Selkirk Parish Church (SC014883) PV project

Selkirk Parish Church (SC014883) PV project. David Bethune. Why bother?. Where next?. Stage 1: Initial proposal (2009). sketches congregational board design costs. Design: 40 x 180Wp modules Coverage 53.5 m 2 Capacity 7.2 kWp Predicted annual output: 5,575 kWh

hall-sharpe
Download Presentation

Selkirk Parish Church (SC014883) PV project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SelkirkParish Church(SC014883)PV project David Bethune

  2. Why bother?

  3. Where next?

  4. Stage 1: Initial proposal (2009) • sketches • congregational board • design • costs

  5. Design: • 40 x 180Wp modules • Coverage 53.5 m2 • Capacity 7.2 kWp • Predicted annual output: 5,575 kWh • Cost £31K (+scaffolding, electrical connection) • predicted saving £2.5K per annum • payback time c12 years

  6. Design:

  7. inverter (in roof space) • direct connection to existing supply • generation meter (with display) • no moving parts = minimal maintenance

  8. Stage 2: Permissions (2010) • congregational board • planning permission • listed building • general trustees

  9. Stage 3: Funding (2010) £34K • LCBP2e 50% • E-on Source Fund • Scottish Power Green Energy Fund • EDF Green Fund

  10. Stage 4: Decision (Dec 2010) • LCBP2e 50% • loan from General Trustees • £5,700 from own funds

  11. Installation (Feb 2011)

  12. complete!

  13. Was it worth it?

  14. after 8 months ….

  15. Financially: heading towards c7000 Units per annum = £3530 from FiTs + £105 from export + ?£500 reduced bills = £4000+ per annum benefit

  16. Environmentally: > 3 tonnes CO2 per annum less If all 2000 churches …. …. 6 kilo tonnes saving!

  17. a success! • significant financial benefit • significant environmental benefit • a visual sign to our community • encouraging others • members houses • manses • community buildings

  18. It’s good stewardship!

  19. Thanks for listening! David Bethune david@dbethune.com 01750 21703