D
Chapter eight Making capital investment decisions
Learning objectives LO8.1 Understand how to determine the relevant cash flows for a proposed project. LO8.2 Understand how to determine if a project is acceptable. LO8.3 Understand how to set a bid price for a project. LO8.4 Understand how to evaluate the equivalent annual cost of a project.
Chapter organisation • Project cash flows: a first look • Incremental cash flows • Project cash flows • More on project cash flows • Some special cases of discounted cash flow analysis • Summary and conclusions
Project cash flows • The incremental cash flows for project evaluation consist of any and all changes in the firm’s future cash flows that are a direct consequence of undertaking the project. • The stand-alone principle is the evaluation of a project based on the project’s incremental cash flows.
Types of cash flows • Sunk costs a cost that has already been incurred and cannot be removed incremental cash flow. • Opportunity costs the most valuable alternative that is given up if a particular investment is undertaken = incremental cash flow. • Side effects erosion the cash flows of a new project that come at the expense of a firm’s existing projects = incremental cash flow. continued
Types of cash flows • Financing costs the interest rate used to discount the cash flows reflects, in part, the financing costs of the project incremental cash flow. • An investment of the firm in the project’s net working capital represents an additional cost of undertaking the investment. • Always use after-tax incremental cash flow, since taxes are definitely a cash flow.
Investment evaluation Step 1 Calculate the tax effect of the decision. Step 2 Calculate the cash flows relevant to the decision. Step 3 Discount the cash flows to make the decision.
Example—Investment evaluation • Purchase price $42 000. • Salvage value $1 000 at end of Year 3. • Net cash flows: Year 1 $31 000 Year 2 $25 000 Year 3 $20 000. • Tax rate is 30%. • Depreciation 20%, reducing balance. • Required rate of return 12%.
Year 0 Year 1 Year 2 Year 3 Tax paid (6 780) (5 484) 1 764 Net cash flow 31 000 25 000 20 000 Salvage value 1 000 Outlay (42 000) Cash flow $(42 000) $24 220 $19 516 $22 764 Solution—Cash flows
Solution—NPV and decision Decision: NPV > 0, therefore, ACCEPT.
Interest • As the project’s NPV is positive, the cash flows from the investment will cover interest costs (as long as the interest cost is less than the required rate of return). • Interest costs should not, therefore, be included as an explicit cash flow. • Interest costs are included in the required rate of return (discount rate) used to evaluate the project.
Depreciation • The depreciation expense used for capital budgeting should be the depreciation schedule required for tax purposes. • Depreciation is a non-cash expense; consequently, it is only relevant because it affects taxes. continued
Depreciation • There are two methods of depreciation: • prime cost (straight-line method in accounting) • diminishing value (reducing balance method in accounting) • Depreciation tax shield = DT where D = depreciation expense T = marginal tax rate.
Disposal of assets • If the salvage value > book value, a gain is made on disposal. This gain is subject to tax (excess depreciation in previous periods). • If the salvage value < book value, the ensuing loss on disposal is a tax deduction (insufficient depreciation in previous periods).
Capital gains tax • Capital gains made on the sale of assets such as rental property are subject to taxation. • For taxation purposes, the calculation of a capital gain is complicated and depends upon whether the seller is an individual or an entity, such as a company or trust. • Capital losses are not a tax deduction but can be offset against future capital gains.
Inflation • When a project is being evaluated, anticipated inflation would be reflected in the estimates of the future cash flows and the interest rate used as the discount rate in the analysis. • As a result, there will be no distortion to the analysis by not identifying inflation specifically.
Incremental form of analysis • The description ‘incremental’ is often replaced by ‘marginal’. • The advantage of using a marginal form of analysis is that there will only be one calculation and not two. • By using a marginal form we are implicitly analysing one option: that is, to do nothing. • The sign of the NPV tells us whether or not it is sensible to change.
Example—Incremental cash flows A firm is currently considering replacing a machine purchased two years ago, with an original estimated useful life of five years. The replacement machine has an economic life of three years. Other relevant data is summarised below:
Solution—NPV and decision Decision: NPV < 0, therefore, REJECT.
A note on cash flows • Cash flows do not always conveniently occur at the end of the period. • Taking revenue at the period end is a conservative approach to evaluation. • If the facts make it necessary to take cash flows as occurring at the beginning of the period, this only requires a minor adjustment to the analysis. • The period examined could be yearly, monthly or even weekly. If so, the discount rate must match the period (e.g. a weekly analysis needs a weekly rate).
Setting the bid price • How to set the lowest price that can be profitably charged. • Cash outflows are given. • Determine cash inflows that result in zero NPV at the required rate of return. • From cash inflows, calculate sales revenue and price per unit.
Example—Setting the bid price • Consider the following information: • A local distributor has requested bid for 5 trucks each year for the next 4 years. • You can buy a truck for $12 000. • Need to lease a factory space for $30 000 per year. • Labour and material costs are $ 6 000 per year. • Requires $72 000 in fixed assets (initial outlay) with expected salvage of $5 000 at the end of the project (depreciate straight-line). • Tax rate = 30% • Required return = 20% continued
Example—Setting the bid price Solution: • Step 1: Find the net initial outlay • Step 2: Find the cash inflows (CFs) over the life of the project that makes NPV zero. continued
Example—Setting the bid price • Assuming that the CF is the same for each year and that it occur at the end of each year, we can write: continued
Example—Setting the bid price • Step 3: Find the sale price that gives a cash inflow of $27 161 per year. Cash inflow = Profit + Depreciation $27 161 = Profit + ($72 000/4) Profit = $27 161 − $18 000 = $9 161 We know: Profit = (Sales − Costs − Depreciation)(1 − TC) Sales = $9 161/0.70 + $120 000 + $18 000 = $151 087 Sales per truck = $151 087 / 5 = $30 218
Setting the option value • A buy option is an arrangement that gives the holder the right to buy an asset at a fixed price sometime in the future. Option value = Asset value × Probability of the value – Present value of the exercise price × Probability the exercise price will be paid
Annual equivalent cost (AEC) • When comparing two mutually-exclusive projects with different lives, it is necessary to make comparisons over the same time period. • AEC is the present value of each project’s costs calculated on an annual basis. • NPVs are calculated, and then converted to AECs using the relevant PVIFA (present value interest factor for annuities). • Select the project with the lowest AEC.
Example—AEC • Project A costs $3 000, and then $1 000 per annum for the next four years. • Project B costs $6 000, and then $1 200 for the next eight years. • Required rate of return for both projects is 10 per cent. • Which is the better project?
Solution—Interpretation ‘Project A is better, because it costs $1 946 per year compared to Project B’s $2 325 per year’.
Annual equivalent benefit (AEB) • The AEB is used when comparing projects with cash inflows and outflows, but with unequal lives. • The steps required to calculate the AEB are the same as those used for AEC. • Select the project with the highest AEB.
Quick quiz • How do we determine if cash flows are relevant to the capital budgeting decision? • What are the different methods for computing operating cash flow, and when are they important? • What is the basic process for finding the bid price? • What is equivalent annual cost, and when should it be used?
Summary and conclusions • Discounted cash flow (DCF) analysis is a standard tool in the business world. • The information provided for a specific decision may be complex; however, the analysis reduces to three distinct steps: Step 1 Calculate the taxable income Step 2 Calculate the cash flows relevant to the decision Step 3 Discount the cash flows to make the decision. • Cash flows should be identified in a way that makes economic sense.