1 / 27

I-80 db

I-80 db. I-80 DB Location & Scope. 10 miles on I-80 from Robb Dr. to Vista Blvd. Reconstruction through congested downtown Installation of new 10-mile ITS system Preserved Operational Capacity. I-80 DB Why Design Build?. Accelerate Schedule Innovation Pavement Traffic Operations

haines
Download Presentation

I-80 db

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. I-80 db

  2. I-80 DB Location & Scope • 10 miles on I-80 from Robb Dr. to Vista Blvd. • Reconstruction through congested downtown • Installation of new 10-mile ITS system • Preserved Operational Capacity

  3. I-80 DB • Why Design Build? • Accelerate Schedule • Innovation • Pavement • Traffic Operations • Public Outreach

  4. I-80 DB • Procurement Strategy • Fixed Scope; Lump Sum Price Centers • Evaluation Criteria • 50% Price • 40% Technical • 10% Schedule • Pre-Proposal for Pavement Design • $50K/day early completion incentive

  5. I-80 DB Schedule • Construction began 3 months after NEPA approval • Impacts of Early Completion Incentive • At-Risk Early Start • Completed construction 6 months ahead of original DB schedule

  6. I-80 DB Risk Transfer • Subsurface Conditions • 3rd Party Coordination • Utility Relocation • Public Outreach

  7. I-80 DB • Risk Transfer Leads to Innovation

  8. I-80 DB Innovation • 67 Different ATC’s – 10 Used • Maintenance of Traffic • Auxiliary Lanes • Ramp Meters

  9. I-80 DB Lessons Learned • Aesthetic Concepts/Design • Develop concepts in advance • More prescriptive specs • Soft Subgrade Conditions • Risk is difficult to transfer • Communicate during procurement • Conditional ATC’s • Competing interests • Impacts to acceleration

  10. West Mesquite DB

  11. West Mesquite • Location & Scope • Downtown Mesquite, NV • Replace Diamond Interchange with Roundabouts at Ramp Terminals • Replace Bridges on I-15

  12. West Mesquite • Why Design Build? • Speed of Delivery • Opportunity for Innovation • Reduce Impacts to I-15

  13. West Mesquite • Procurement Strategy • Fixed Scope & Variable Price • Evaluation Criteria • 60% Price • 30% Technical • 10% Schedule • Limit the lane closures on I-15

  14. West Mesquite Schedule • Construction began 1 month after NEPA approval • Completed construction 6 months ahead of engineer’s estimated schedule • 3 months ahead of other Proposers

  15. West Mesquite Risk Transfer • 3rd Party Coordination • Utility Relocation • Public Outreach

  16. West Mesquite Innovation • 30 Different ATC’s – 4 Used • Accelerated Bridge Construction (ABC) • Bridge slide – limited disruption to I-15

  17. West Mesquite Bridge Slide

  18. West Mesquite Lessons Learned • Specifications for Innovation • Hollow Nail Walls • Bridge Deck Quality • Remediation requirements • Innovation & Small DB Projects • Bridge Slide great example

  19. I-15 ITS Design-Build

  20. I-15 ITS Location & Scope • 15 miles of I-15 - South of Las Vegas • Installation of a new ITS system • Integration with RTC’s Freeway and Arterial System of Transportation (FAST)

  21. I-15 ITS • Why Design Build? • Innovation • Technology Expertise • Immediate Need • Minimize traffic impacts

  22. I-15 ITS • Procurement Strategy • Fixed Scope; Lump Sum Price • Evaluation Criteria • 65% Technical • 35% Price • $5k per day early completion incentive

  23. I-15 ITS Schedule • Construction began 1 month after NEPA approval • System was operational 9 months ahead of Bid-Build scenario

  24. I-15 ITS Risk Transfer • 3rd Party Coordination • Utility Relocation • Public Outreach

  25. I-15 ITS Innovation • 10 Different ATC’s - 1 Used • Combination of Wireless & Fiber solutions

  26. I-15 ITS Lessons Learned • Keeping up with Technology • Resources with experience • Evaluating new products • Aligning vendor spec’s/products • Warranties • Consistency among projects

  27. How is Design Build Working for NDOT? • Schedule • Risk Transfer • Innovation

More Related