WER Clarity Migration Plan

WER Clarity Migration Plan. As of 11/14/2011 Doug Smith. Overview of the Four Phases. WER Dev Refresh completes 11/22/2011 Migration WER Dev to CSIT/UAT 1/10/2012 Production 1 (inactive data) 1/19/2012 Production 2 (active data) 2/14/2012

hanae-rivas
Download Presentation

WER Clarity Migration Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WER Clarity Migration Plan As of 11/14/2011 Doug Smith

  2. Overview of the Four Phases • WER Dev Refresh completes 11/22/2011 • Migration WER Dev to CSIT/UAT 1/10/2012 • Production 1 (inactive data) 1/19/2012 • Production 2 (active data) 2/14/2012 • Staff is committed part time as available and daily production responsibilities will have priority

  3. Refresh WER Dev • Refresh Dev from WER Prod with comparison of MSP, financials and reports • Testing includes the rebuilding of the “stored” MS project plans • Completes on 11/22/2011

  4. WER Dev migration to CSIT Staging • Assumptions: Dev refresh testing completes on 11/22 • Thanksgiving blackout 11/23 to 11/27- no work • Migration 11/28-12/8, UAT 12/8-12/16 resuming 1/2/2012-1/10/2012

  5. WER UAT Details • After data is moved to CSIT staging, WER UAT proceeds • UAT stops 12/16 when resources go on PTO and restarts in 1/2 and completes 1/10

  6. Production Phase 1 – inactive data • No outage is involved • Migration of inactive data

  7. Production Phase 2 –active data • The Production migration of active data has a 3 day outage on 2/9 – 2/11 for both WER and WWC environments • Validation to be performed by all Business Unit Clarity Functional admins on 2/12 • In service Monday 2/13

  8. Final day activities - details • By 3pm on 2/12 production validation starts for validation WER, WHG and WVO • By 8pm on 2/12 final go/no go

  9. Proprietary Content • Proprietary Content Omitted