An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Brigham Young University Provo City Council Neighborhood Symposium January 29, 2013

  2. Existing Conditions

  3. Main Items of Work: • New pedestrian plaza between Law Building and Wilkinson Center • Additional parking near Harris Fine Arts Center • Improved pedestrian access through parking lots • Convenient drop-off access in front of Wilkinson Center • Schedule: • Construction begins May 1 • Substantial completion by August 15 Phase 1 Work Zone

  4. Traffic Impacts: • Permanent closure of East Campus Drive south of Heritage Drive Phase 1 Permanent Closure

  5. Traffic Impacts: • Permanent closure of East Campus Drive south of Heritage Drive • Lane restrictions and partial closures during Phase 1 construction Phase 1 Lane Restrictions

  6. Phase 1 Completed

  7. Main Items of Work: • New sidewalk on south side of 1230 North • Improved intersection at 450 East • New pedestrian drop-off at Hinckley Center • Schedule: • Construction to begin summer of 2014 Phase 2 Work Zone

  8. Traffic Impacts: • Lane restrictions during construction Phase 2 Work Zone

  9. Phase 2 Completed

  10. Main Items of Work: • New roundabout entry north of the Administration Building • Additional parking near the Museum of Art • Improved pedestrian access from student housing to central campus • Schedule: • Construction to begin summer of 2015 Phase 3 Work Zone

  11. Traffic Impacts: • Permanent closure of East Campus Drive/Heritage Drive intersection. Phase 3 Work Zone

  12. Phase 3 Completed

  13. End of Construction